Intercontinental Group, Inc. v. S & S Air Conditioning Co.

391 So. 2d 377, 1980 Fla. App. LEXIS 18253
District Court of Appeal of Florida·Decided December 23, 1980·No. No. 80-598·Published

Opinion

PER CURIAM.

The pivotal question in this case is when are materials “finally” furnished to an owner by a contractor in order to secure a mechanics lien, pursuant to Section 713.-08(5), Florida Statutes (1977).

We hold that where the work is suspended on the project by the owner and the contractor is unable to go forward with the work (although he has material on the job site needed to complete the work), the materials are “finally” furnished when the owner notifies the contractor that he wants the work to proceed and the materials are then utilized. Baldyga Construction Company, Inc. v. Hurff, 164 N.J.Super. 587, 397 A.2d 396 (1978); Gaston v. Avansino, 39 Nev. 128, 154 P. 85 (1915); Anno. 97 ALR 780 and cases cited therein. Compare, Miller Electric Company of Miami, Inc. v. Sweeny, 199 So.2d 734 (Fla. 3d DCA 1967).

No error was made in the award of attorney fees. See: Section 713.29, Florida Statutes (1977).

Therefore, the final judgment under review is affirmed.

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Intercontinental Group, Inc. v. S & S Air Conditioning Co., 391 So. 2d 377, 1980 Fla. App. LEXIS 18253 (Fla. Ct. App. 1980).

391 So. 2d 377 (Intercontinental Group, Inc. v. S & S Air Conditioning Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Baldyga Construction Co. v. Hurff
397 A.2d 396 (New Jersey Superior Court App Division, 1978)
Miller Electric Co. of Miami v. Sweeny
199 So. 2d 734 (District Court of Appeal of Florida, 1967)
Gaston v. Avansino
154 P. 85 (Nevada Supreme Court, 1915)