International Bow & Stern Dock Co. v. United States

60 F. 523, 1894 U.S. App. LEXIS 2738
U.S. Circuit Court for the District of New Jersey·Decided March 16, 1894·Published·Cited by 1 cases

Opinion

DALLAS, Circuit Judge.

This suit was brought by petition of the International Bow & Stem Dock Company, filed under and in pursuance of the act of congress approved March 8, 1887, entitled “An act to provide for the bringing of suits against the government of the United States.” To this petition the United States, by Henry S. White, Esq., the United States attorney for the district of New Jersey, duly made answer in writing, and thereupon, on February 20, 1894, the cause was, in accordance with said act, tried by the court without a jury. The evidence adduced, and the arguments of counsel, have since been fully considered, and this opinion is now filed under the terms of the seventh section of the same statute.

First. Specific Findings of the Facts.

(1) The petitioner and the United States. entered into a written contract, dated February 25, 1889, by which the former agreed to deliver at the naval station, Key West, Fla., within six months from the date of the contract (excluding the months of July, August,. and September), in accordance with the plans and specifications' thereto appended and made part of the contract, “one adjustable floating stern dock,” for the sum of $30,000, to be paid in certain specified installments as the work progressed, and by a final payment of $3,000, to be made “upon the delivery of the dock, ■ready in all respects for use, after a satisfactory test, to the commanding officer of the naval station at Key West, Fla.” The only portion of the “specifications” to which it is necessary to refer is in these words:

“Dock to be tested where built, or at Key West, at the option of the government. A suitable vessel, approved by the contractors, to be furnished by the government at the port where dock is to be tested, within two months after being notified that dock is completed, and ready to be- tested. Dock to be delivered at Key West, and to be at contractor’s risk while in transit. Satisfactory test to mean placing the dock under stern of the ship fur-nishred,. and removing the water down to the keel. Officers and crew of the vessel' to render proper assistance. Contractors to be allowed to build on government land, and to have the use of tools and machinery belonging to the government at the naval station where built, free of cost to them. Coal .and water for testing purposes to be supplied by the government.”

[525] (2) Apart from the matters of fact reserved for separate statement in the following paragraphs of these findings, the petitioner complied with the said contract, and did and performed all things on its part to be done and performed according to the provisions thereof; and it was paid by the government the sum of $30,000, which was the total amount agreed to be paid to it, with the exception of the final balance of $3,000, which, under the terms of the contract, was to be paid upon delivery and satisfactory test of the dock. The government has the actual possession of the dock, but has always refused, and still does refuse, to “accept” it. This unpaid balance of $3,000 constitutes the petitioner’s claim in this suit.

(3) The structure erected by the petitioner under the contract is, in fact, an “adjustable floating stern dock.” It is a dock which is “adjustable” according to the meaning of that word as' used in the contract.

(4) On May 3, 1890, the petitioner notified the United States, in writing, that the dock was at Key West, “completed and ready to be tested,” but it has been admitted that the time for testing was extended, and that at the expiration of the last period of extension, to wit, in January, 1891 (no testing having been made), the dock was formally tendered, and demand made for payment of the balance of $3,000, which was refused.

(5) Within the period allowed for testing as aforesaid, the government offered to furnish any one of four specified vessels, either of which, as it claimed, and still claims, was a “suitable vessel” to be used for testing. One of these vessels, but not any of the others,' was “approved by the contractors.” The vessel approved was the Baltimore. It was offered by Rear Admiral Gherardi, whose orders were that he was to supply a ship of his squadron, to be docked for the final testing of the dock. This offer was, however, not acted upon, because it was withdrawn in pursuance of an order of the secretary of the navy, who deemed it inexpedient to employ the Baltimore in the manner proposed. No more particular reason was assigned, or has been shown, for this withdrawal The declination of the plaintiff to approve any other of the vessels which were offered by the government was not capricious, groundless, or unreasonable. In addition to the Baltimore, the Philadelphia and the Chicago were designated by the plaintiff as vessels which it was willing to approve. The dock (as had been contemplated by both parties) was constructed with especial and immediate reference to a certain class of vessels. Those which, were offered and refused were not of that class, and to, have prepared the dock for testing under any one of them would have involved the plaintiff in very considerable expense for necessary adjustment and ballast. 1 ,

Second. Conclusions of Law.

1. That the correct construction of the contract in suit, with regard to the only question which has been raised on that subject, is that the, dock was to be “adjustable,” not automatically,1 but by cutting away and filling in the gates so as to conform their. [526] outline to tbe contour of the hull of any vessel proposed to 'be docked.

2. That the plaintiff having duly offered the dock for testing, and the government having failed, during the time limited by the contract as extended, to furnish for that purpose any vessel which the plaintiff approved, or was bound to approve, and the plaintiff having, at the expiration of that time, formally tendered the dock, the latter did all that, under the circumstances, it was necessary for it to do to entitle it to the final payment of $3,000, and to the judgment in its favor to be rendered at the conclusion of this opinion.

Third. General Observations.

Free access — add to your briefcase to read the full text and ask questions with AI

International Bow & Stern Dock Co. v. United States, 60 F. 523, 1894 U.S. App. LEXIS 2738 (circtdnj 1894).

60 F. 523 (International Bow & Stern Dock Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sanderson v. Trump Manufacturing Co.
102 N.E. 2 (Indiana Supreme Court, 1913)