International Ass'n of Machinists & Aerospace Workers v. General Electric Co.

406 F.2d 1046, 70 L.R.R.M. (BNA) 2477, 1969 U.S. App. LEXIS 9189
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 27, 1969
DocketNo. 180, Docket 32399
StatusPublished
Cited by13 cases

This text of 406 F.2d 1046 (International Ass'n of Machinists & Aerospace Workers v. General Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
International Ass'n of Machinists & Aerospace Workers v. General Electric Co., 406 F.2d 1046, 70 L.R.R.M. (BNA) 2477, 1969 U.S. App. LEXIS 9189 (2d Cir. 1969).

Opinion

FEINBERG, Circuit Judge:

We have here another case involving whether a dispute between parties to a collective bargaining agreement is ar-bitrable. General Electric Company (“Company”) appeals from a decision of the United States District Court for the Northern District of New York, William H. Timbers, J.,1 ordering arbitration of a grievance brought by petitioners International Association of. Machinists and Aerospace Workers, AFL-CIO, and Auburn Electronics Local 967, International Association of Machinists and Aerospace Workers, AFU-CIO (“Union”). 282 F.Supp. 413 (N.D.N.Y.1968). For reasons set forth below, we affirm.

The facts are undisputed and relatively simple. On June 26, 1967, the Company announced that production at its plant in Auburn, New York, would be suspended for July 3, and that most employees should not report to work. On June 29, the Union filed a grievance, claiming a contract violation. After exhausting the grievance procedures, the Union in January 1968, invoking section 301 of the Labor Management Relations Act of 1947, 29 U.S.C. § 185, filed a petition in the district court to compel arbitration under section 4 of the United States Arbitration Act, 9 U.S.C. § 4. The primary basis of the Union’s grievance is that the Company violated Article IY, section 3, of the 1966-1969 labor agreement; that section requires the Company, before changing the “hours of work or working schedule of a substantial number of employees” to discuss the change with the Union and give one week’s notice thereof. The Company’s original response on the merits was that only a “temporary layoff” was involved; Article XII, section 1, of the contract appears to suggest that no notice is necessary as to such a layoff. There are other peripheral arguments in the controversy which need not be discussed in detail;2 the issue before us is not whether the Company breached the agreement, but whether the dispute is arbitrable.

As to that, the Company claims that the district court erroneously interpreted [1048]*1048Article XVI of the agreement, which deals with arbitration. The relevant portions of that Article require arbitration of an unsettled grievance, at the request of either party, provided it involves,

(a) the interpretation or application of any of the following provisions of this Agreement, except as otherwise specified:
******
Article IV, Working Hours, except as to issues involving the Company’s right to schedule shutdowns. [Emphasis added.] 3

According to the Company, the parties have thus excluded from arbitration all issues involving shutdowns; since a shutdown is involved here, that should end the case. The Union, however, argues that (1) the Company’s action was not a shutdown because concededly the entire plant was not closed on July 3, and (2) even if there was a shutdown, the Company’s violation of Article IV is nonetheless arbitrable. According to the Union, the effect of the exclusionary language of Article XVI quoted above is to make nonarbitrable only the Company’s right to shut down if it decides that exigencies demand it. On this theory, the Company’s decision to shut down the plant cannot be questioned in arbitration, but the consequences of the Company's action can be; e. g., did it violate other sections of the contract?

To resolve the issue of arbitrability, there is no need to rehearse the applicable law here at length; we have done so in the recent past. See, e. g., IUE v. General Electric Co., 407 F.2d 253 (2d Cir. 1968); ILA v. New York Shipping Ass’n, 403 F.2d 807 (2d Cir. 1968). It is enough to say that the authorities there quoted teach us that it is “national policy” to encourage arbitration of labor disputes, that doubts as to arbitrability should be “resolved in favor of coverage,” that language excluding certain disputes from arbitration must be “clear and unambiguous” or “unmistakably clear,” and that arbitration should be ordered “unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute.” This is an imposing litany for the Company to overcome. While the arbitration clause in the 1966-1969 agreement is not identical with the broad provisions contained in the now-familiar trilogy,4 the language is spacious enough. Moreover, the exclusionary clause exhibits what counsel for the Union at oral argument called “calculated ambiguity” on at least two issues: (1) What does “shutdown” mean; e. g., is it partial or total, and if the former, how much of a “shutdown” is required to qualify as such; and (2) even if a “shutdown” is involved, does the exclusion from arbitration of the Company’s “right to schedule shutdowns” also render non-arbi-trable an alleged breach of other sections of the agreement caused by the Company’s shutdown? We are by no means sure of the answers to these questions, and we certainly cannot say with the required “positive assurance” that the arbitration clause is not “susceptible” of the Union’s construction. Accordingly, we think that under the controlling authorities the district court correctly ordered arbitration.

The Company argues that the district court erred by failing to decide whether a shutdown had occurred. As to this, Judge Timbers said:

Aside from the belatedness of the company’s asserted claim that its July 3 action constituted a shutdown, it is doubtful that it was a shutdown with[1049]*1049in the meaning of the agreement; the company’s answer of August 6 referred to “a one day temporary lack of work in most areas of the Plant” (emphasis added); most salaried employees worked; and some production departments were in full production. Even if the company’s July 3 action could be construed as a shutdown, it also constituted a change in hours of work or working schedule with respect to which the exclusion clause does not relieve the company of the requirements of notification and discussion.
******
The Court has not overlooked the advisability of ordering a further hearing to take oral testimony * *. Such course in the instant case is believed to be neither necessary or appropriate. The arbitration clause clearly covers the asserted dispute * * *

It is true that the court technically made no explicit finding on whether there was a shutdown. But it clearly displayed its lack of enthusiasm for the Company’s broad interpretation of the word and indicated its belief that what had occurred did not amount to a shutdown. This was made more emphatic by its later conelusion that “The arbitration clause clearly covers the asserted dispute.” Finally, it flatly ruled that even if a shutdown had occurred, the Union’s grievance was still arbitrable, a conclusion with which, as indicated, we agree. Under these circumstances, no error was committed.

Finally, the Company seeks reversal because the Union commenced its action by petition under section 4 of the United States Arbitration Act instead of by complaint under section 301 of the Labor Management Relations Act, and because the Union thereafter used the summary procedures of the Arbitration Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Galveston v. Galveston Municipal Police Ass'n
57 S.W.3d 532 (Court of Appeals of Texas, 2001)
Dryer v. Los Angeles Rams
709 P.2d 826 (California Supreme Court, 1985)
Frank Derwin v. General Dynamics Corporation
719 F.2d 484 (First Circuit, 1983)
Janmort Leasing, Inc. v. Econo-Car International, Inc.
475 F. Supp. 1282 (E.D. New York, 1979)
White Motor Corporation v. International Union
491 F.2d 189 (Second Circuit, 1974)
Johnson v. Colts, Inc.
306 F. Supp. 1076 (D. Connecticut, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
406 F.2d 1046, 70 L.R.R.M. (BNA) 2477, 1969 U.S. App. LEXIS 9189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/international-assn-of-machinists-aerospace-workers-v-general-electric-ca2-1969.