International Fidelity Insurance Co. v. Americaribe-Moriarty JV

192 F. Supp. 3d 1326, 2016 U.S. Dist. LEXIS 92559, 2016 WL 3647668
CourtDistrict Court, S.D. Florida
DecidedJune 22, 2016
DocketCase No. 15-24183-Civ-COOKE/TORRES
StatusPublished
Cited by3 cases

This text of 192 F. Supp. 3d 1326 (International Fidelity Insurance Co. v. Americaribe-Moriarty JV) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Fidelity Insurance Co. v. Americaribe-Moriarty JV, 192 F. Supp. 3d 1326, 2016 U.S. Dist. LEXIS 92559, 2016 WL 3647668 (S.D. Fla. 2016).

Opinion

ORDER ON CROSS MOTIONS FOR SUMMARY JUDGMENT

MARCIA G. COOKE, United States District Judge

Plaintiffs International Fidelity Insurance Company and Allegheny Casualty Company (collectively “IFIC”) bring this action for a declaratory judgment that Defendant Americaribe-Moriarty JV (“AMJV”) failed to satisfy the conditions precedent to assert a claim- against the performance bond issued by IFIC, and that AMJV materially breached the performance bond, rendering it null and void. [1328]*1328See generally Compl., ECF No. 1. In response, AMJV asserts a counterclaim against IFIC alleging that IFIC breached the performance bond by refusing to remedy the subcontractor’s default or to arrange for the performance of the subcontractor’s obligations under the subcontract. See generally Countercl., ECF No. 12.

AMJV filed a Motion for Summary Judgment with Integrated Memorandum of Law in Support (ECF No. 39), to which IFIC filed their Response in Opposition' to Defendant’s Motion for Summary Judgment (ECF No. 53), and AMJV filed its Reply to Plaintiffs Opposition Response Regarding Defendant’s Motion for Summary Judgment (ECF No. 62). IFIC filed their own Motion for Final Summary Judgment and Supporting Memorandum of Law (ECF No. 51) and Statement of Undisputed Material Facts in Support of Final Motion for Summary Judgment (ECF No. 52), to which AMJV filed its Response in Opposition to Plaintiffs’ Motion for Final Summary Judgment (ECF No. 63) and Statement of Material Facts in Opposition to Plaintiffs’ Motion for Summary Judgment (ECF No. 61), and IFIC filed their Reply to Defendant’s Response in Opposition to Plaintiffs’ Motion for Final Summary Judgment (ECF No. 69).

I have reviewed both AMJV’s and IFIC’s Motions for Summary Judgment and accompanying attachments, the Responses and Replies thereto and accompanying attachments, the record, and the relevant legal authorities. I agree that AMJV materially breached the performance bond, rendering it null and void. As such, IFIC’s Motion for Final Summary Judgment is granted and AMJV’s Motion for Summary Judgment is denied.

I. BACKGROUND

On February 26, 2014, AMJV, as general contractor, entered into a written subcontract agreement with Certified Pool Mechanics 1, Inc. (“CPM”), as subcontractor, to perform certain pool work at a project commonly known as Brickell City Centre Super Structure, located at 700 Brickell Avenue, Miami, Florida. Pis.’ Statement Undisputed Material Facts ¶ 1, ECF No. 52. On April 1, 2014, IFIC issued a performance bond in connection with the subcontract on behalf of CPM, as principal, and AMJV, as obligee. Id. at ¶ 2,

On July 15, 2015, AMJV sent CPM a letter outlining various issues with CPM’s work regarding the “East Block Pool Installation” and formally notified CPM of its default pursuant to Paragraph 11.2(a) of the subcontract. See ECF No. 52-4. AMJV further informed CPM that it had three working days to cure the default. See id. However, on August 17, 2015, AMJV sent a letter to both CPM and IFIC to advise IFIC of CPM’s “serious project delay and poor performance” and to “request[] an immediate conference call with [IFIC] to substitute CPM’s scope at the East Hotel pools with an alternative subcontractor^]” See ECF No. 52-5. In response, in a letter to AMJV dated August 20, 2015, IFIC listed its availability for a conference call, informed AMJV of its attempts to “communicate with the appropriate representative of [its] principal to investigate the facts and circumstances concerning this matter,” requested further information from AMJV, and warned AMJV “not to take any steps with respect to the completion of the project” without IFIC’s prior consent. See ECF No. 52-6.

