IRON EAGLE DEVELOPMENT, LLC. v. Quality Design Systems, Inc.

65 P.3d 509, 138 Idaho 487, 2003 Ida. LEXIS 32
CourtIdaho Supreme Court
DecidedFebruary 27, 2003
Docket27755
StatusPublished
Cited by42 cases

This text of 65 P.3d 509 (IRON EAGLE DEVELOPMENT, LLC. v. Quality Design Systems, Inc.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IRON EAGLE DEVELOPMENT, LLC. v. Quality Design Systems, Inc., 65 P.3d 509, 138 Idaho 487, 2003 Ida. LEXIS 32 (Idaho 2003).

Opinion

KIDWELL, Justice.

Iron Eagle Development, L.L.C. (Iron Eagle) and Heartland, L.L.C. (Heartland) appeal from an order granting summary judgment in favor of Quality Design Systems, Inc. (Quality Design) for breach of a “build to suit” lease. We affirm the judgment of the district court.

*490 I.

FACTS AND PROCEDURAL BACKGROUND

In late 1999, Quality Design and Iron Eagle negotiated a contract to lease an office building to be built to Quality Design’s specifications. The office building was to be built in the Rocky Mountain Business Park in Eagle, Idaho. Quality Design sought a new building to relocate its operations because its lease was to expire on October 31, 2000. On December 20, 1999, Quality Design and Iron Eagle executed a contract to lease a building not yet built.

Heartland, a construction company known to both parties, was not a party to the contract and was not designated as the general contractor in the contract other than a statement that the building would be built per drawings provided by Heartland. However, both Iron Eagle and Quality Design understood that Iron Eagle would employ Heartland’s services to build the facility. As a result, two separate contracts existed. First, Quality Design and Iron Eagle entered into a contract whereby Quality Design was to lease a building built to its specifications from Iron Eagle. Second, Iron Eagle and Heartland entered into an agreement for Heartland to construct the building that Iron Eagle was going to lease to Quality Design. Quality Design was not a party to the second agreement.

Quality Design informed Iron Eagle that it needed to move into the new building no later than August 2000 in order to avoid disruption of its business. Iron Eagle informed Quality Design that the building process would take five to six months. The contract provided neither a beginning date for construction nor a move in date; rather, the lease was to begin upon occupancy, defined in the contract as “substantial completion and occupancy allowed by the City of Eagle.”

In early April 2000, Quality Design contacted Iron Eagle regarding the status of the project. Iron Eagle informed Quality Design that the City of Eagle had yet to issue any permits, but that the permits would be issued soon. Iron Eagle also informed Quality Design it had not yet obtained financing. Iron Eagle advised Quality Design that in order to obtain financing, Quality Design’s president needed to sign a personal guarantee, the lease would have to be changed to triple net terms, and Quality Design would have to release its option to purchase. Quality Design refused Iron Eagle’s requested modifications.

On April 10, 2000, Heartland informed Quality Design it would be ready to move forward on construction of the site on April 13, 2000. Quality Design advised Heartland to hold off because it was going to look for alternative properties to lease. As of April 13, 2000, Heartland had yet to obtain the necessary building permits for the project. On April 13, 2000, Quality Design advised Iron Eagle it would proceed with the contract to lease the yet to be constructed building if: (1) the contract’s original terms were honored; (2) it was provided a construction schedule establishing a move in date of August 2000; (3) and Iron Eagle provided proof of financing. On April 18, 2000, Heartland provided Quality Design with a letter from Home Federal Savings and Loan (Home Federal) stating Home Federal could not yet commit to the project, but its preliminary review for financing was positive. Quality Design then informed Iron Eagle it would not lease the build to suit facility.

On April 26, 2000, Quality Design advised Iron Eagle, in writing, it would be willing to lease the building if Iron Eagle provided adequate assurances: (1) of financing; (2) that Quality Design would have no obligations for financing to be obtained; (3) that Quality Design’s president would not be required to provide a personal guarantee; (4) the option to purchase would remain in the lease; (5) construction would be completed by the end of August 2000; and (6) that Iron Eagle post a performance bond in case of a construction delay. Iron Eagle refused to post a bond. Iron Eagle provided a construction schedule with a completion date of October 16, 2000. On May 12, 2000, Quality Design received a letter from the lender stating approval of the construction loan might occur within two or three days. However, as of that date, the City of Eagle had *491 not approved the necessary building permits. On May 26, 2000, not receiving all the adequate assurances it asked for, Quality Design leased a preexisting facility in Meridian.

