Ippolito v. TJC Development, LLC

83 A.D.3d 57, 920 N.Y.S.2d 108
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 22, 2011
StatusPublished
Cited by21 cases

This text of 83 A.D.3d 57 (Ippolito v. TJC Development, LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ippolito v. TJC Development, LLC, 83 A.D.3d 57, 920 N.Y.S.2d 108 (N.Y. Ct. App. 2011).

Opinion

OPINION OF THE COURT

Dickerson, J.

Introduction

The plaintiffs owned a home at 273 Park Avenue in Babylon (hereinafter the premises). They entered into a contract (hereinafter the agreement) with the defendant TJC Development, LLC (hereinafter TJC), pursuant to which TJC was to perform substantial home improvement renovations to the premises. The defendants Gerald Pointing and Joseph Torto were officers, directors, and/or shareholders of TJC. Ultimately, the plaintiffs terminated TJC’s involvement with the project for numerous alleged failures and shortcomings. The plaintiffs demanded arbitration against TJC, proceeded to arbitration, and were awarded the sum of $121,155.32 by the arbitrator. At approximately the same time the plaintiffs filed their demand for arbitration against TJC, the plaintiffs commenced this action pursuant to Lien Law article 3-A against TJC, Pointing, and Torto. In the order appealed from, the Supreme Court, inter alia, granted that branch of the defendants’ cross motion which was to dismiss the complaint pursuant to CPLR 3211 (a) (1) and (5), concluding that the plaintiffs’ Lien Law claim was not viable. We disagree. Contrary to the Supreme Court’s determination, the plaintiffs, as homeowners contracting for the performance of certain home improvements, were beneficiaries of the trust created by operation of Lien Law § 70, and they had standing to assert a cause of action pursuant to Lien Law article 3-A against TJC, or its officers or agents, alleging that the funds they paid to TJC were improperly diverted within the meaning of Lien Law § 72. However, as we will also discuss, the plaintiffs’ cause of action insofar as asserted against TJC is barred by the doctrine of res judicata based on the prior arbitration proceeding.

Factual and Procedural Background

The Plaintiffs’ Motion

By notice of motion dated February 4, 2009, the plaintiffs moved to certify this action as a class action, defining the class [60]*60as all beneficiaries of Lien Law article 3-A trust funds received by TJC in connection with the project, to direct the defendants to provide a list of all such beneficiaries, to establish the method of notice to class members, and for such other and further relief deemed appropriate by the motion court.

The plaintiff Anthony Ippolito (hereinafter Anthony) submitted an affidavit in support of the plaintiffs’ motion, asserting that after TJC’s alleged breach of the agreement, the plaintiffs were compelled to commence an arbitration proceeding against TJC. During the arbitration proceeding, the plaintiffs demonstrated that TJC breached its contractual obligation, which was to complete the relevant construction project between August 2004 and December 2004. The plaintiffs further demonstrated that TJC abandoned the project by failing to provide sufficient manpower to complete the work, and by failing to complete the project within a reasonable time.

The arbitrator, in his award, found, among other things, that TJC breached the contract. Accordingly, the arbitrator determined that the plaintiffs were justified in declaring that TJC had breached the contract, and in retaining others to complete the project. According to Anthony, the arbitrator awarded the plaintiffs the principal sum of $102,674, plus interest, for a total award of $121,155.32.

The plaintiffs alleged that the money they paid to TJC constituted trust funds pursuant to Lien Law article 3-A, and that TJC, through its corporate officers, Pointing and Torto, failed to hold and apply the trust funds for the benefit of the trust beneficiaries, including the plaintiffs, but rather misappropriated the funds. In addition, TJC failed to maintain the required records concerning the trust.

The plaintiffs also submitted the arbitrator’s award in the arbitration proceeding between the plaintiffs and TJC. The award stated, in pertinent part:

“[TJC] breached the contract by failing to adequately prosecute the project and not completing the project in a reasonably timely fashion. Therefore, [the plaintiffs] were justified in terminating the contract and retaining others to complete the project . . .
“Based upon this finding, [the plaintiffs] are entitled to an award equal to the reasonable costs to complete the work under the contract, and the reason[61]*61able value of the work needed to correct any deficient work performed by [TJC], less the amount remaining to be paid under [TJC’s] contract. . .
“[TJC] is entitled to a credit for the sum remaining to be paid under its contract. Based upon the above, within 30 days of the date that the award is transmitted to counsel, [TJC] shall pay to [the plaintiffs] the sum of $121,155.32.”

