International Contract Co. v. City of Seattle

127 P. 115, 70 Wash. 504, 1912 Wash. LEXIS 1075
Washington Supreme Court·Decided October 14, 1912·No. No. 10002·Published·Cited by 1 cases

Opinion

Ellis, J.

This is an action for a writ of mandate, to require the proper officers of the city of Seattle to allow and pay certain items as extras under a contract of relator with the city. The cause was tried to the court without a jury. After a full hearing upon the evidence, the court dismissed the action at the relator’s costs. The relator has appealed.

On September 24, 1909, the respondent, pursuant to certain ordinances duly passed, entered into a contract with the appellant for the construction of a concrete lining for the Green Lake low service reservoir, called the “lower reservoir,” and for the Green Lake intermediate service reservoir, called the “upper reservoir.” • The earthwork for both reservoirs had previously been performed by other [506]*506contractors under a separate contract. According to the contract here involved, the concrete lining was to consist of a bottom course or base and a top course or mortar surface. The base was to be six inches thick, and was to consist of one part cement, three parts sand, and five parts gravel, known as a 1:3:5 aggregate. The mortar surface was to be one inch thick, and consist of one part cement to one part sand, or a 1:1 aggregate. Under the contract, the total thickness of the lining would therefore be seven inches. In case of back filling made necessary by depressions or channels, the concrete filling was to be a 1:4:8 aggregate. The contract contained specific provisions for excavation, concrete filling, redressing slopes, and for extra work. These provisions were as follows:

“Excavation: The contractor shall make such excavation as may be necessary to bring the surface on which the concrete lining is to be placed to a true form and grade to receive the lining. Material necessarily excavated for this purpose shall be removed from the reservoir basin and deposited on the adjacent grounds at such locations as ordered by the engineer in charge. The price bid for excavation per cubic yard shall include excavating, loading, hauling, and dumping as above specified. Particular attention is called to the necessity of accurately finishing the surface to be concreted, and no extra yardage in concrete will be allowed for filling areas excavated below grade, unless such excavation below grade is ordered by the engineer in charge.
“Concrete Filling: When so ordered by the city engineer, channels or depressions eroded in the sides and bottoms of the reservoir basins shall be refilled with concrete which shall be mixed in the proportions of one part of cement to four parts of sand and eight parts of gravel. Concrete filling will be paid for at the rate bid therefor per cubic yard in place.
“Redressing Slopes: When it is necessary in the opinion of the city engineer to redress or repair the surface of the slopes of the reservoir it shall be done by the contractor before the concrete lining is placed thereon. Such redressing or repairing of slopes will be paid for at the rate bid therefor per square yard, such payment to be in full for performing [507]*507the work and maintaining it in condition until the concrete is placed thereon. Redressed or repaired slopes shall be in all respects as firm and true to grade as the original.”

The contract also provided:

“Contractors must base their proposals on the basis of the quantities hereinafter given, but as these quantities are only approximate and not guaranteed to be correct, and intended only as a basis for the comparison of bids, payment will be made only for actual amount of work done and material furnished, whether it be more or less than the estimated amount.”

The contract was let to the appellant at rates and on approximate estimates as follows: Lower reservoir concrete filling, 9,500 cubic yards, $9.08 per cubic yard; redressing slopes, 2,000 square yards, one dollar per square yard; excavation, 800 cubic yards, fifty cents per cubic yard. Upper reservoir concrete lining, 9,500 cubic yards, $9.18 per cubic yard; redressing slopes, 200 square yards, one dollar per square yard; excavation, 800 cubic yards, fifty cents per cubic yard. The appellant seeks to recover for four items of labor and material furnished in the work claimed as extras, which the respondent has refused to allow.

(1) The first item was for redressing the bottom of the upper reservoir to the extent of 28,248 square yards. The appellant claims that this was extra work for which fifteen cents a square yard was a reasonable price, at which rate this work would amount to $8,487.20. The respondent claims that this was covered by the contract as excavation. Computed as such, there were 259 cubic yards. The city paid for this at the contract rate for excavation of fifty cents per cubic yard, amounting to $129.50. The appellant, therefore, claims a balance for this item of $8,857.70. The contract must be construed with reference to the condition of the subject-matter at the time it was let. It is admitted that the contract, plans, and specifications contain no provision for redressing the bottom of either reservoir. The reason for this, as is clearly shown by the evidence, was that, at the [508]*508time the bids were called for, the bottoms of the basins were supposed to be already smooth, level, and down to grade. The evidence also shows that the reason for inserting the provision as to redressing the slopes was that the slopes of the lower reservoir, having passed through a winter after completion, were eroded, and when the contract was let in September, 1909, it was apparent that these slopes would have to be redressed before receiving the lining. The work of lining the upper reservoir was commenced by the appellant soon after the contract was let. About fourteen per cent of the bottom of this basin was completed before the work was interrupted by the winter rains, and no claim was made for redressing the bottom as to that part, nor for any redressing prior to March 1, 1910. This also tends to show that no redressing was necessary when the contract was let. The respondent claimed that, whatever redressing was done for this fourteen per cent was largely necessitated by the cutting up of the bottom by the appellant’s teams being driven over it in rainy weather, and this seems to have been reluctantly conceded by the appellant. There was evidence that, when the work was resumed in the spring, the slopes had been more or less eroded; that the bottom had soft spots produced by water standing upon it; that rains and freezing had heaved the surface; and that the bottom had been to some extent disturbed by the progress of the work during rainy weather. We think that, on the evidence, the court would have been justified in finding that the leveling of the bottom was rendered necessary mainly by these causes. The contract, apparently in anticipation of such contingencies, provided:

“The contractor is to sustain, without claim against the city, all losses or damages to the work to be done under these specifications, arising from the action of the elements, ,or from any unforeseen obstruction or incumbrances on the line of work, which may be encountered in the prosecution of the same.”

[509]*509It is manifest that the appellant was not entitled to have work so necessitated treated as extra work under the contract. Much testimony of contractors and engineers was admitted on both sides as to whether the leveling of the bottom under a contract such as this should be considered as excavation or as redressing.

Free access — add to your briefcase to read the full text and ask questions with AI

International Contract Co. v. City of Seattle, 127 P. 115, 70 Wash. 504, 1912 Wash. LEXIS 1075 (Wash. 1912).

127 P. 115 (International Contract Co. v. City of Seattle) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wilson v. Salt Lake City
174 P. 847 (Utah Supreme Court, 1918)