ion Network v. Colo Mined Land
Opinion
The summaries of the Colorado Court of Appeals published opinions constitute no part of the opinion of the division but have been prepared by the division for the convenience of the reader. The summaries may not be cited or relied upon as they are not the official language of the division. Any discrepancy between the language in the summary and in the opinion should be resolved in favor of the language in the opinion.
SUMMARY
July 25, 2019
2019COA114
No. 18CA1148, Information Network v. Colo Mined Land — Energy and Environment — Mining — Mined Land Reclamation Act
In this case, a division of the court of appeals concludes for the first time that under the Colorado Mined Land Reclamation Act, temporary cessation is a factual status, rather than a legal one. Therefore, the Colorado Mined Land Reclamation Board lacked the legal authority to approve a further period of cessation when the mine had not produced any minerals for more than the ten-year statutory limitation in section 34-32-103(6)(a)(III), C.R.S. 2018.
COLORADO COURT OF APPEALS 2019COA114
Court of Appeals No. 18CA1148 City and County of Denver District Court No. 17CV33475 Honorable Michael A. Martinez, Judge
Information Network for Responsible Mining, Earthworks, and Sheep Mountain Alliance,
Plaintiffs-Appellants, v. Colorado Mined Land Reclamation Board, Defendant-Appellee.
JUDGMENT REVERSED AND CASE REMANDED WITH DIRECTIONS
Division V
Opinion by JUDGE TOW
Richman and Harris, JJ., concur
Announced July 25, 2019
Travis Stills, Durango, Colorado; Roger Flynn, Jeffrey C. Parsons, Lyons, Colorado, for Plaintiffs-Appellants
Philip J. Weiser, Attorney General, Charles J. Kooyman, Senior Assistant Attorney General, Denver, Colorado, for Defendant-Appellee
¶1 Information Network for Responsible Mining, Earthworks, and Sheep Mountain Alliance (collectively, the objectors) appeal the district court’s judgment, affirming the Colorado Mined Land Reclamation Board (the Board) order granting the request of Piñon Ridge Mining, LLC for approval of a second period of temporary cessation. 1 We reverse.
I. Background
¶2 In November 1999, Piñon Ridge Mining was issued a permit for a uranium mining operation known as the Van 4 Shaft (the site), releasing the company’s predecessor from its permit. The site last produced ore in 1989. In March 2014, the Division of Reclamation, Mining, and Safety (the Division) approved an initial period of temporary cessation for the site, with an effective date of June 13, 2012.
¶3 In May 2017, the Division received a request for approval of a second period of temporary cessation for the site. The objectors filed objections to this request. The Board held a hearing on the matter. During the hearing, a representative of Piñon Ridge Mining
1 Additional parties filed objections during the proceedings before the Board but did not join this appeal.
testified that minerals had not been extracted since it had taken over the site because the depressed market price of uranium made production unprofitable. The representative also testified that the operator had explored one other avenue for extraction.
¶4 The Board ultimately granted the request for approval of a second period of temporary cessation. The district court affirmed the Board’s order. The objectors now appeal the Board’s decision.
II. Analysis
¶5 The objectors assert that the district court erred in affirming the Board’s order, which, the objectors argue, ignored the plain language of the Colorado Mined Land Reclamation Act (MLRA) when approving a second period of temporary cessation. We agree.
A. Standard of Review
¶6 The Board is a state agency governed by the State Administrative Procedure Act, sections 24-4-101 to -108, C.R.S. 2018. In reviewing the Board’s actions, we stand in the same position as the district court. See Haney v. Colo. Dep’t of Revenue, 2015 COA 125, ¶ 14. We must set aside an agency action that is
(I) Arbitrary or capricious;
(II) A denial of statutory right;
(III) Contrary to constitutional right, power, privilege, or immunity;
(IV) In excess of statutory jurisdiction, authority, purposes, or limitations;
(V) Not in accord with the procedures or procedural limitations of this article 4 or as otherwise required by law;
(VI) An abuse or clearly unwarranted exercise of discretion;
(VII) Based upon findings of fact that are clearly erroneous on the whole record;
(VIII) Unsupported by substantial evidence when the record is considered as a whole; or (IX) Otherwise contrary to law, including failing to comply with section 24-4-104(3)(a) or 24-4-
105(4)(b).
§ 24-4-106(7)(b), C.R.S. 2018. “In all cases under review, the court shall determine all questions of law and interpret the statutory and constitutional provisions involved and shall apply the interpretation to the facts duly found or established.” § 24-4-106(7)(d).
B. Applicable Law
¶7 The MLRA was enacted to encourage and foster mining of the state’s natural resources and subsequent reclamation of the land affected by such extraction. § 34-32-102(1), C.R.S. 2018. Under the MLRA, a mining permit may continue in effect even if the mining operation “temporarily cease[s] production for one hundred eighty days or more,” provided the operator files a “Notice of
Temporary Cessation” with the Office of Mined Land Reclamation. § 34-32-103(6)(a)(II), C.R.S. 2018. Production must be resumed within five years of temporary cessation or the operator must “file[] a report requesting an extension of the period of temporary cessation.” § 34-32-103(6)(a)(III). But “[i]n no case shall temporary cessation of production be continued for more than ten years without terminating the operation and fully complying with the reclamation requirements of this article.” Id.
¶8 Temporary cessation is defined as “those limited periods of non-production as specified according to Section 1.13.” Div. of Reclamation, Mining & Safety Rule 1.1(53), 2 Code Colo. Regs. 407-1. According to Section 1.13, indications that temporary cessation has occurred include
(1) there are no personnel working at the site for one hundred eighty (180) consecutive days;
(2) there are only security personnel at the site;
(3) there are personnel other than security people at the site, but they are engaged in activities which can be described as maintenance or housekeeping, or related activity;
(4) there are personnel at the site, but they are engaged in activities which are not significantly moving the site towards
completion of the mining operation. The Board will judge these activities in relation to the size of the operation, the nature of the ore body and other facts;
(5) there is no sale or processing of material or movement of stockpiled material;
(6) [t]here is only minimal or token excavation of mineral or other material;
or
(7) mine development has ceased and mining has not recommenced.
Id. at Rule 1.13.2. In contrast, indications that temporary cessation has not occurred are that the extraction of minerals is complete but final reclamation-related activities are occurring, or a permit has been issued for the site but mining operations have yet to begin. Id. at Rule 1.13.3.
C. Temporary Cessation is a Factual Status
¶9 As a preliminary matter, we conclude that the district court erred in affirming the Board’s order, which treated temporary cessation as a legal status, rather than a factual one, and “reset” the effective date of that status.
¶ 10 During the Board’s hearing, it was disclosed that in 2011 or 2012, the Division realized that a large number of mines had not been in production for quite some time. Yet, they had been treated as being in intermittent status, rather than in a status of temporary
cessation.2 The Division consequently informed the licensees that these mines would be “reset” to temporary cessation status. 3 At the hearing, the Division representative explained to the Board,
Free access — add to your briefcase to read the full text and ask questions with AI
2019 COA 114 (ion Network v. Colo Mined Land) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.