OPINION BY
KELLY, J.:
Appellant/Plaintiff, Ira G. Steffy & Son, Inc., appeals from the order entered in the
Lehigh County Court of Common Pleas sustaining the preliminary objections of Appellee/Defendant, Citizens Bank of Pennsylvania, and dismissing Appellant’s amended complaint. After an extensive review of the record, we affirm the trial court’s opinion, finding that Appellant, a subcontractor who was not paid for work performed on a project after Appellee bank failed to release construction funds to the developer, has failed to state a claim for relief against Appellee.
Appellant’s amended complaint, filed on June 9, 2009, averred that pursuant to the terms of a construction loan agreement (CLA) that was executed on December 3, 2007, Appellee agreed to loan Macungie Crossings I, L.L.C,
(Macungie) $35,900,000 to construct a warehouse (the Project) on a tract of land in Lehigh County, Pennsylvania. As part of the agreement, Macungie mortgaged the property to Appellee. Opus East, LLC (Opus) was hired as the general contractor.
On February 20, 2008, Opus executed a subcontract with Appellant to perform structural metal work in exchange for payment of approximately $3,000,000.
Beginning in February of 2009, Opus materially breached the subcontract agreement by failing to make monthly progress payments to Appellant. Appellant claimed that it had substantially completed its work by March 10, 2009, but it was “prevented” from finishing due to Opus’ lack of payment. (Amended Complaint, at ¶ 12). “In numerous communications with Opus and Macungie,” Appellant was “advised” that progress payments were not made because Appellee wrongfully refused to advance money to Macungie under the CLA.
(Id,.,
at ¶ 13).
Specifically, on March 23, 2009, Brian Grindall of Opus indicated that [Appel-lee] had failed to release any funds for the January, 2009 draw request, even though Macungie was not in default under the [CLA]. Upon [Appellant’s] information and belief, [Appellee] has failed to release any funds for any work performed in February, 2009, or thereafter.
(Id.).
Appellant argued that “by entering into the [CLA] and causing the mortgage and note to be filed[, Appellee] represented ... that there would be funds of up to $35,-900,00[] available to complete the construction!,]” and Appellant acted in reasonable reliance upon this representation when it entered into the subcontract with Opus.
(Id.,
at ¶¶ 25, 26). Thus, Appellee, “acting with full knowledge” that its “wrongful withholding of funds” would “jeopardize!]” Opus’ subcontracts and cause Macungie to default under the CLA, would be unjustly enriched if it were able to seize the property through foreclosure without having paid the fair and reasonable value for it.
(Id.,
at ¶¶ 14-15). Because “more than sufficient [CLA] funds remain[ed] ... to complete the Project!,]” Appellant requested that a constructive trust be imposed on the remaining funds for the value of its unpaid labor and materials.
(Id.,
at ¶¶ 22-23). Appellant also
sought relief under theories of fraudulent misrepresentation, intentional interference with contractual relations, and breach of contract as a third-party beneficiary.
Pursuant to Pa.R.C.P. 1028(a)(4), Appel-lee filed preliminary objections on July 2, 2009. First, Appellee asserted that Appellant failed to show how the withholding of funds was unjust, because “[Appellee] has merely acted within its rights under the [l]oan [documents so as to best protect its own financial interests.” (Preliminary Objections, 7/2/09, at ¶8). Appellee claims that Macungie was in default under the terms of the CLA,
and commenced foreclosure on the property.
Appellee further responded that Appellant failed to plead the requisite elements for claims of misrepresentation, intentional interference with contractual relations, or breach of contract as a third-party beneficiary. The trial court sustained Appellee’s preliminary objections and dismissed Appellant’s action in its entirety on August 7th.
On appeal, Appellant claims that the trial court erred in sustaining Appel-lee’s preliminary objections where its amended complaint stated a claim for: (1) unjust enrichment, and as such, imposition of a constructive trust; (2) breach of the CLA, of which it was a third-party beneficiary; (3) intentional interference with its subcontract with Opus; and (4) misrepresentation.
