IPS Contracting, Inc. v. Rivian Automotive, LLC

CourtDistrict Court, E.D. Michigan
DecidedOctober 22, 2021
Docket2:21-cv-10983
StatusUnknown

This text of IPS Contracting, Inc. v. Rivian Automotive, LLC (IPS Contracting, Inc. v. Rivian Automotive, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
IPS Contracting, Inc. v. Rivian Automotive, LLC, (E.D. Mich. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

IPS Contracting, Inc.,

Plaintiff,

v. Civil Case No. 21-10983

Rivian Automotive, LLC, Sean F. Cox United States District Court Judge Defendant. ______________________________/

OPINION AND ORDER GRANTING DEFENDANT’S PARTIAL MOTION TO DISMISS

This is a civil dispute arising out of a demolition contract. Plaintiff, IPS Contracting, alleges that they are entitled to scrap material, which Defendant, Rivian Automotive, LLC, has failed to provide them. Plaintiff alleges that Defendant: (1) breached a contractual agreement; (2) was unjustly enriched; (3) is liable for promissory estoppel; (4) made an innocent misrepresentation; and (5) is liable for conversion and statutory conversion. (Am. Compl., ECF No. 6, at PageID 38- 45). Currently, the matter before the Court is Defendant’s Partial Motion to Dismiss (ECF No. 10). The motion has been fully briefed, and the Court concludes that oral argument is not necessary. Thus, the Court orders that the motions will be decided without a hearing. See E.D. Mich. LR 7.1(f). For the following reasons, the Court GRANTS Defendant’s motion and DISMISSES Counts II - VI. BACKGROUND On March 29, 2021, Plaintiff initiated this action against Defendant in Wayne County

Circuit Court. (ECF No. 1-1). Plaintiff alleges the following claims: breach of contract (Count One); quantum meruit/unjust enrichment (Count Two); promissory estoppel (Count Three); innocent misrepresentation (Count Four); conversion (Count Five); and statutory conversion (Count Six). (Am. Compl., at PageID 38-45). On May 1, 2021, Defendant removed the matter to this Court pursuant to 28 U.S.C. §§ 1332(a), 1441, and 1446. (ECF No. 1). On June 29, 2021, Defendant filed a Partial Motion to

Dismiss pursuant to FED. R. CIV. P. 12(b)(6) requesting the Court dismiss Counts II through VI for failure to state a claim. (ECF No. 10). Because this matter comes before the Court on a motion to dismiss the Amended Complaint, the following allegations in Plaintiff’s Amended Complaint are taken as true. Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009).

In January 2017, Defendant “purchased a Plant in order to manufacture its new fleet of electric vehicles.” Id. at ¶ 7. To produce the electric vehicles, Defendant needed to “demolish, strip-out and massively reconfigure the Plant, which when purchased, had been filled with paint booths, multiple assembly line conveyors and other equipment . . . .” Id. at ¶ 8. On January 16, 2019, Plaintiff submitted a bid to perform the demolition work. Id. at ¶ 10.

Plaintiff alleges that the bid not only stated that the total cost would be “$6,596,920” but it also “expressly stated” that said bid was contingent upon Plaintiff “receiving title to all scrap and equipment (i.e., robots, conveyors, panels, scrap metal, etc.).” Id. Defendant accepted Plaintiff’s proposal and “issued a purchase order on January 31, 2019, in the amount of $6,596,920.” Id. at ¶ 18. Throughout the course of the demolition, Defendant submitted subsequent purchase orders to the Plaintiff. Id. at ¶ 12-13. The “same language” regarding the scrap equipment was used in each subsequent purchase order. Id. at ¶ 13. Plaintiff further alleges that “[t]he inclusion of the transfer of title of the scrap and equipment . . . is

