International Paving Systems, Inc. v. Van-Tulco, Inc.

866 F. Supp. 682, 1994 U.S. Dist. LEXIS 15078, 1994 WL 578592
CourtDistrict Court, E.D. New York
DecidedOctober 11, 1994
Docket88-CV-1066 (DRH)
StatusPublished
Cited by26 cases

This text of 866 F. Supp. 682 (International Paving Systems, Inc. v. Van-Tulco, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Paving Systems, Inc. v. Van-Tulco, Inc., 866 F. Supp. 682, 1994 U.S. Dist. LEXIS 15078, 1994 WL 578592 (E.D.N.Y. 1994).

Opinion

MEMORANDUM AND ORDER

HURLEY, District Judge.

In these consolidated cases regarding the rights and obligations of the parties to several contracts for the renovation of the St. George Ferry Terminal in Staten Island, New York, the parties have moved for various forms of pre-trial relief, including summary judgment, amendment of the complaints, and impleader of additional parties. For the reasons set forth below, these motions are denied in part and granted in part.

Background

In June of 1983, the City of New York (the “City”) entered into a contract with Berger, Lehman Associates, P.C. (“Berger Lehman”), pursuant to which Berger Lehman was to design and plan the work for a construction project (the “Project”) involving the renovation of the bus ramps at the St. George Ferry Terminal in Staten Island, New York. A few weeks later, the City, acting through the New York City Department of Transportation, entered into a contract with VanTulco, Inc. (“Van-Tulco”), whereby Van-Tulco would be the general contractor for the Project.

As part of Van-Tulco’s contract with the City, Van-Tulco was required to furnish and deliver a labor and material payment bond. Van-Tulco delivered such a bond, with VanTulco acting as principal and Reliance Insurance Company of New York, Rebanee Insurance Company, American Reinsurance Company, North American Reinsurance Corporation, and Employers Reinsurance Corporation acting as joint and co-sureties. According to the terms of the bond, Van-Tulco and the co-sureties became jointly and severally bable for the payment of all persons, firms, suppbers, subcontractors and corporations furnishing materials for or performing labor within the purview of the contract between Van-Tulco and the City.

Van-Tulco entered into a subcontract with AVA Construction, Inc. (“AVA”), whereby AVA was to supply and install latex modified concrete (“latex concrete”) on the ramps of the ferry terminal. AVA, in turn, entered into an agreement with International Paving Systems, Inc. (“International Paving”), as sub-subcontractor, pursuant to which International Paving was to supply the latex concrete for the Project.

Shortly after its installation, certain portions of the latex concrete showed signs of cracking and delamination. As a result, the *686 City is currently withholding payment of an outstanding contract balance to Van-Tulco pending a judicial determination of, inter alia, the cause of the cracking and delamination.

In early 1988, International Paving commenced an action against Van-Tulco and the co-sureties to recover pursuant to the payment bond. In this action, International Paving is seeking monies that AVA allegedly failed to pay pursuant to the sub-subcontract for the latex concrete. Subsequently, in 1990, Donald J. Crecca, as trustee in bankruptcy for AVA, sued Van-Tulco for monies due under its subcontract for the supply and installation of the latex concrete. In this second action, Van-Tulco asserted a counterclaim and offset against AVA on the ground that the cracking and delamination of the latex concrete was due to defects in the workmanship and materials furnished by AVA. Van-Tulco also brought a third-party action against the City asserting that VanTulco installed the latex concrete in accordance "with the plans and specifications for the Project but that those plans and specifications were defective. Van-Tulco seeks to recover monies due under its general contract with the City, including monies owed for the concrete work on the Project. The City, in turn, brought a fourth-party action against Berger Lehman, asserting that if the plans and specifications were defective, it is the responsibility of Berger Lehman. The main claim in this action between AVA and Van-Tulco has been discontinued pursuant to a settlement, but Van-Tulco’s counterclaims against AVA and the third- and fourth-party actions remain pending. Pursuant to this Court’s Order dated November 10, 1992, the two actions were consolidated. 806 F.Supp. 17.