When reviewing the dismissal of a complaint based upon preliminary objections in the nature of a demurrer, we treat as true all well-pleaded material, factual averments and all inferences fairly deducible therefrom. Where the preliminary objections will result in the dismissal of the action, the objections may
be sustained only in cases that ai’e clear and free from doubt. To be clear and free from doubt that dismissal is appropriate, it must appear with certainty that the law would not permit recovery by the plaintiff upon the facts averred. Any doubt should be resolved by a refusal to sustain the objections. Moreover, we review the trial court’s decision for an abuse of discretion or an error of law.
Burgoyne v. Pinecrest Community Ass’n,
924 A.2d 675, 679 (Pa.Super.2007).
Where one party has been unjustly enriched at the expense of another, he is required to make restitution to the other. In order to recover, there must be both (1) an enrichment, and (2) an injustice resulting if recovery for the enrichment is denied....
[[Image here]]
Section 110 [of the Restatement of Restitution] deals with the situation where a third party benefits from a contract entered into between two other parties. It provides that, in the absence of some misleading by the third party, the mere failure of performance by one of the contracting parties does not give rise to a right of restitution against the third party.
Meehan v. Cheltenham Township,
410 Pa. 446, 189 A.2d 593, 595-96 (1963) (emphasis added).
In
D.A. Hill Co. v. Clevetrust Realty Investors,
524 Pa. 425, 573 A.2d 1005 (1990), our Supreme Court has addressed unjust enrichment claims brought by a subcontractor against a third-party lending institution. In
D.A. Hill,
an investment company provided a construction loan, secured by a mortgage, to a developer to build a shopping mall.
Id.
at 1006. The developer hired a general contractor, who in turn hired the plaintiff as a subcontractor.
Id.
After construction began, the development company defaulted on its loan by failing to make a mandatory interest payment.
Id.
at 1007. In accordance with its rights under the loan agreement, the investment company refused to disburse additional funds, the general contractor received no money, and the subcontractor was left without compensation for its work.
Id.
Eventually, the investment company foreclosed on the property.
Id.
The plaintiff subcontractor then brought suit against the investment company on the theory that the investment company had been unjustly enriched by the subcontractor’s work.
Id.
at 1008.
The Pennsylvania Supreme Court found that in order to prevail, the subcontractor would have had to demonstrate that the investment company was enriched, and that such enrichment was unjust.
Id.
at 1009. Enrichment is “measured by the value of the benefit to the owner,
not by the value of the invoice submitted by the subcontractor.”
Id.; see also Meehan, supra
at 595 (subcontractor “cannot merely allege its own loss as the measure of recovery — i.e., the value of labor and materials expended — but instead must demonstrate that the owner has in fact benefited.”);
Gee v. EBerle,
279 Pa.Super. 101, 420 A.2d 1050, 1062 (1980) (benefit of subcontractor’s work to owner can be demonstrated by price of property at foreclosure sale). Furthermore, the enrichment would only be considered unjust if the owner had requested the benefit, contracted directly with, or misled the subcontractor.
D.A. Hill, supra
at 1009, 1010. The Court ruled in favor of the investment
company, finding that the subcontractor failed to establish the existence of a benefit at the time of foreclosure.
Id,.,
at 1010. The Court explained its decision:
The legislature in Pennsylvania has by statute provided the mechanics’ lien as a means by which a contractor or subcontractor can obtain security for work done. Other security can be acquired by contract.... [A] court should not rewrite the contract of the parties or legislate a right to receive payment from a mortgagee who has been compelled to go into possession to preserve its security. Such a rule would do much to impair the availability of capital upon which the building industry so greatly depends.
Id.
at 1010 n. 5 (quoting
Myers-Macomber Engineers v. M.L.W. Constr. Corp.,
271 Pa.Super. 484, 414 A.2d 357, 361 (1979)). Additionally, we find the recent comments made by the United States District Court for the Eastern District of Pennsylvania
on this issue illuminating:
A contrary rule allowing subcontractors to recover directly from owners in other circumstances would destroy the balance of contractual relationships in the construction industry and reverse the public policy of Pennsylvania as articulated by the Supreme Court....