The amount awarded consisted of an estimated reasonable cost to complete the project in the sum of $164,340, less the balance remaining to be paid to TJC ($61,666), for a subtotal of $102,674, plus interest from December 7, 2006, through December 7, 2008, in the sum of $18,481.32, for a total award of $121,155.32.

Defendants’ Cross Motion to Dismiss

By notice of cross motion dated February 10, 2009, the defendants cross-moved, inter alia, pursuant to CPLR 3211 (a) (1) and (5) to dismiss the complaint.

In support of their cross motion, the defendants observed that, in or about November 2007, the plaintiffs filed a demand for arbitration pursuant to the arbitration clause incorporated into the agreement between the plaintiffs and TJC. The demand sought only to recover damages which the plaintiffs claimed resulted from TJC’s alleged breach. In the demand, the plaintiffs did not refer to any claim against TJC pursuant to Lien Law article 3-A based on diversion of trust funds. Further, during arbitration, the plaintiffs did not advance any such claim.

The defendants asserted, among other things, that the plaintiffs’ claim was within the scope of the claims subject to arbitration pursuant to the arbitration clause incorporated into the agreement between the plaintiffs and TJC. Relying on the doctrines of res judicata and collateral estoppel, the defendants asserted that the plaintiffs waived their right to proceed against TJC on a “trust fund diversion” theory because they did not advance such a claim against TJC at arbitration.

The defendants asserted that TJC, and not its officers, would be the only statutory trustee of funds received from the plaintiffs under the Lien Law. The defendants contended that there could be no claim against the principals of TJC for participating in the diversion of the funds without proof that the corporation received and misapplied trust funds. Accordingly, the defendants asserted that the plaintiffs had no claim [62]*62without proving that TJC failed to apply the full amount of money received to its expenses in performing the work for which the money was paid.

Also in support of their cross motion, the defendants submitted a copy of the plaintiffs’ demand for arbitration. The plaintiffs were named as the claimants, and TJC was named as the respondent. The claim was described as “[fjailure to complete the work provided for in the contract in a timely manner and consistent with contractual deadlines and failure to perform work in a reasonable, proper and workmanlike manner.” The arbitration clause was reproduced in the demand for arbitration as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quality Aggregates, Inc. v. Prime Mix Corp.
2025 NY Slip Op 06882 (Appellate Division of the Supreme Court of New York, 2025)
Ramus v. Bruwer
S.D. New York, 2025
Park E. Constr. Corp. v. Uliano
2024 NY Slip Op 06353 (Appellate Division of the Supreme Court of New York, 2024)
Proco Enter. Inc. v. Murad
2024 NY Slip Op 33811(U) (New York Supreme Court, New York County, 2024)
Flintlock Constr. Servs., LLC v. HPH Servs., Inc.
2024 NY Slip Op 04282 (Appellate Division of the Supreme Court of New York, 2024)
Matter of Enigbonjaye v. NYS Justice Ctr. for People with Special Needs
2024 NY Slip Op 00766 (Appellate Division of the Supreme Court of New York, 2024)
Tristate Cleaning Solutions, Inc. v. Landco H & L, Inc.
204 A.D.3d 1064 (Appellate Division of the Supreme Court of New York, 2022)
People v. Cook
128 A.D.3d 928 (Appellate Division of the Supreme Court of New York, 2015)
Caban v. New York Methodist Hospital
119 A.D.3d 717 (Appellate Division of the Supreme Court of New York, 2014)
Leon v. Shmukler
992 F. Supp. 2d 179 (E.D. New York, 2014)
ACKMAN, KIMBERLY L. v. HABERER, MARK
Appellate Division of the Supreme Court of New York, 2013
Ackman v. Haberer
111 A.D.3d 1378 (Appellate Division of the Supreme Court of New York, 2013)
Holt Construction Corp. v. Grand Palais, LLC
108 A.D.3d 593 (Appellate Division of the Supreme Court of New York, 2013)
Sweet Constructors, LLC v. Wallkill Medical Development, LLC
106 A.D.3d 810 (Appellate Division of the Supreme Court of New York, 2013)
Gorman v. Fowkes
97 A.D.3d 726 (Appellate Division of the Supreme Court of New York, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
83 A.D.3d 57, 920 N.Y.S.2d 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ippolito-v-tjc-development-llc-nyappdiv-2011.