Interfinancial Midtown, Inc. v. Choate Construction Co.

644 S.E.2d 281, 284 Ga. App. 747, 2007 Fulton County D. Rep. 705, 2007 Ga. App. LEXIS 250
CourtCourt of Appeals of Georgia
DecidedMarch 7, 2007
DocketA06A2218, A06A2219
StatusPublished
Cited by9 cases

This text of 644 S.E.2d 281 (Interfinancial Midtown, Inc. v. Choate Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interfinancial Midtown, Inc. v. Choate Construction Co., 644 S.E.2d 281, 284 Ga. App. 747, 2007 Fulton County D. Rep. 705, 2007 Ga. App. LEXIS 250 (Ga. Ct. App. 2007).

Opinion

MlKELL, Judge.

These companion cases arise from a protracted dispute between Interfinancial Midtown, Inc. (Interfinancial), the owner of some Atlanta property, and Choate Construction Company (Choate), which did construction work on that property and then filed a lien and a suit for breach of contract when it was not paid. Though the parties entered into a settlement agreement, they were soon at odds on its meaning. In Case No. A06A2218, Interfinancial appeals from the trial court’s denial of its motion for summary judgment on the contract; in Case No. A06A2219, it appeals from the trial court’s grant of Choate’s motion to enforce the settlement agreement and its award of fees. We find that the trial court did not err when it denied Interfinancial summary judgment on the contract and enforced the settlement agreement, but that the latter provided only for the survival of Choate’s lien, and not for any payment arising from a sale of the property. We therefore affirm in Case No. A06A2218, affirm in part and reverse in part in Case No. A06A2219, and vacate and remand for further proceedings on fees.

The record shows that in June 2001, Choate and Interfinancial entered into a contract under which Choate agreed to build townhouses on property owned by Interfinancial. The contract provided that “[a] 11 claims, disputes or other matters in question between the parties ... shall be resolved by mediation, litigation, or arbitration as specified in this Article.” The contract went on to specify that

[a]s a condition precedent to initiating any litigation or arbitration . . ., the parties shall make a good faith effort to mediate a resolution of the dispute with the assistance of a qualified mediator to be chosen by agreement of the parties. In the event that the parties are unable to agree upon a qualified mediator, a mediator shall be designated by the Atlanta Regional Office of the American Arbitration Association (“AAA”). The mediation shall be held in accordance with the Construction Industry Mediation Rules of the AAA or by such other standards as established by the mediator. Demand for mediation shall be made within a reasonable time after the claim, dispute, or other matter in question has arisen but in no event after the date when [a claim] would be barred by the applicable statute of limitations.

(Emphasis supplied.) After disputes arose concerning payment, Choate ceased work and filed a lien in the amount of $403,849 plus *748 interest. Choate then contacted Interfinancial and asked it to agree to submit Choate’s claim to mediation. Interfinancial replied that Choate would have to release its lien before Interfinancial would participate. Choate refused to do so.

In April 2002, the parties entered into a settlement agreement under which Interfinancial agreed to give Choate $275,000 from the proceeds of any sale of the property. The settlement agreement also provided that

[i]n the event the closing of the Sale Transaction is not consummated, and the full Settlement Payment is not made to Choate within sixty (60) days of the date of this Agreement, then . . . the Title Clearance Documents shall be returned to Choate and will be deemed null and void and of no force or effect, the Lien of record will remain in full force and effect, and the rights and obligations of the parties shall be the same as prior to the execution of this Agreement and shall continue and shall not be affected by the execution of this Agreement or the failure of the Settlement events (hereinafter defined) to have occurred within the time frame required hereunder.

Choate filed suit for breach of contract and lien foreclosure in November 2002. Interfinancial counterclaimed and filed a motion to dismiss, arguing that when Choate failed to mediate before filing its lien, it failed to satisfy the underlying contract’s condition precedent to litigation. The trial court denied the motion to dismiss and ordered the parties to engage in mediation, which they did. Interfinancial then moved for summary judgment on the same ground. The trial court found that questions of fact existed as to whether the parties had made a good faith effort to mediate, denied the motion, and certified its decision for immediate review. When Interfinancial failed to timely file its application for interlocutory appeal, however, this Court denied the application and dismissed the appeal without prejudice.

In the meantime, on July 29, 2004, Interfinancial sold the property to an affiliate. Interfinancial did not pay Choate any money in the wake of the sale, however. The trial court having struck Choate’s lien as improperly filed, Choate amended its complaint to include an alternative claim for breach of the settlement agreement. After Choate moved to enforce the agreement, the trial court entered summary judgment in favor of Choate, holding that Interfinancial owed Choate $275,000 and attorney fees. The trial court later awarded Choate $14,000 for fees expended to enforce the agreement and *749 $6,000 for fees expended in defending against Interfinancial’s motion to disqualify Choate’s counsel.

On appeal from either a grant of summary judgment or a grant of a motion to enforce a settlement agreement, we review the evidence de novo to determine whether the moving party has shown that “the documents, affidavits, depositions and other evidence in the record reveal that there is no evidence sufficient to create a jury issue on at least one essential element of the [nonmovant’s] case.” 1 Since Inter-financial moved for summary judgment under the contract, and since Choate moved to enforce the settlement agreement superseding that contract, we examine the evidence in the light most favorable to Choate in Case No. A06A2218 and in the light most favorable to Interfinancial in Case No. A06A2219.

Case No. A06A2218

1. Interfinancial argues that because no material issue of fact remained concerning Choate’s failure to mediate, and thus to fulfill a condition precedent to the contract, the trial court erred when it denied Interfinancial’s motion for summary judgment. 2 We disagree.

The contract at issue here provides that “[d]emand for mediation shall be made within a reasonable time after the claim, dispute, or other matter in question has arisen” — a category broad enough to include not only the dispute between these parties, but also the lien that first memorialized it. This provision does not require either party to make the mediation demand in writing. In fact, as Choate points out, the parties struck the preprinted language of the American Institute of Architects form contract requiring a written demand and replaced it with their own, which does not require that the demand be in writing. Nor have we seen any Georgia law suggesting that the act of filing a lien, on its own, amounts as a matter of law to the commencement of “litigation” for purposes of a construction contract. 3

Choate has provided some evidence that it requested mediation within a reasonable time after filing its lien, and that Interfinancial *750 refused.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palatini v. the State
774 S.E.2d 818 (Court of Appeals of Georgia, 2015)
McCLURE v. McCURRY Et Al.
765 S.E.2d 30 (Court of Appeals of Georgia, 2014)
Fulton County School District v. Jan S. Hersh
Court of Appeals of Georgia, 2013
Fulton County School District v. Hersh
740 S.E.2d 760 (Court of Appeals of Georgia, 2013)
Savannah Yacht Corp. v. Thunderbolt Marine, Inc.
676 S.E.2d 728 (Court of Appeals of Georgia, 2009)
Walker v. Walker
668 S.E.2d 330 (Court of Appeals of Georgia, 2008)
Note Purchase Co. of Georgia, LLC v. Brenda Lee Strickland Realty, Inc.
654 S.E.2d 393 (Court of Appeals of Georgia, 2007)
Johnston v. Correale
648 S.E.2d 180 (Court of Appeals of Georgia, 2007)
Ranwal Properties, LLC v. John H. Harland Co.
646 S.E.2d 730 (Court of Appeals of Georgia, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
644 S.E.2d 281, 284 Ga. App. 747, 2007 Fulton County D. Rep. 705, 2007 Ga. App. LEXIS 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interfinancial-midtown-inc-v-choate-construction-co-gactapp-2007.