* * *
... As
D.A. Hill
makes clear, the conferral of a benefit is a necessary, but not sufficient, condition of a valid unjust enrichment claim. “The doctrine does not apply simply because the defendant may have benefit[t]ed as a result of the actions of the plaintiff.”
[Styer v. Hugo,
422 Pa.Super. 262, 619 A.2d 347, 350 (1993) (citing
D.A. Hill, supra), aff'd
535 Pa. 610, 637 A.2d 276 (1994) ]. In order to avoid dismissal of the unjust enrichment claim, [the plaintiff] must allege in its complaint facts showing that the defendants specifically requested benefits or misled [the plaintiff].
Goldsmith Assocs. v. Del Frisco’s of Phila., Inc.,
2009 WL 3172752, 5, 2009 U.S. Dist. LEXIS 92193, 13-15 (E.D.Pa. Oct. 1, 2009) (some citations omitted).
In the instant case, Appellant argued that its work on the Project had increased the value of the property, and Appellee will be unjustly enriched if it “seize[s] the benefit ... without having paid the fair and reasonable value therefore.” (Amended Complaint, at ¶ 14). On appeal, Appellant claims that the trial court erred in holding that a partially-completed project cannot be the source of unjust enrichment to a lender.
{See
Trial Ct. Op., 8/7/09, at 7) (“A partially completed project does not yield a lender all that it bargained for in terms of security. Hence, in such circumstances, it cannot be deemed unjustly enriched when the specter of additional, and perhaps, indeterminate payments remain in the offing in order to protect its collateral.”) Appellant argues that in so holding, the trial court either made an unlawful finding of fact at the pleadings stage, that is, that indeterminate payments were left to be made, or erred as a matter of law pursuant to
Gee, supra
at 1057 n. 5.
While we agree with Appellant that the trial court may have made an improper finding of fact, we affirm its order of dismissal on other grounds.
Nationwide Mut. Ins. Co. v. Fleming,
924 A.2d 1259, 1269 n. 5 (Pa.Super.2007) (we may uphold decision of trial court if there is any proper basis for result reached),
aff'd,
992 A.2d 65 (Pa.2010). Regarding the “enrichment” prong, we find that Appellant’s pleadings are not “clear and free from doubt.”
See Burgoyne, supra.
However, this finding is not based on the alleged value of the unpaid labor and materials or the degree to which the work was completed. Rather, it is based on both parties’ presentation of evidence that Appellee had commenced foreclosure proceedings on the property, and that default judgment was entered against Macungie. Had discovery in this case been allowed, Appellant would potentially be able to show that Appellee was enriched by its work, if the value of the property seized at foreclosure exceeded the amount advanced.
Yet even if Appellant could show enrichment, it did not plead facts showing that any such enrichment would be unjust.
See D.A. Hill, supra
at 1010. Indeed, regarding the “unjust prong,” Appellant has failed to demonstrate that it had either the requisite contractual relationship with Appellee
or was misled by Appellee.
See id.
Appellant was not a party to Appellee’s Construction Loan Agreement (CLA) with Macungie, and Appellee was not a party to Appellant’s subcontractor agreement with Opus. Pursuant to the pleadings, the only interaction that Appellant had with Appel-lee was on April 2, 2009, when it sent a letter to Appellee regarding Opus’ missed payments.
(See
Amended Complaint, Exh. E at 1). No response to this letter was included in the record.
Appellant repeatedly points to section 7.1(a) of the CLA, where Appellee reserved the right to make direct payments to subcontractors, should it choose to, as evidence of a contractual relationship between the two parties.
(See, e.g., id.,
at ¶ 3). We find Appellant misreads this paragraph. While section 7.1(a) allows for direct payments to be made, it specifically disclaims the formation of any contractual relationship as a result of these payments:
Loan proceeds may be paid directly by [Appellee] to the Contractors[
due them on account of work performed and/or materials furnished.... These direct payments shall not create any privity of contract, trustee, beneficiary, or guai'antor (surety) relationship of any kind between said parties and [Appel-lee].
