Intershell International Corp. v. Great Eastern Marine Service, Inc.

CourtMassachusetts Appeals Court
DecidedOctober 4, 2024
Docket23-P-1117
StatusUnpublished

This text of Intershell International Corp. v. Great Eastern Marine Service, Inc. (Intershell International Corp. v. Great Eastern Marine Service, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intershell International Corp. v. Great Eastern Marine Service, Inc., (Mass. Ct. App. 2024).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1117

INTERSHELL INTERNATIONAL CORP.

vs.

GREAT EASTERN MARINE SERVICE, INC.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This action concerns a contract for the defendant, Great

Eastern Marine Service, Inc. (GEM), to construct a pier for the

plaintiff, Intershell International Corp. (Intershell). The

parties dispute whether the agreement included a condition

precedent that GEM would obtain a building permit such that

construction would be complete before June 1, 2020. GEM did not

obtain a building permit in time to do so (through no fault of

either party), and Intershell then brought this action in which

both parties alleged, among other claims and counterclaims, that

the other breached their agreement. After a bench trial, a

judge of the Superior Court concluded that the agreement did

contain an unfulfilled condition precedent and, as a result, the contract was unenforceable. The judge ordered GEM to return the

$100,000 that Intershell previously had paid GEM, less $5,000

that GEM expended in preparation to complete the work.

The parties cross-appealed from the judgment. GEM argues

that the judge's findings that the contract contained a

condition precedent and that Intershell's $100,000 payment

constituted a refundable deposit were clear error. Intershell

counters that it was entitled to prejudgment interest on the

amount it received under the judgment. We vacate so much of the

judgment as declined to award prejudgment interest and remand

for reconsideration.1 We otherwise affirm.

Background. We set forth the undisputed facts as well as

those found by the judge after trial. We reserve certain facts

for our later discussion.

Intershell is a commercial fishing business and GEM is a

marine construction business. Howard Monte Rome is Intershell's

general manager. Kenneth Taliadoros (Kenneth) is GEM's owner

and president, and Kenneth's son, Jonathan Taliadoros

(Jonathan), is an engineer for GEM.2

1 Although the judgment itself does not include the order to return the deposit, we treat that order as subsumed in the final judgment that entered on April 6, 2023.

2 Because Kenneth and Jonathan share a last name, we refer to them by their first names.

2 1. The bid and the contract. In December 2019, Intershell

sought bids to construct a new pier (project) on its property in

the city of Gloucester (city).3 Intershell wanted the project

completed by June 1, 2020,4 which was the start of its busy

season. To that end, Rome and Kenneth, who were acquainted

because of the parties' previous business dealings over the

years, met at the property to discuss the project. At that

meeting, Rome gave Kenneth copies of certain documents including

an amended order of conditions (OOC) that Intershell had

obtained for the project from the city's conservation

commission.

On January 10, GEM sent a written bid for the project in

the amount of $357,500 to Intershell. The bid provided that

"[u]nless specifically modified in the attached

quotation/proposal, payment terms require [one-third] upon

acceptance, [one-third] upon [fifty percent] completion and

[one-third] upon [one hundred percent] completion." In the e-

mail message accompanying the bid, Kenneth stated that the

"quote includes [GEM] pulling the building permit for the

project." Notwithstanding that representation, the bid

specified that "[a]ll permits are by owner."

3 My Management Group, LLC, an Intershell affiliate, is the record owner of the property.

4 Unless otherwise specified, all events took place in 2020.

3 On January 25, Rome, Kenneth, and Jonathan met to discuss

GEM's bid. During that meeting, the parties agreed to the terms

set forth in GEM's bid with the following three oral

modifications: (1) Intershell's first payment to GEM would be

in the amount of $100,000 rather than one-third of the bid price

($117,975); (2) GEM was responsible for obtaining the building

permit for the project; and (3) the project had to be completed,

and GEM's equipment and barge removed from the site by June 1.

The parties signed the bid and Intershell provided GEM with

$100,000. Of the three bids that Intershell received for the

project, GEM's bid was the highest. However, Intershell

selected GEM's bid because GEM was the only bidder prepared to

complete the project by June 1.

2. Building permit and GEM's preparation work. On

February 19, Kenneth submitted the building permit application

to the city. Kenneth believed that the city would quickly issue

the building permit because Intershell already obtained several

environmental-related permits, including the OOC. On February

22, GEM brought a barge and other equipment to the job site. At

that time, Kenneth informed Rome that he had not yet received

the building permit. A few days later, Jonathan and another GEM

employee performed some preparation work on the job site,

including removing debris and preparing to demolish and remove a

4 concrete slab. GEM spent between $5,000 and $6,000 to complete

this work.

On February 27, Kenneth contacted the city's building

department to inquire about the status of the permit application

and learned that the conservation commission was "holding up"

approval of the application. Kenneth then contacted the

conservation commission and was told that the permit application

had to be denied because the OOC previously obtained by

Intershell was not valid. Kenneth immediately told Rome and, in

turn, Rome took prompt action to obtain a new OOC.

Rome kept Kenneth apprised of the status of the OOC, but

its issuance was delayed by the conservation commission. When

it became clear that the new OOC would not issue in time for GEM

to obtain a building permit and complete the project by June 1,

Intershell took the position that the contract was null and void

and offered to cover GEM's costs thus far. GEM continued to

offer to complete the project once the permit issued.

In April, Rome directed Kenneth to remove its barge and

equipment, and GEM did so. In May, Rome requested that Kenneth

return Intershell's $100,000 and stated that the parties could

discuss GEM performing the work in the coming fall or winter.

GEM continued to offer to perform under the agreement once the

permit was obtained. That same month, Rome suggested that GEM

provide a new bid consistent with the lower bid prices that it

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tilo Roofing Co. Inc. v. Pellerin
122 N.E.2d 460 (Massachusetts Supreme Judicial Court, 1954)
Sterilite Corp. v. Continental Casualty Co.
494 N.E.2d 1008 (Massachusetts Supreme Judicial Court, 1986)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Peabody N.E., Inc. v. Town of Marshfield
689 N.E.2d 774 (Massachusetts Supreme Judicial Court, 1998)
Uno Restaurants, Inc. v. Boston Kenmore Realty Corp.
805 N.E.2d 957 (Massachusetts Supreme Judicial Court, 2004)
Twin Fires Investment, LLC v. Morgan Stanley Dean Witter & Co.
445 Mass. 411 (Massachusetts Supreme Judicial Court, 2005)
Casavant v. Norwegian Cruise Line Ltd.
460 Mass. 500 (Massachusetts Supreme Judicial Court, 2011)
Rood v. Newberg
718 N.E.2d 886 (Massachusetts Appeals Court, 1999)
National Starch & Chemical Co. v. Greenberg
810 N.E.2d 1239 (Massachusetts Appeals Court, 2004)
Nissan Automobiles of Marlborough, Inc. v. Glick
816 N.E.2d 161 (Massachusetts Appeals Court, 2004)
Henry v. Morris
819 N.E.2d 619 (Massachusetts Appeals Court, 2004)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Aronovitz v. Fafard
934 N.E.2d 851 (Massachusetts Appeals Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Intershell International Corp. v. Great Eastern Marine Service, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/intershell-international-corp-v-great-eastern-marine-service-inc-massappct-2024.