On September 7, 2000, Iron Eagle and Heartland sued Quality Design for breach of an express contract, breach of an intended third party beneficiary contract, and equitable claims including unjust enrichment, quantum meruit, implied contract, quasi estoppel, and equitable estoppel.

On December 22, 2000, Quality Design moved for summary judgment. During a March 26, 2001 hearing, the district court granted partial summary judgment on the appellants’ express contract claims. In early April, each party filed motions to reconsider and the appellants filed a motion to set aside and/or amend the complaint. On April 6, 2001, the district court entered a written order of its partial summary judgment. In that same order, the district court also denied the appellants’ motion to amend.

On June 29, 2001, the district court entered a memorandum decision and order in which it granted Quality Design’s motion to reconsider and denied the appellants’ motion to reconsider. On July 10, 2001, the appellants filed a second motion to reconsider, asking the district court to consider the additional claims the appellants identified in their amended complaint. On August 9, 2001, the district court entered an order denying the appellants’ motions to reconsider and amend and granted Quality Design’s motion for final judgment. On September 27, 2001, following Quality Design’s motion for costs and fees, the district court entered an amended judgment awarding costs, fees, and post judgment interest to Quality Design. The appellants timely filed this appeal.

II.

STANDARD OF REVIEW

Summary judgment is proper when “the pleadings, depositions, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” I.R.C.P. 56(c) (2002). In a motion for summary judgment, this Court should liberally construe all facts in favor of the nonmoving party and draw all reasonable inferences in favor of the nonmoving party. Northwest Bec-Corp v. Home Living Serv., 136 Idaho 835, 838-39, 41 P.3d 263, 266-67 (2002). Summary judgment must' be denied if reasonable persons could reach differing conclusions or draw conflicting inferences from the evidence presented. Id.

A decision to grant or deny a motion to amend a complaint is discretionary. Trimble v. Engelking, 134 Idaho 195, 196, 998 P.2d 502, 503 (2000).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. Blast
Idaho Supreme Court, 2024
Golden v. Larsen
D. Idaho, 2023
Medrain v. Lee
462 P.3d 132 (Idaho Supreme Court, 2020)
DAFCO v. Stewart Title Guaranty Co
Idaho Supreme Court, 2014
DAFCO LLC v. Stewart Title Guaranty Co.
331 P.3d 491 (Idaho Supreme Court, 2014)
Thomas Ulrich v. John Bach
308 P.3d 1232 (Idaho Supreme Court, 2013)
Buku Properties v. Raoel H. Clark
291 P.3d 1027 (Idaho Supreme Court, 2012)
Tanner Mickelsen v. Broadway Ford, Inc.
280 P.3d 176 (Idaho Supreme Court, 2012)
McCann v. McCann
275 P.3d 824 (Idaho Supreme Court, 2012)
Watson v. Watson
159 P.3d 851 (Idaho Supreme Court, 2007)
Mannos v. Moss
155 P.3d 1166 (Idaho Supreme Court, 2007)
Oldcastle Precast, Inc. v. Parktowne Construction, Inc.
128 P.3d 913 (Idaho Supreme Court, 2005)
Neibaur v. Neibaur
125 P.3d 1072 (Idaho Supreme Court, 2005)
State v. Porter
128 P.3d 908 (Idaho Supreme Court, 2005)
Sorensen v. Saint Alphonsus Regional Medical Center, Inc.
118 P.3d 86 (Idaho Supreme Court, 2005)
State v. Korsen
111 P.3d 130 (Idaho Supreme Court, 2005)
Rahas v. Ver Mett
111 P.3d 97 (Idaho Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
65 P.3d 509, 138 Idaho 487, 2003 Ida. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iron-eagle-development-llc-v-quality-design-systems-inc-idaho-2003.