(Id.,
Exh. A § 7.1(a)) (emphasis added). As such, Appellant has failed to set forth any evidence to suggest that it had a direct contractual agreement with Appellee, or that Appellee requested a benefit from it.
Furthermore, Appellant has not set forth sufficient facts that would warrant an inference that it was misled by Appellee.
In its amended complaint, Appellant asserted that “[b]y entering into the [CLA] and causing the mortgage and note to be filed of record, [Appellee] represented to all parties interested in the Project that there would be funds of up to $35,900,00[ ] available to complete the construction,” and that Appellee intended for the subcontractors to rely upon this representation.
(Id.,
at ¶ 25). However, the purpose of recording a mortgage is to provide notice that the property in question is encumbered; it does not amount to a positive guarantee that funds will be released by the lender.
US Bank N.A. v. Mallory,
982 A.2d 986, 994 n. 6 (Pa.Super.2009) (“Mortgages are recorded to provide notice to the world as to whose interest encumbers title.”)
While Appellant argues that Appellee violated the CLA by withholding funds even though Macungie was not in default, the only evidence it offers in support of this contention is that it learned of this information from an Opus representative.
(See
Amended Complaint,, at ¶ 13). Moreover, even if Appellant could prove Appel-lee’s alleged misconduct, it does not' have standing to challenge this behavior.
This Court faced a similar set of facts in
R.M. Shoemaker Co. v. Southeastern Pennsylvania Economic Development Corp.,
275 Pa.Super. 594, 419 A.2d 60 (1980), where a general contractor attempted to show that the owner of the property was not insolvent at the time the lending institution refused to advance funds under the construction loan. This Court found the contractor’s claim unpersuasive, because the owner
has not challenged [the lender’s] refusal to advance moneys, and [the contractor] acquired no rights under the loan agreement. Therefore, even if [the owner] had been solvent and [the lender] had been in violation of the loan agreement by refusing to advance money, only [the owner] could complain of [the lender’s] breach. [The contractor] was not a party to the agreement and had no standing to enforce it by legal action.
Id.
at 63.
Similar to the contractor in
R.M. Shoemaker Co.,
Appellant had acquired no rights under the loan agreement between Appellee and Macungie. As such, Appellant has no standing to complain of a breach of that agreement by Appellee. Such a challenge is within the province of Macungie, who, according to the pleadings, was found to be in default and consented to Appellee’s motion to appoint a receiver.
(See
Response to Preliminary Objections, at Exh. A n.1).
While Appellant has presented a potential claim for enrichment, it has failed to state a claim that such enrichment would be unjust. Accordingly, we find that the trial court did not abuse its discretion in sustaining Appellee’s preliminary objections pursuant to Appellant’s claim for unjust enrichment.
In addition, Appellant argues that the CLA establishes that subcontractors are intended third-party beneficiaries of the agreement. However, we agree with the trial court’s finding that this claim is without merit.
(See
Trial Ct. Op., at 7).
To be considered a third-party beneficiary in [Pennsylvania] it is necessary to
show both parties to the contract had an intent to benefit the third party through the contract and did, in fact, explicitly indicate this intent in the contract.
Strutz v. State Farm Mut. Ins. Co.,
415 Pa.Super. 371, 609 A.2d 569, 570 (1992) (citations omitted) (emphasis added),
appeal denied,
532 Pa. 657, 615 A.2d 1313 (1992). Nowhere in the CLA does Appel-lee or Macungie show an intent to make Appellant a third-party beneficiary to the agreement. To the contrary, the terms of the CLA show that its drafters specifically rejected the idea of subcontractors as third-party beneficiaries.