significant and was a material component of [Plaintiff’s] bid estimate.” Id. at ¶ 15. Plaintiff alleges that “the scrap and equipment . . . has a substantial economic value.” Id. at ¶ 16. Once Plaintiff initiated the demolition work, it: began to notice that volume of scrap and equipment it had intended to harvest from the Plant was substantially less than expected. For example, thousands of tons of copper wire were missing, robots that were intended to be removed by [Plaintiff] were not present and air filtering equipment had vanished. Id. at ¶ 18. The “scrap and equipment” at issue were allegedly going to be used by Plaintiff to offset the “costs to perform the work in question.” Id. at ¶ 39. The unexplained removal of the “scrap and equipment was continuous and systematic throughout the life of the project.” Id. at ¶ 19. When Plaintiff told Defendant about the situation, “Defendant’s . . . representatives responded . . . with feigned concern, or . . . told [Plaintiff] that Plaintiff was not entitled to the scrap material and equipment.” Id. at ¶ 20. Plaintiff alleges that they were able to “generate some revenue from the recovery of scrap and equipment” but “it was millions of dollars less than what was reasonably anticipated.” Id. at ¶ 21. Furthermore, Plaintiff alleges “that several Rivian employees working at the Plant were actually stealing the scrap and equipment.” Id. at ¶ 22. Plaintiff has asked Defendant to be reimbursed “for the value of the scrap, material and equipment that it was denied as a result of [Plaintiff’s] and its employees’ theft and misappropriation.” Id. at ¶ 23. Defendant has refused to reimburse Plaintiff. Id. Plaintiff filed this matter in response. (ECF No. 1).

STANDARD OF REVIEW A motion to dismiss tests the legal sufficiency of the plaintiff’s complaint. To survive a motion to dismiss, the complaint must state sufficient “facts to state a claim to relief that is plausible on its face.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007). Claims comprised of “labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Id. at 555. “A claim has facial plausibility when the plaintiff pleads factual content that allows

the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal, 556 U.S. 662 (2009). Although the Court must accept all well-pleaded factual allegations as true for purposes of a motion to dismiss, the Court is “not bound to accept as true a legal conclusion couched as a factual allegation.” Twombly, 550 U.S. at 555. Thus, to avoid dismissal, “a complaint must contain sufficient factual matter,” accepted as true, to state a claim for relief that is plausible on its face. Id. at 678. In practice, a complaint must contain either direct or inferential allegations respecting

all the material elements to sustain recovery under some viable legal theory. Lillard v. Shelby County Bd. of Educ., 76 F.3d 716, 726 (6th Cir. 1996). “A complaint should not be dismissed for failure to state a claim unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Mayer v. Mylod, 988 F.2d 635, 638 (6th Cir. 1993). “The fundamental purpose of pleadings under the Federal Rules of Civil Procedure is to give adequate notice to the parties of each side’s claims and to allow cases to be decided on the merits after an adequate development of the facts.” Id.

“When a court is presented with a Rule 12(b)(6) motion, it may consider the Complaint and any exhibits attached thereto, public records, items appearing in the record of the case and exhibits attached to defendant’s motion to dismiss so long as they are referred to in the Complaint and are central to the claims contained therein.” Weiner v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
General Aviation, Inc. v. The Cessna Aircraft Co.
915 F.2d 1038 (Sixth Circuit, 1990)
Armisted v. State Farm Mutual Automobile Insurance
675 F.3d 989 (Sixth Circuit, 2012)
Alan Weiner, D.P.M. v. Klais and Company, Inc.
108 F.3d 86 (Sixth Circuit, 1997)
M&D, INC v. McCONKEY
585 N.W.2d 33 (Michigan Court of Appeals, 1998)
Barber v. Smh (Us), Inc
509 N.W.2d 791 (Michigan Court of Appeals, 1993)
Cascade Electric Co. v. Rice
245 N.W.2d 774 (Michigan Court of Appeals, 1976)
Unibar Maintenance Services, Inc v. Saigh
769 N.W.2d 911 (Michigan Court of Appeals, 2009)
Derderian v. Genesys Health Care Systems
689 N.W.2d 145 (Michigan Court of Appeals, 2004)
United States Fidelity & Guaranty Co. v. Black
313 N.W.2d 77 (Michigan Supreme Court, 1981)
Martin v. East Lansing School District
483 N.W.2d 656 (Michigan Court of Appeals, 1992)
Llewellyn-Jones v. Metro Property Group, LLC
22 F. Supp. 3d 760 (E.D. Michigan, 2014)
Mayer v. Mylod
988 F.2d 635 (Sixth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
IPS Contracting, Inc. v. Rivian Automotive, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ips-contracting-inc-v-rivian-automotive-llc-mied-2021.