International ProcessPlants and Equipment Corp. v. Harris

CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 6, 2025
Docket2:22-cv-01630
StatusUnknown

This text of International ProcessPlants and Equipment Corp. v. Harris (International ProcessPlants and Equipment Corp. v. Harris) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International ProcessPlants and Equipment Corp. v. Harris, (E.D. Pa. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

INTERNATIONAL PROCESSPLANTS CIVIL ACTION AND EQUIPMENT CORP., Plaintiff, v. NO. 22-01630 FIRST STANDARD ASURETY, LLLP; DAVID HARRIS; METRO INDUSTRIAL WRECKING & ENVIRONMENTAL CONTRACTORS, INC.; MIWEC ASSET RECOVERY, INC.; RINO ROTONDO; AMERICAN EAGLE SERVICES GROUP, INC.; and PAUL MAUCHA, Defendants. Hodge, J. March 6, 2025 MEMORANDUM I. INTRODUCTION Plaintiff International ProcessPlants and Equipment Corp. (“IPP”) commenced this action against Defendants First Standard Asurety, LLLP (“FSA”), FSA owner David Harris, Metro Industrial Wrecking & Environmental Contractors, Inc. (“Metro”), MIWEC Asset Recovery, Inc. (“MIWEC”), Metro and MIWEC owner Rino Rotondo, American Eagle Services Group, Inc. (“AESG”), and AESG owner Paul Maucha (collectively “Defendants”), asserting claims for civil Racketeer Influenced and Corrupt Organizations Act (“RICO”) violations under 18 U.S.C. §§ 1961-1968 and common law fraudulent inducement and conversion. (ECF No. 23.) After failing to respond to IPP’s Amended Complaint, defaults were entered against Defendants AESG and Rotondo. (ECF Nos. 27, 28.) FSA and Harris (together “the FSA Defendants”) and Metro, MIWEC, and Rotondo (together “the Metro Defendants”) then filed separate Rule 12(b)(6) Motions to Dismiss for Failure to State a Claim. (ECF Nos. 36, 40.) The Metro Defendants also filed a Motion to Vacate the default entered against Rotondo and a Motion to Dismiss for Improper Venue or Transfer pursuant to FRCP 12(b)(3) and 28 U.S.C. §1404(a), and for failure to state a claim pursuant to FRCP 12(b)(6). (ECF No. 40.)

The Court having considered the motions and all responses thereto orders that: the FSA Defendants’ Motion to Dismiss (ECF No. 36) is denied; Defendant Rotondo’s Motion to Vacate the Default is denied; the Metro Defendants’ Motion to Dismiss for Improper Venue or Transfer (ECF No. 40) is denied; and the Metro Defendants’ Motion to Dismiss for failure to state a claim is granted. As to the claims against the Metro Defendants, the RICO claim (Count I) and Fraudulent Inducement claim (Count II) are dismissed without prejudice. IPP’s Conversion claim against the Metro Defendants (Count III) is dismissed with prejudice. II. FACTUAL BACKGROUND1 At the Motion to Dismiss stage, the Court must take Plaintiff’s allegations as true. IPP describes the facts as follows. This dispute arises out of a demolition project at the site of a former

chemical manufacturing plant located at 900 River Road, Conshohocken, Pennsylvania (the “Project”). (ECF No. 23 ¶ 18.) IPP entered into a contract with the owner of the plant facility, under which IPP agreed to purchase and remove items including salvageable equipment, spare parts, and accessories, and to demolish the buildings, infrastructure, and structures at the site. (Id. ¶ 19.) On or about November 26, 2019, IPP entered into a subcontract with Metro (the “Subcontract”), under which Metro agreed to perform the dismantling, rigging, removal, and loading of equipment from the site, as well as the scrapping and demolition of the buildings, infrastructure, and structures, in exchange for payment of $100,000 to IPP and Metro’s retention

1 The Court adopts the pagination supplied by the CM/ECF system. of scrap salvage rights. (Id. ¶ 20.) In order to secure Metro’s obligations under the Subcontract, Metro was required to procure a performance bond and a payment bond for IPP’s benefit, at Metro’s own cost and expense. (ECF No. 23-1 at 10.) On or about December 17, 2019, Metro procured these bonds—an AIA Document A312 – 2010 Performance Bond (the “Performance