Discussion

I. Motion by the City to Dismiss the Third-Party Action for Lack of Subject Matter Jurisdiction

At the outset, the Court considers the City’s contention that the Court lacks subject matter jurisdiction over Van-Tulco’s third-party action against the City. To properly address this claim, the Court must first address whether the City was properly impleaded in this action.

A. Propriety of Impleader

In support of its motion to dismiss the third-party action, the City contends that its impleader was improper under Federal Rule of Civil Procedure 14(a). (City Reply Mem. at 5-12.) Rule 14(a) provides in relevant part that

[a]t any time after commencement of the action a defending party, as a third-party plaintiff, may cause a summons and complaint to be served upon a person not a party to the action who is or may be liable to the third-party plaintiff for all or part of the plaintiffs claim against the third-party plaintiff.

Fed.R.Civ.P. 14(a) (emphasis added). The general purpose of Rule 14(a) is to serve judicial economy, discourage inconsistent results, and limit the prejudice incurred by a defendant by removal of the time lag between a judgment against the defendant and a judgment over against a third-party defendant. Blais Constr. Co., Inc. v. Hanover Square Assocs.-I, 733 F.Supp. 149, 152 (N.D.N.Y.1990) (citing Dery v. Wyer, 265 F.2d 804, 806-07 (2d Cir.1959)).

It is well settled that, for impleader to be available, the third party defendant must be “liable secondarily to the original defendant,” or that “the third party must necessarily be liable over to the defendant for all or part of the plaintiffs recovery,” or that “the defendant must attempt to pass on to the third party all or part of the liability asserted against the defendant.” See, e.g., United States v. Joe Grasso & Son, Inc., 380 F.2d 749, 751-52 (5th Cir.1967) (emphasis in original) (citations omitted). “Whichever expression is preferred, it is clear that impleader under Rule 14 requires that the liability of the third party be dependent upon the outcome of the main claim.” Id. at 752 (emphasis added).

Because the third-party claim must be “dependent” upon the original claim, “there must be a more than tenuous relationship between the main and third-party claims,” National Union Fire Ins. Co. of *687 Pittsburgh, PA v. Gordon, No. 87 Civ. 7695, 1991 WL 4753, at *7 (S.D.N.Y. Jan. 14,1991), and “[t]he mere fact that the alleged third-party claim arises from the same transaction or set of facts as the original claim is not enough.” 6 Charles A. Wright, Arthur R. Miller & Mary K. Kane, Federal Practice and Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davidson v. Paige
D. Hawaii, 2021
Odyssey Reinsurance Co. v. Cal-Regent Insurance Services Corp.
123 F. Supp. 3d 343 (D. Connecticut, 2015)
Ibasis Global, Inc. v. Diamond Phone Card, Inc.
278 F.R.D. 70 (E.D. New York, 2011)
Luyster v. Textron, Inc.
266 F.R.D. 54 (S.D. New York, 2010)
Falcone v. MarineMax, Inc.
659 F. Supp. 2d 394 (E.D. New York, 2009)
E.I. DuPont De Nemours & Co. v. Kolon Industries, Inc.
688 F. Supp. 2d 443 (E.D. Virginia, 2009)
Scd Rma, LLC v. Farsighted Enterprises, Inc.
591 F. Supp. 2d 1141 (D. Hawaii, 2008)
Winbco Tank Co. v. Palmer & Cay of Minnesota, LLC
435 F. Supp. 2d 945 (S.D. Iowa, 2006)
Doucette v. Vibe Records, Inc.
233 F.R.D. 117 (E.D. New York, 2005)
Pfizer, Inc. v. Stryker Corp.
348 F. Supp. 2d 131 (S.D. New York, 2004)
Siemens Westinghouse Power Corp. v. Dick Corp.
299 F. Supp. 2d 242 (S.D. New York, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
866 F. Supp. 682, 1994 U.S. Dist. LEXIS 15078, 1994 WL 578592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-paving-systems-inc-v-van-tulco-inc-nyed-1994.