As noted above, section. 7.1(a) of the CLA gave Appellee the right to make direct payments to subcontractors, but expressly states that no beneficiary relationship shall result from these payments. (Amended Complaint, at Exh. A § 7.1(a)). Even more telling is section 10.4 of the CLA, entitled “No Third Parties Benefit-ted[,]” which states that “[n]o part of the Loan proceeds will be at any time subject or liable to attachment or levy at the suit of ... any subcontractor [and n]o party is intended to be a third party beneficiary of the Loan proceeds or [the CLA].”
(Id.,
at Exh. A. § 10.4) (emphasis added). As such, the CLA demonstrates Appellee’s unambiguous intent to deny third-party beneficiary status to subcontractors.
Appellant cites to two cases,
Kreimer v. Second Federal Sav. & Loan
Asso., 196 Pa.Super. 644, 176 A.2d 132 (1961), and
In re Gebco Inv. Corp.,
641 F.2d 143 (3d Cir.1981),
in support of its argument that a construction loan agreement which permits a lender to make direct payments to a subcontractor evince an intent to convey a third-party beneficiary status upon the subcontractor. We first note that the agreement in
Kreimer, supra
at 133, unlike the agreement in the instant case, required the lender to make direct payments to the subcontractors. Furthermore, both cases are distinguished from the case
sub judice
because the agreements in neither
Kreimer
nor
Gebco
contained language that expressly disclaimed third-party beneficiary status. It is the practice of this Court to find against third-party beneficiary status when a construction loan agreement specifically disclaims an intent to confer such status on subcontractors.
See, e.g., Gee, supra
at 1055-56 n. 4 (express provision of agreement disclaimed intent to create third party beneficiary). Accordingly, we find that the trial court did not abuse its discretion in dismissing Appellant’s claim for breach of contract as a third-party beneficiary to the CLA.
Furthermore, we find that the trial court properly dismissed Appellant’s claim for relief under a theory of intentional interference with contractual relations.
The elements of a cause of action for intentional interference with a contractual relation, whether existing or prospective, are as follows:
(1) the existence of a contractual, or prospective contractual relation between the complainant and a third party;
(2) purposeful action on the part of the defendant, specifically intended to harm the existing relation, or to prevent a prospective relation from occurring;
(3) the absence of privilege or justification
on the part of the defendant; and
(4) the occasioning of actual legal damage as a result of the defendant’s conduct.
In determining whether a particular course of conduct is improper for purposes of setting forth a cause of action for intentional interference with contractual relationships, or, for that matter, potential contractual relationships, the court must look to section 767 of the Restatement (Second) of Torts. This section provides the following factors for consideration: 1) the nature of the actor’s conduct; 2) the actor’s motive; 3) the interests of the other with which the actor’s conduct interferes; 4) the interests sought to be advanced by the actor; 5) the proximity or remoteness of the actor’s conduct to interference, and 6) the relationship between the parties.
Strickland v. Univ. of Scranton,
700 A.2d 979, 985 (Pa.Super.1997) (citations omitted) (emphasis added).
Appellant has failed to state a claim for intentional interference with contract relations because it has not pleaded facts that would satisfy either the second or third prong of the test set forth in
Strickland.
First, Appellant did not allege any facts that would support the inference that Appellee withheld funds from Macun-gie under the CLA for the specific purpose of harming Appellant’s subcontract with Opus. Rather, Appellant merely contends that Appellee wrongfully refused to release funds under the CLA “with the full knowledge that [its] actions would cause Opus not to perform its payment obligations to [Appellant].” (Amended Complaint, ¶ 30). Although Appellee might have been aware that the withholding of funds would interfere with potential subcontracts, it does not follow that the actions were taken for this specific purpose. Furthermore, even if Appellee’s motive was, as Appellant claims, to seize the benefit of the substantially completed property without having paid a fair and reasonable price for it, then Appellee’s intent would be to interfere with the CLA between itself and Macungie; the state of Appellant’s relations with Opus would be irrelevant.
Second, we agree with the trial court that the nexus between Appellant and Appellee is “too attenuated for the action to fall within the ambit of tortuous interference with contractual relations.”