Bond”) and an AIA Document A312 – 2010 Payment Bond (the “Payment Bond”)—from FSA. (ECF No. 23 ¶ 22.) IPP claims that throughout the course of the Project, Metro consistently failed to complete its work in a timely manner and in compliance with the Subcontract. (ECF No. 23 ¶ 23.) Metro’s breaches of the Subcontract included failing to provide proper equipment; using faulty, worn equipment; failing to provide a qualified labor force; failing to employ competent project managers; failing to adhere to the project schedule and causing delays; and failing to fulfill required payments to subcontractors and suppliers. (Id. ¶ 24.) When IPP informed Metro of its breaches, Metro failed to remedy or cure the breaches, or even respond to IPP’s communications. (Id. ¶ 25.) Due to Metro’s breaches, IPP exercised its rights under the Subcontract to terminate

Metro for default. (Id. ¶ 26; see also ECF No. 23-3 at 2.) IPP then filed the Demand for Arbitration against Metro with the American Arbitration Association (“AAA”), as required under the Subcontract. (ECF No. 23 ¶ 27; ECF No. 23-1 at 16.) The Arbitration was captioned AAA case no. 01-20-0019-3703. (ECF No. 23 ¶ 27.) On or about December 3, 2019, IPP sent FSA, Metro’s surety, a formal Notice of Claim under the Performance Bond, demanding that FSA reimburse IPP $759,628.36 to remedy Metro’s material breaches. (ECF No. 23 ¶¶ 28-29.) The damages included “the unpaid balance due IPP for (supplemental) work performed and invoiced; the unpaid balance due Metro’s subcontractor IPE Rigging for work performed and invoiced; and the unpaid balance due Metro’s subcontractor People’s and Sons for work performed and invoiced.” (ECF No. 23 ¶ 30.) IPP also demanded that FSA indemnify and hold harmless IPP for other costs, damages, and expenses that resulted from Metro’s breaches. (Id. ¶ 31; see also ECF No. 23-4 at 3.) IPP later amended the amount of damages to $459,830.44, when Metro’s unpaid subcontracts declined to file mechanics’ liens by the

statutory deadline. (ECF No. 23 ¶ 32.) FSA did not respond to IPP’s notices or otherwise communicate with IPP until January 31, 20212—more than a year after IPP sent FSA its initial Notice of Claim—when FSA sent IPP an email denying IPP’s claim under the Bond. (ECF No. 23 ¶ 33; see also ECF No. 23-5 at 2.) According to IPP, the denial letter included “demonstrably false” statements, and mischaracterized express provisions of the Subcontract as well as the Performance Bond itself. (ECF No. 23 ¶ 34.) IPP identifies one such mischaracterization in its amended complaint— “FSA stated that the Subcontract required IPP to remit payment to Metro (in the amount of $700,000.00), but rather it was Metro who paid IPP $100,000.00, in exchange for scrap salvage rights on the Project.” (Id.) In addition, FSA questioned IPP’s qualifications under the Payment Bond, despite IPP bringing its

claims under the separate Performance Bond. (Id. ¶ 35.) On February 4, 2021, IPP filed a complaint in the Eastern District of Pennsylvania against FSA; that case (Civil Action No. 2:21-cv-00525) was stayed when FSA agreed to participate in the AAA arbitration. (Id. ¶ 36.) On or about April 27, 2021, the United States Department of Justice filed an indictment against Defendant Paul Maucha, the owner, agent and trustee of Defendant AESG, alleging that through AESG, Maucha committed criminal acts including offering fraudulent surety bonds. (ECF No. 23 ¶¶ 15-16, 37; ECF No. 23-6.) Under the scheme, “Mr. Maucha and AESG ‘committed to pay out on the surety bond to a third-party beneficiary if the purchaser of the bond failed to meet

2 The email from FSA referenced in the complaint is dated January 29, 2020. (ECF No. 23-5 at 2.) This appears to be a typo in the original email; the year included in the email should have been 2021.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hemi Group, LLC v. City of New York
559 U.S. 1 (Supreme Court, 2010)
Koster v. (American) Lumbermens Mutual Casualty Co.
330 U.S. 518 (Supreme Court, 1947)
United States v. Turkette
452 U.S. 576 (Supreme Court, 1981)
Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Sedima, S. P. R. L. v. Imrex Co.
473 U.S. 479 (Supreme Court, 1985)
Reves v. Ernst & Young
507 U.S. 170 (Supreme Court, 1993)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Boyle v. United States
556 U.S. 938 (Supreme Court, 2009)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
EBC, Inc. v. Clark Building System, Inc.
618 F.3d 253 (Third Circuit, 2010)
Santiago v. Warminster Township
629 F.3d 121 (Third Circuit, 2010)
Karen Malleus v. John George
641 F.3d 560 (Third Circuit, 2011)
Tabas v. Tabas
47 F.3d 1280 (Third Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
International ProcessPlants and Equipment Corp. v. Harris, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-processplants-and-equipment-corp-v-harris-paed-2025.