I&R Mechanical, Inc. v. Cutter Northern Refractories, Inc.

14 Mass. L. Rptr. 284
CourtMassachusetts Superior Court
DecidedDecember 17, 2001
DocketNo. 993354D
StatusPublished

This text of 14 Mass. L. Rptr. 284 (I&R Mechanical, Inc. v. Cutter Northern Refractories, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I&R Mechanical, Inc. v. Cutter Northern Refractories, Inc., 14 Mass. L. Rptr. 284 (Mass. Ct. App. 2001).

Opinion

Botsford, J.

This is an action for breach of contract related to work on a public construction project. The case was tried without a jury before me. Set forth below are my findings of fact based on the credible evidence introduced at trial. A discussion of the legal issues follows. For the reasons stated there, I conclude that the plaintiff has proved its claim of contract breach.

Findings of Fact

The plaintiff I&R Mechanical Inc. (I&R) is a mechanical contractor that performs heating, ventilating and air conditioning (HVAC) work on public construction projects. On March 12,1998, I&R filed a sub-bid to do HVAC work on a public construction project for renovations to the East Boston High School in Boston (the high school project). The plans and specifications for the high school project included repairs to the existing chimney as part of the HVAC work to be performed. The project was governed by the public bidding laws, and I&R’s sub-bid was required to comply with G.L.c. 149, §44F. As part of its filed sub-bid, I&R was required to list the companies that I&R proposed to supply labor or materials, including the work involving existing chimney repairs.

Cutter Northern Refractories, Inc. (Cutter Northern) is a refractory contractor engaged in work that involves structures such as chimneys that are subject to temperatures in excess of 1500 degrees Fahrenheit; Cutter Northern fabricates, redesigns, rebuilds and repairs such structures. On March 11, 1998, the day before the high school project sub-bids were due, Keith Price of I&R contacted Brian Lenihan of Cutter Northern to solicit a bid on the chimney repair work.1 Lenihan is the vice president for construction of Cutter Northern. Price told Lenihan he needed a bid that day for the chimney repair work portion of the HVAC work on the high school project, explained he needed to file such a bid, and faxed to Lenihan a copy of the two pages from the project specifications that concerned the chimney repairs. Price also told Lenihan that Cutter Northern would need to supply the staging for the job. The same day, Lenihan faxed back a response to I&R which stated in part:

Subject: East Boston High School, Chimney Repairs
Cutter Northern Refractories is please to submit our proposal to supply all labor, material and supervision necessary to accomplish the attached scope of work.
Cutter Northern Refractories price for this work: $15,640.00
Payment terms are 30% with purchase order, balance net 30 days.
Cutter Northern will supply all staging necessary.
Price does not include state, local, or federal taxes.
Please call me if you have any questions. Thank you for thinking of Cutter Northern for your refractory needs.
Sincerely,
Brian T. Lenihan
Vice President of Construction

[285]*285(Emphasis in original.) Attached to this one-page letter was a separate page describing the scope and nature of work that Cutter Northern was offering to perform. Lenihan knew that he was submitting a bid proposal for work on a public high school renovation project, and although Price did not tell him explicitly that this was a public construction project governed by the public bid construction laws, Lenihan acknowledged that he had some experience with public construction projects and with filed sub-bids in particular. I infer that Lenihan knew or understood that the East Boston High School project was a public construction project, and that I&R might well use Cutter Northern’s bid proposal in its filed sub-bid for the HVAC work on the project.2

I&R filed its sub-bid for the HVAC work on March 12, 1998. Cutter Northern was included within the bid as the company that would perform the chimney repair work for the listed price of $15,640.00. I&R’s total sub-bid for the work came to $2,130,000.00. I&R did not notify Cutter Northern that it was being included in I&R’s sub-bid.

For reasons not relevant to this case, the City of Boston rejected all the sub-bids on the high school project, and thereafter put the project out to bid again. The new due date for all sub-bids was May 29, 1998.3

At some point during the week before May 29, Keith Price of I&R called Brian Lenihan of Cutter Northern and asked if Cutter Northern’s bid for the chimney repair work would be the same as before. Lenihan responded that so long as there were no changes to the work at issue, the quoted figures would remain the same. Lenihan had not inspected the East Boston High School site at that time.4

On May 28, 1998 — around the same time as his May conversation with Keith Price — Lenihan also submitted a written proposal concerning the chimney repair work for the high school project to another HVAC subcontractor called Enterprise Equipment Co., Inc. Lenihan listed in the Enterprise proposal the same price of $15,640.00 for the work, although the proposal did not include a condition about payment of 30% of the price “with purchase order” and was silent on the subject of staging.5 As was true of the written bid proposal to I&R, however, the written proposal to Enterprise Equipment did not contain a condition that it was subject to a site inspection, and Lenihan did not state orally to Enterprise Equipment that the proposal was conditioned on such an inspection.

Neither Brian Lenihan nor any other person associated with Cutter Northern had inspected the East Boston High School site before submitting the proposal to I&R in March 1998, or before confirming the proposal in May 1998. Keith Price of I&R also had not inspected the site by the time of the second filed sub-bid on May 29, 1998. Before each of the due dates for the sub-bids, there had been two scheduled dates for subcontractors to visit the site, but Cutter Northern was not made aware of these dates.

On May 29, 1998, I&R resubmitted its sub-bid for the HVAC work at a lower total price of $2,064,000.00. I&R again included Cutter Northern as the entity that would perform the required chimney repair work at the price of $15,640.00.

I&R was awarded the HVAC subcontract on the high school project. InAugust 1998, I&R sent Cutter Northern a proposed contract form for the chimney repair work. Cutter Northern did not sign the contract. Keith Price attempted to contact Lenihan, and finally reached him some time in the first half of 1999. There ensued a number of communications between Keith Price and Lenihan, between Ingrid Price, the president of I&R, and Lenihan, and thereafter between Ingrid Price and Thomas Cutter, the principal of Cutter Northern. The end result was that Cutter Northern informed I&R that it would not perform the chimney repair work at the price of $15,640.00. It appears the reason Cutter Northern took this position was based on its inspection of the East Boston High School site in the fall of 1998, after I&R had been awarded the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loranger Construction Corp. v. E. F. Hauserman Co.
384 N.E.2d 176 (Massachusetts Supreme Judicial Court, 1978)
Atkinson v. Rosenthal
598 N.E.2d 666 (Massachusetts Appeals Court, 1992)
Cavanagh v. Cavanagh
598 N.E.2d 677 (Massachusetts Appeals Court, 1992)
David J. Tierney, Jr., Inc. v. T. Wellington Carpets, Inc.
392 N.E.2d 1066 (Massachusetts Appeals Court, 1979)
Rhode Island Hospital Trust National Bank v. Varadian
647 N.E.2d 1174 (Massachusetts Supreme Judicial Court, 1995)
Massachusetts Employers Insurance Exchange v. Propac-Mass, Inc.
420 Mass. 39 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
14 Mass. L. Rptr. 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ir-mechanical-inc-v-cutter-northern-refractories-inc-masssuperct-2001.