The parties, including CPM,’conducted a telephone conference on September 2, 2015 to discuss CPM’s performance under the subcontract. Pis.’ Statement. Undisputed Material Facts ¶ 8. Subsequently, IFIC mailed AMJV a letter dated September 15, 2015. In that letter, IFIC informed AMJV that they were in the process of reviewing the information provided by AMJV re[1329]*1329garding CPM’s default, but that the information provided was incomplete, See ECF No. 52-7. IFIC also noted that the completion date of the project had been “altered significantly from the baseline schedule” and that “the duration of [CPM’s] activities [had] been significantly reduced,” lending credence to CPM’s argument that the schedule was impacted due to events beyond CPM’s control. Id. As such, IFIC alerted AMJV that it needed “to better understand whether the impacts to the schedule [were] the result of CPM or the result of predecessor activities over which CPM [had] no control,” requested a reply and further information from AMJV, and reminded AMJV that any attempt to complete the bonded work- using another subcontractor would be a violation of the bond. Id. However, on September 16, 2015, AMJV obtained a proposal from a new potential subcontractor, Dillon Pools, Inc. (“Dillon Pools”), to complete the remaining scope of the subcontract. See ECF No. 52-9. Additionally, in an email exchange dated September 17, 2015, AMJV and Dillon Pools established a “presumed starting date” of September 21, 2015. See ECF No. 52-10.

In a letter dated September 21, 2015, which was addressed to both IFIC and CPM, AMJV officially declared CPM in default, terminated the subcontract, and made a demand upon IFIC to perform under the performance bond, pursuant to Sections 3.2 and 3.3 of the performance bond and Paragraph 12.2(a) of the subcontract. See ECF No. 52-8. Then, on September 22, 2015, AMJV sent IFIC a letter stating that it “intend[ed] to award the subcontract to complete the remaining work ... to Dillon Pools, Inc.” ECF No. 52-11. In that same letter, AMJV asked that IFIC “provide all necessary lists of material, delivery dates and pricing to Dillon Pools as enquired in their effort to complete the Pool scope of work for the project.” Id. As of September 23, 2015, Dillon Pools “commenced performing supplementation work and on site investigations to determine corrective work required for the project ...” ECF No. 52-12.

In a letter dated September 29, 2015, IFIC acknowledged receipt of AMJV’s letter declaring CPM in default, requested that AMJV provide them with the information they had previously requested in order to further their investigation, reminded AMJV not to take any steps with respect to completion of the project without IFIC’s consent, and informed AMJV of their desire to conduct a-site visit on October 1, 2015. See ECF No. 52-13. However, in a letter dated October 1, 2015, AMJV requested that IFIC “immediately arrange for a contract to be prepared for execution by [AMJV] and a contractor selected with ' [AMJVs] concurrence” as IFIC were “not licensed or qualified to perform and complete the Construction Contract (§ 5.2)” and AMJV “[would] not consent for CPM to perform and complete thé Construction Contract (§ 5.1).” ECF No. 52-14 (emphasis omitted). AMJV also stated that its letter served as “AMJV’s additional written notice to [IFIC] demanding that [IFIC] perform its obligations under [the] Bond within seven days.” Id.

In a contract dated October 1, 2015 between AMJV, as contractor, and Dillon Pools, as subcontractor, Dillon Pools agreed “to furnish all labor, material, equipment, layout, etc., necessary for the complete performance of the Swimming Pools and Spa Work not completed by Certified Pool Mechanics 1, Inc. (CPM).” ECF No. 61-5 at 8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wildewood Operations v. WRV Holdings
Court of Special Appeals of Maryland, 2023

Cite This Page — Counsel Stack

Bluebook (online)
192 F. Supp. 3d 1326, 2016 U.S. Dist. LEXIS 92559, 2016 WL 3647668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-fidelity-insurance-co-v-americaribe-moriarty-jv-flsd-2016.