(See
Trial Ct. Op., at 11). Here, Appellee entered into loan agreement with Macun-gie for the purpose of constructing a warehouse. Appellant claims that Macungie then entered into a separate agreement with Opus to design and build the project, which in turn resulted in a separate subcontract between Opus and Appellant to provide structural metal work.
It simply cannot be said that the alleged conduct by [Appellee], which in no manner specifically targeted Opus, qualifies as purposeful action specifically intended to cause harm to [Appellant’s] contractual relations with that entity.... Were the rule otherwise, every garden variety breach-of-contract claim could be transformed into a tortious-interference allegation by a plaintiff who claims that an obligor on his contract has been rendered unable to perform as a consequence of a breach of some other contract to which the plaintiff was, in fact, not a party.
(Id.,
at 10-11).
Accordingly, we find that the trial properly dismissed Appellant’s claim for inten
tional interference with contractual relations.
Finally, we find that the trial court did not abuse its discretion in sustaining Appellee’s preliminary objections to Appellant’s claim of misrepresentation. The elements of fraudulent misrepresentation are as follows:
(1) A representation
(2) which is material to the transaction at hand;
(3) made falsely, with knowledge of its falsity or recklessness as to whether it is true or false;
(4) with the intent of misleading another into relying on it;
(5) justifiable reliance on the misrepresentation; and,
(6) the resulting injury was proximately caused by the reliance.
Heritage Surveyors & Eng’rs, Inc. v. Nat’l Penn Bank,
801 A.2d 1248, 1250-51 (Pa.Super.2002). Scienter, or the maker’s knowledge of the untrue character of his representation, is a key element in finding fraudulent misrepresentation.
See
Restatement (Second) of Torts § 526,
Comment a.
“It is well-established that the breach of a promise to do something in the future is not actionable in fraud.”
Shoemaker v. Commonwealth Bank,
700 A.2d 1003, 1006 (Pa.Super.1997).
Appellant alleged that
[b]y entering into the [CLA] and causing the mortgage and note to be filed of record, [Appellee] represented to all parties interested in the Project that there would be funds of up to $35,900,-000[ ] available to complete the construction. Further, upon information and belief, [Appellee] intended that subcontractors, such as [Appellant], rely upon [Appellee’s] representation that sufficient construction funds would be available.
(Amended Complaint, at ¶25). Appellant contended that it acted in reliance upon this representation in entering into the subcontract, and that, contrary to the representation, Appellee ceased funding the Project even though Macungie did not breach the CLA.
On the basis of the record before us, Appellant has failed to show that Ap-pellee made a material misrepresentation of fact. A loan agreement between a lender and a borrower, coupled with a recorded note and mortgage, is not a guarantee that such funds will be made available to all tangential parties involved. As stated above, “[mjortgages are recorded to provide notice to the world as to whose interest encumbers title[,]”
U.S. Bank N.A., supra,
not to guarantee that payments will be made by the lender. Furthermore, as previously indicated, Appellant failed to demonstrate any communication between itself and Appellee save for a letter sent to Appellee on April 2, 2009 regarding Opus’ missed payments. (Amended Complaint, Exh. E at 1). As such, Appellant’s complaint fails to show that Appellee made any kind of representation, let alone a misrepresentation, to Appellant.
Furthermore, as the trial court properly deduced, the essential element of scienter is lacking. Appellant “claims only that [Appellee] represented that money would be available, and then failed to perform on that promise without justification.” (Trial Ct. Op., at 4). However, Appellant has not contended that at the time Appellee entered into the CLA with Macungie, it knowingly misrepresented that money would be available in order to induce Appellant’s reliance. We find that the trial court did not abuse its discretion in sustaining Appellee’s preliminary objections to misrepresentation.
In sum, we find that Appellant has failed to state a claim for relief under theories of unjust enrichment, third-party beneficiary status, intentional interference with contractual relations, or misrepresentation. We therefore affirm the trial court’s order sustaining Appellee’s preliminary objections and dismissing Appellant’s complaint.
Order affirmed.