Baldyga Construction Co. v. Hurff

397 A.2d 396, 164 N.J. Super. 587, 1978 N.J. Super. LEXIS 1240
CourtNew Jersey Superior Court Appellate Division
DecidedDecember 22, 1978
StatusPublished
Cited by1 cases

This text of 397 A.2d 396 (Baldyga Construction Co. v. Hurff) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldyga Construction Co. v. Hurff, 397 A.2d 396, 164 N.J. Super. 587, 1978 N.J. Super. LEXIS 1240 (N.J. Ct. App. 1978).

Opinion

Staller, J. S. C.

This is a motion for summary judgment brought by defendants Donald and Diane Hurff against plaintiff Baldyga Construction Company, Inc. (Baldyga) in an action in which plaintiff seeks to enforce a mechanic’s lien.

Plaintiff subcontractor is a masonry contractor which, sometime in 1977, contracted with a general contractor, the Behm Corporation (Behm), to do masonry work on a home being built for the Hurffs. Baldyga’s contract called for it to perform work consisting of clearing the lot, staking out the [589]*589house, installing the footings, foundations, steps, flatwork, brickwork and fireplace, and finishing the grading. Various stages of this work were to be done at different times during the construction of the Hurff home, starting with the first work to be performed on the home and ending with one of the last jobs to be completed, the grading.

On November 2, 1977, prior to having furnished any materials for or having performed any labor on defendants’ home, plaintiff filed a mechanic’s notice of intention with the Clerk of Cape May County (File No. 19981) pursuant to the provisions of N. J. S. A. 2A:44--71 et seq., and on the same date served a copy of said notice on the defendants, the Hurffs and Behm, by certified mail.

Baldyga then proceeded to complete the lay-out, excavation, footings and foundations of the house and porch. The value of this work is $7,679, of which $3,000 has been paid to plaintiff. This work was started in November 1977 and completed no later than January 1978.

Since January 1978 no labor or materials have been supplied or furnished to the Hurff home by plaintiff. The general contractor, without the knowledge of the Hurffs, hired another masonry contractor to complete the remainder of the masonry work. This work was performed during a five-day period in April 1978 and consisted of a brick facing on the downstairs half of the house, a fireplace and chimney, a concrete floor in the garage and a cement floor for the front porch.

Plaintiff, as subcontractor, asserts that it was at all times ready and able to complete the above-mentioned work and was waiting for notice to return to the job to do so. Plaintiff also asserts that when it left the Hurff job in January 1978 it was with the understanding that it would be called back to install the fireplace and chimney and to do the facing and concrete flooring, at different stages of construction.

The general contractor stopped work sometime in May 1978. When no work was performed by Bchm or its subcontractors for a period of time thereafter, Hurff’s attorney sent [590]*590a letter to Behm dated July 19, 1978, informing it that it was no longer on the job because of a breach of contract in failing to complete the house by June 1, as allegedly had been promised. Apparently, Behm is no longer operating its business.

Baldyga was not notified of this termination until a letter from Hurffs’ attorney was received by plaintiff’s attorney on August 14, 1978. The effect of this letter was to inform plaintiff that Behm was off the job and that plaintiff would not be called upon to complete its masonry contract.

On September 29, 1978 plaintiff filed a mechanic’s lien claim in the office of the Clerk of Cape May County, against the Hurff premises.

The basis of defendants’ motion for summary judgment is that plaintiff’s lien claim was not timely filed as required by N. J. S. A. 2A:44-91, which provides:

Every person intending to claim a lien under this article shall, and no debt shall be a lien by virtue of this article unless the claimant shall, within 4 months after the date of the last labor performed or the materials furnished for which the debt is due, file his lien claim with the proper county clerk, as in this article provided.

The Hurffs argue that plaintiff’s filing on September 29, 1978 was after the expiration of the four-month period, which they contend ended no later than the end of May 1978. They claim that sometime in January, 1978, was “the date of the last labor performed . . . for which the debt is due.” Plaintiff’s position is that the four month period should be computed from the time when it was informed by the Hurffs that the Hurff-Behm contract was considered breached, at which time plaintiff’s own contract to do masonry work on the Hurff premises was effectively terminated.

The question for determination is: at what point, under a building contract requiring work to be performed in various stages at different times during the construction process, the four-month period for filing mechanic’s lien claims should begin to run?

[591]*591While “[mjechanics lien statutes are remedial and are designed to guarantee effective security to those who furnish labor or materials used to enhance the value of the property of others,” J. R. Christ Constr. Co. v. Willete Assocs., 47 N. J. 473 (1966), it is also recognized that those provisions which cover the requirements for establishing a lien, including N. J. S. A. 2A:44-91, are to be “strictly construed.” Columbia Lumber & Millwork Co., Inc. v. DeStefano, 12 N. J. 117 (1953); Friedman v. Stein, 4 N. J. 34 (1950).

There is authority, however, which for the purpose of construing the operation of N. J. S. A. 2A:44-91 focuses on the date of completion of a contract as the time for determining the commencement of the period within which a lien claim may be filed. Derrickson v. Edwards, 29 N. J. L. 468, 80 Am. Dec. 220 (1861). In the case of an entire building contract the court in Derrickson established the principle that

* * * in the contemplation of the statute, the work and materials cannot be considered as furnished, until the whole contract was completed. Neither the language of the act, nor any intention which can be collected from it, requires a mechanic working under a contract, to file lien claims from week to week as his work progresses, [at 470-471]

This principle is especially applicable to the type of contract involved in the present case. The time for performance by Baldyga under its contract with Behm was completely dependent upon the construction progress Behm was making in building the Hurff’s home. Baldyga was called upon to perform masonry work at the beginning of construction, including lay-out, excavation and foundation work, then was to be recalled at different unspecified times to do certain brickwork and finally was to return at or near the end of construction to do the gradings.

There were no clear guidelines as to when these separate phases of work were to be performed, nor was the general progress timetable within plaintiff’s control. The court is [592]*592also aware that the construction of a home may take anywhere from several months to more than a year. It is apparent, then, that plaintiff subcontractor had no way of knowing, when it left the job after completing its initial phase of work in January 1978, whether it would have to wait weeks or months to be called for the next phase. Further, plaintiff, as a subcontractor, was not required to remain at the site during this lull nor to otherwise chart construction progress. Plaintiff’s only expectations were that it would be notified when needed and that it would in fact be needed, as the contract with Behm specified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Intercontinental Group, Inc. v. S & S Air Conditioning Co.
391 So. 2d 377 (District Court of Appeal of Florida, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
397 A.2d 396, 164 N.J. Super. 587, 1978 N.J. Super. LEXIS 1240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldyga-construction-co-v-hurff-njsuperctappdiv-1978.