Interlake Distributors, Inc. v. Old Mill Towne

954 P.2d 1295, 339 Utah Adv. Rep. 7, 1998 Utah App. LEXIS 17, 1998 WL 119801
CourtCourt of Appeals of Utah
DecidedMarch 19, 1998
Docket970549-CA
StatusPublished
Cited by7 cases

This text of 954 P.2d 1295 (Interlake Distributors, Inc. v. Old Mill Towne) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interlake Distributors, Inc. v. Old Mill Towne, 954 P.2d 1295, 339 Utah Adv. Rep. 7, 1998 Utah App. LEXIS 17, 1998 WL 119801 (Utah Ct. App. 1998).

Opinion

OPINION

BILLINGS, Judge:

Jones Paint & Glass, Inc. and Southam & Warburton Aluminum, Inc. appeal a grant of summary judgment dismissing Deseret Pacific Mortgage Company and Old Mill Towne, Inc. from appellants’ mechanics’ hen action. We affirm.

FACTS

In May 1984, Deseret Pacific Mortgage Company (Deseret Pacific) became the construction lender for the Old Mill Towne apartments (the Property). Appellants performed work during construction of the project, with Jones Paint & Glass completing its work on February 4, 1985, and Southam & Warburton Aluminum completing its work on the fifteenth of the same month. Both appellants recorded a notice of mechanics’ hen in March 1985. On October 2, 1985, appehants filed their hen foreclosure suit against Deser-et Pacific, among other parties. Appellants however, did not serve a summons on'Deser-et Pacific. Several other contractors had instituted hen foreclosures in connection with the Old Mill project, and in March 1986, A & Y Building Supply filed a motion to consolidate, which included appehants’ actions against Deseret Pacific.

After the hen foreclosure actions commenced, Old Mill Towne defaulted on its trust deed, and the deed holder foreclosed. Old Mill Towne, Inc. (Old Mill), a separate entity from Old Mill Towne, ultimately obtained the Property in December 1989. In 1991, Old Mill filed a motion to intervene on the basis that it currently held title to the Property and that it believed its title was superior to appellants’ mechanics’ hens. Old Mill was subsequently joined in the action as an intervenor.

Old Mill and Deseret Pacific filed motions for summary judgment to quiet title on the Property. They argued that because appellants faded to file a hs pendens giving notice of the lawsuits, their hens were void as they did not know of the lawsuit within twelve months after appehants completed their work. The trial court granted summary judgment in favor of both parties, concluding neither had actual knowledge of appellants’ lawsuits within the requisite statutory one-year period. The trial court reserved the issue of whether Deseret Pacific was entitled to attorney fees until after htigation on ap-pehants’ contract claims against other parties.

During the trial on appehants’ remaining claims, Deseret Pacific presented evidence of attorney fees it incurred defending against appehants’ mechanics’ hen claims. In its final order, the trial court declined to award attorney fees to Deseret Pacific. Both appellants and Deseret Pacific filed motions for a new trial. Appehants sought a new trial on the summary judgment order . dismissing their mechanics’ hen actions against Deseret *1297 Pacific and Old Mill. Deseret Pacific sought a new trial on the issue of attorney fees. After the parties filed their motions, the Fourth District was consolidated. Until this time Judge Burningham had presided over the case. As a result of the consolidation, however, Judge Burningham’s civil cases were transferred to Judge Schofield, who heard the parties’ motions. Judge Schofield denied appellants’ motion but granted Deseret Pacific’s and ordered appellants to pay attorney fees to Deseret Pacific in the amount proven at trial. This appeal followed.

Appellants argue the trial court improperly granted summary judgment because appellants presented sufficient evidence to create an issue of fact as to whether Deseret Pacific and Old Mill actually knew of their mechanics’ lien litigation within the one-year statutory period. Appellants also assert Judge Schofield did not have the authority to reverse Judge Burningham’s order denying attorney fees to Deseret Pacific. 1

ANALYSIS

I. Summary Judgment

Summary judgment is properly granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Utah R. Civ. P. 56(c). We review the trial court’s grant of summary judgment for correctness. See Kitchen v. California Gas Co., 821 P.2d 458, 460 (Utah Ct.App.1991). In determining whether the moving party was entitled to summary judgment, “we view all relevant facts, including all inferences arising from the facts, in the light most favorable to the party opposing the motion.” Id.

Appellants argue they presented sufficient evidence to support the reasonable inference that Deseret Pacific and Old Mill actually knew that appellants had instituted foreclosure actions on their liens within twelve months of their completing work on the project.

Deseret Pacific and Old Mill argue they are entitled to summary judgment under Utah’s mechanics’ lien statute, which provides:

Actions to enforce the liens herein provided for must be begun within twelve months after the completion of the original contract, or the suspension of work thereunder for a period of thirty days. Within the twelve months herein mentioned the lien claimant shall file for record with the county recorder of each county in which the lien is recorded a notice of the pendency of the action, in the manner provided in actions affecting the title or right to possession of real property, or the lien shall he void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action, and the burden of proof shall be upon the lien claimant and those claiming under him to show such actual knowledge.

Utah Code Ann. § 38-1-11 (1974) (amended 1994) (emphasis added). It is undisputed that appellants did not file notice of the pendency of the action- — a lis pendens — as the statute requires. Thus, under the plain language of the statute, appellants’ liens are void against Deseret Pacific and Old Mill unless within twelve months from the time appellants completed their work, Deseret Pacific and Old Mill were either made parties to or had actual knowledge of the lawsuit. See e.g., Projects Unlimited, Inc. v. Copper State Thrift & Loan Co., 798 P.2d 738, 752 (Utah 1990) (“Only when the claimant fails to timely record the lis pendens can an interested person argue that it is not subject to the lien, and then only if such person was not named as a party and did not have actual knowledge of the action.”)

A. Deseret Pacific

Deseret Pacific was named as a party to appellants’ lawsuit when the action was first filed in October 1985. However, merely naming a person in a lawsuit is not sufficient to make that person a party; one is a party to a lawsuit only if named and served. See, e.g., Dahnken, Inc. v. Wil *1298 marth, 726 P.2d 420, 421 n. 1 (Utah 1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VCS, Inc. v. La Salle Development, LLC
2012 UT 89 (Utah Supreme Court, 2012)
State v. Ruiz
2009 UT App 121 (Court of Appeals of Utah, 2009)
Victor Plastering, Inc. v. SWANSON BUILDING MATERIALS, INC.
2008 UT App 474 (Court of Appeals of Utah, 2008)
Pearson v. Lamb
2005 UT App 383 (Court of Appeals of Utah, 2005)
MacRis v. Sculptured Software, Inc.
2001 UT 43 (Utah Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
954 P.2d 1295, 339 Utah Adv. Rep. 7, 1998 Utah App. LEXIS 17, 1998 WL 119801, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interlake-distributors-inc-v-old-mill-towne-utahctapp-1998.