This text of 278 F.3d 494 (International Turbine Services, Inc. v. VASP Brazilian Airlines) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Turbine Services, Inc. v. VASP Brazilian Airlines, 278 F.3d 494, 2002 U.S. App. LEXIS 90, 2002 WL 15514 (5th Cir. 2002).

Opinion

BOBBY R. BALDOCK, Circuit Judge:

Defendant VASP Brazilian Airlines (“VASP”), a foreign corporation, appeals the district court’s grant of summary judgment and award of damages*'on Plaintiff International Turbine Services, Inc.’s («ITS”) breach of contract claim. ITS is a Texas Corporation. We have jurisdiction pursuant to 28 U.S.C. § 1291. We affirm.

*496 I.

On October 1, 1997, ITS and VASP entered into an Aircraft Engine Lease Agreement (“Lease”). ITS leased to VASP an aircraft turbine engine and engine stand. The original Lease was for a two-month term. Through a series of amendments and renewals, the parties' extended the initial term through August 18, 1998. Upon termination, the Lease required VASP to return the engine in operable condition to ITS’ facility in Dallas, Texas.

The Lease required ITS to deliver the engine with a Federal Aviation Administration (FAA) “approved return to service tag affixed to it.” Aside from the service tag, VASP leased the engine in “AS IS WHERE IS, condition and with all faults” (emphasis in original). The Lease required VASP to service, maintain and repair the engine at its own cost and expense. The Lease further provided that VASP bore “the risk of loss and damage to the Engine and all component parts from any and every cause whatsoever” with one exception: ITS retained responsibility for shop visits required to overhaul and repair “time controlled” and “on-condition” parts which were not damaged by the act or omission of VASP. 1 Under the terms of the Lease, VASP was responsible for conducting maintenance inspections to identify when such shop visits were required, and for scheduling the required overhaul or repair. The Lease contained, a valid choice of law provision specifying Texas law.

On June 15, 1998, the pilot of a VASP plane on which the engine was mounted aborted take-off due to strong vibrations in the enginfe. VASP personnel inspected the engine and discovered it was damaged. Specifically, a high-pressure turbine (“HPT”) blade failed causing severe damage to the engine. The HPT blade is an on-condition part. VASP sent the engine to an Air France repair facility in France for inspection. This inspection confirmed the engine damage was due to the failure of an HPT blade, and that the extent of the damage rendered the engine unusable. After receiving this confirmation, VASP informed ITS it disputed responsibility for the repair costs, and would no longer submit payments under the Lease. VASP also instructed ITS to retrieve the engine from the French repair facility. ITS refused and filed this action in state court seeking damages for breach of contract. VASP counterclaimed asserting failure of consideration. VASP removed the case to federal court based on diversity jurisdiction. See 28 U.S.C. § 1332.

Before the district court, ITS argued that the Lease unambiguously required VASP to (1) repair any and all damage to the engine; (2) make monthly lease payments while the engine remained in VASP’s possession; and (3) return the engine to ITS in operable condition upon termination of the Lease. VASP acknowledged it did not repair or return the engine and did not make lease payments after September 1998. The district court agreed the Lease was unambiguous and concluded VASP received the bargained for consideration. Accordingly, the court granted ITS’ motion for summary judgment on its breach of contract claim, dismissed VASP’s counterclaim, and awarded ITS damages and prejudgment interest. Specifically, the district court awarded damages in the amount of $2.4 million, the cost to repair the engine, and $1,425 million, the total past-due lease payments. *497 The court awarded prejudgment interest on the entire damage award at a rate of ten percent per annum.

On appeal, VASP asserts the district court improperly granted summary judgment because (1) the Lease did not unambiguously assign responsibility for engine damage caused by the failure of an on-condition part; 2 and (2) a genuine issue of material fact exists as to whether VASP received the bargained-for consideration. In addition, VASP asserts the district court erred in calculating prejudgment interest.

II.

We review a grant of summary judgment de novo, applying the same standard as the district court. Roberts v. Cardinal Services, 266 F.3d 368, 373 (6th Cir.2001). A motion for summary judgment is properly granted only if no genuine issue of material fact exists and the moving party is entitled to judgment as a matter of law. Id.

A.

In construing a contract under Texas law, courts must examine and consider the entire writing and give effect to all provisions such that none are rendered meaningless. Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983). Where the contract language is clear and definite, the contract is not ambiguous and the court must apply the plain language as a matter of law. DeWitt County Elec. Co-op., Inc. v. Parks, 1 S.W.3d 96, 100 (Tex.1999). A contract term is not ambiguous merely because the parties to an agreement proffer conflicting interpretations of a term. Id. An ambiguity arises only where the agreement is reasonably susceptible to more than one interpretation. Id.

The Lease provides, in relevant part: During the Lease Term, Lessee will at its cost and expense, repair and maintain the Engine in accordance with Operator’s FAA approved Part 121 Maintenance Program or equivalent (which Lessee represents Operator has) so as to keep the Engine in as good operating condition as when delivered to Lessee, reasonable wear and tear excepted. .... Lessee shall assume and bear risk of loss and damage to the Engine and all component parts from any and every cause whatsoever, except that Lessor will be responsible for any required shop visit to cover the overhaul and repair of time-controlled components, parts and on-condition components or parts, which were not damaged by reason of the act or omission of Lessee (emphasis added).

The parties agree that an HPT blade is an “on-condition” part and that the failure of an HPT blade caused the engine damage. VASP asserts that under the terms of the Lease, ITS bears responsibility for any damage caused by the failure of a time-controlled or on-condition part. 3

*498

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
278 F.3d 494, 2002 U.S. App. LEXIS 90, 2002 WL 15514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-turbine-services-inc-v-vasp-brazilian-airlines-ca5-2002.