Intershell International Corp. v. Great Eastern Marine Service, Inc.

Massachusetts Appeals Court·Decided October 4, 2024·No. 23-P-1117·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1117

INTERSHELL INTERNATIONAL CORP.

vs.

GREAT EASTERN MARINE SERVICE, INC.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This action concerns a contract for the defendant, Great

Eastern Marine Service, Inc. (GEM), to construct a pier for the

plaintiff, Intershell International Corp. (Intershell). The

parties dispute whether the agreement included a condition

precedent that GEM would obtain a building permit such that

construction would be complete before June 1, 2020. GEM did not

obtain a building permit in time to do so (through no fault of

either party), and Intershell then brought this action in which

both parties alleged, among other claims and counterclaims, that

the other breached their agreement. After a bench trial, a

judge of the Superior Court concluded that the agreement did

contain an unfulfilled condition precedent and, as a result, the

contract was unenforceable. The judge ordered GEM to return the $100,000 that Intershell previously had paid GEM, less $5,000 that GEM expended in preparation to complete the work.

The parties cross-appealed from the judgment. GEM argues that the judge's findings that the contract contained a condition precedent and that Intershell's $100,000 payment constituted a refundable deposit were clear error. Intershell counters that it was entitled to prejudgment interest on the amount it received under the judgment. We vacate so much of the judgment as declined to award prejudgment interest and remand for reconsideration.1 We otherwise affirm.

Background. We set forth the undisputed facts as well as those found by the judge after trial. We reserve certain facts for our later discussion.

Intershell is a commercial fishing business and GEM is a marine construction business. Howard Monte Rome is Intershell's general manager. Kenneth Taliadoros (Kenneth) is GEM's owner and president, and Kenneth's son, Jonathan Taliadoros (Jonathan), is an engineer for GEM.2

1. The bid and the contract. In December 2019, Intershell sought bids to construct a new pier (project) on its property in the city of Gloucester (city).3 Intershell wanted the project completed by June 1, 2020,4 which was the start of its busy season. To that end, Rome and Kenneth, who were acquainted because of the parties' previous business dealings over the years, met at the property to discuss the project. At that meeting, Rome gave Kenneth copies of certain documents including an amended order of conditions (OOC) that Intershell had obtained for the project from the city's conservation commission.

On January 10, GEM sent a written bid for the project in the amount of $357,500 to Intershell. The bid provided that "[u]nless specifically modified in the attached quotation/proposal, payment terms require [one-third] upon acceptance, [one-third] upon [fifty percent] completion and [one-third] upon [one hundred percent] completion." In the e- mail message accompanying the bid, Kenneth stated that the "quote includes [GEM] pulling the building permit for the project." Notwithstanding that representation, the bid specified that "[a]ll permits are by owner."

On January 25, Rome, Kenneth, and Jonathan met to discuss GEM's bid. During that meeting, the parties agreed to the terms set forth in GEM's bid with the following three oral modifications: (1) Intershell's first payment to GEM would be in the amount of $100,000 rather than one-third of the bid price ($117,975); (2) GEM was responsible for obtaining the building permit for the project; and (3) the project had to be completed, and GEM's equipment and barge removed from the site by June 1. The parties signed the bid and Intershell provided GEM with $100,000. Of the three bids that Intershell received for the project, GEM's bid was the highest. However, Intershell selected GEM's bid because GEM was the only bidder prepared to complete the project by June 1.

2. Building permit and GEM's preparation work. On February 19, Kenneth submitted the building permit application to the city. Kenneth believed that the city would quickly issue the building permit because Intershell already obtained several environmental-related permits, including the OOC. On February 22, GEM brought a barge and other equipment to the job site. At that time, Kenneth informed Rome that he had not yet received the building permit. A few days later, Jonathan and another GEM employee performed some preparation work on the job site, including removing debris and preparing to demolish and remove a

concrete slab. GEM spent between $5,000 and $6,000 to complete this work.

On February 27, Kenneth contacted the city's building department to inquire about the status of the permit application and learned that the conservation commission was "holding up" approval of the application. Kenneth then contacted the conservation commission and was told that the permit application had to be denied because the OOC previously obtained by Intershell was not valid. Kenneth immediately told Rome and, in turn, Rome took prompt action to obtain a new OOC.

Rome kept Kenneth apprised of the status of the OOC, but its issuance was delayed by the conservation commission. When it became clear that the new OOC would not issue in time for GEM to obtain a building permit and complete the project by June 1, Intershell took the position that the contract was null and void and offered to cover GEM's costs thus far. GEM continued to offer to complete the project once the permit issued.

In April, Rome directed Kenneth to remove its barge and equipment, and GEM did so. In May, Rome requested that Kenneth return Intershell's $100,000 and stated that the parties could discuss GEM performing the work in the coming fall or winter. GEM continued to offer to perform under the agreement once the permit was obtained. That same month, Rome suggested that GEM provide a new bid consistent with the lower bid prices that it

previously received (between $220,000 and $265,000) because the parties' agreement was "no longer valid" and Intershell was not willing to pay "the premium" price for the project given that the June 1 deadline could not be met. In June, Rome notified Kenneth that Intershell received the OOC and was ready "to make a plan for the work." Kenneth responded that the parties' attorneys should have further discussions. Intershell later awarded the project to another company for $219,000.

3. The judge's findings. In August, Intershell brought an action for breach of contract and violation of G. L. c. 93A.5 GEM brought counterclaims for breach of contract, breach of the covenant of good faith and fair dealing, and violation of G. L. c. 93A. The matter proceeded to a jury-waived trial where Rome, Kenneth, and Jonathan testified. After hearing the parties' evidence, the judge allowed each party's motion for involuntary dismissal of the other's c. 93A claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Intershell International Corp. v. Great Eastern Marine Service, Inc., (Mass. Ct. App. 2024).

Intershell International Corp. v. Great Eastern Marine Service, Inc. (Intershell International Corp. v. Great Eastern Marine Service, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tilo Roofing Co. Inc. v. Pellerin
122 N.E.2d 460 (Massachusetts Supreme Judicial Court, 1954)
Sterilite Corp. v. Continental Casualty Co.
494 N.E.2d 1008 (Massachusetts Supreme Judicial Court, 1986)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Peabody N.E., Inc. v. Town of Marshfield
689 N.E.2d 774 (Massachusetts Supreme Judicial Court, 1998)
Uno Restaurants, Inc. v. Boston Kenmore Realty Corp.
805 N.E.2d 957 (Massachusetts Supreme Judicial Court, 2004)
Twin Fires Investment, LLC v. Morgan Stanley Dean Witter & Co.
445 Mass. 411 (Massachusetts Supreme Judicial Court, 2005)
Casavant v. Norwegian Cruise Line Ltd.
460 Mass. 500 (Massachusetts Supreme Judicial Court, 2011)
Rood v. Newberg
718 N.E.2d 886 (Massachusetts Appeals Court, 1999)
National Starch & Chemical Co. v. Greenberg
810 N.E.2d 1239 (Massachusetts Appeals Court, 2004)
Nissan Automobiles of Marlborough, Inc. v. Glick
816 N.E.2d 161 (Massachusetts Appeals Court, 2004)
Henry v. Morris
819 N.E.2d 619 (Massachusetts Appeals Court, 2004)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Aronovitz v. Fafard
934 N.E.2d 851 (Massachusetts Appeals Court, 2010)