Interchange Bank v. Warde Electric Contracting, Inc. (In Re Warde Electric Contracting, Inc.)

308 B.R. 659, 2004 U.S. Dist. LEXIS 7714, 2004 WL 943602
CourtDistrict Court, S.D. New York
DecidedApril 28, 2004
Docket02 B 22894(ASH). 03 Civ. 4003(WCC)
StatusPublished
Cited by2 cases

This text of 308 B.R. 659 (Interchange Bank v. Warde Electric Contracting, Inc. (In Re Warde Electric Contracting, Inc.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interchange Bank v. Warde Electric Contracting, Inc. (In Re Warde Electric Contracting, Inc.), 308 B.R. 659, 2004 U.S. Dist. LEXIS 7714, 2004 WL 943602 (S.D.N.Y. 2004).

Opinion

*661 OPINION AND ORDER

CONNER, Senior District Judge.

Appellant Interchange Bank (the “Bank”) appeals to this Court from an Order (the “Order”) issued April 2, 2003 by the Bankruptcy Court (Honorable Adlai S. Hardin, Jr., U.S.B.J.) denying appellant’s motion to compel payment of $110,550 from the debtor’s estate. 1 Appellant’s motion was opposed in the Bankruptcy Court and on appeal in this Court by debtor-appellee Warde Electric Contracting, Inc. (the “debtor”). For the reasons stated herein, we affirm the Order of the Bankruptcy Court.

BACKGROUND

Unless otherwise noted, the following facts are undisputed. The debtor is an electrical contracting company. In 1998, the debtor entered into a contract with RWKS Transit, Inc. a/k/a Railworks Transit, Inc. (“Railworks”) to provide electrical work in connection with the rehabilitation of the Jackson-West Street Substation and Circuit Breaker Houses (the “Jackson project” or the “project”). Railworks had previously been retained by the New York City Transit Authority (“NYCTA”) to serve as general contractor on the project. On December 13, 1999, the debtor executed a Purchase Order listing itself as the purchaser from RZS Solutions, Inc. (“RZS”) of certain custom alarm units (the “alarm units”) for use on the Jackson project. On January 16, 2002, RZS directed an Invoice to the debtor billing the debtor $102,500 for the alarm units and listing the debtor as the party to receive shipment.

On February 15, 2002, Railworks issued a two-party check for $102,500 payable to the debtor and RZS. Shortly thereafter, the debtor endorsed the check and remitted it to RZS as payment for the alarm units. According to both the debtor and the Bank, Railworks agreed to issue the check in partial satisfaction of a $700,000 debt owed to the debtor by Railworks. At the hearing on this matter before the Bankruptcy Court, counsel for Railworks objected to this characterization of the facts and stated Railworks’ position that the check was issued solely to secure delivery of the alarm units. (Tr. at 23.) The Bankruptcy Court found that the check was issued to secure delivery of the alarm units, not to pay the debtor for any portion of an outstanding debt. (Id. at 25-27, 29-30.) It relied on the relationship of Rail-works and RZS as general contractor and sub-subcontractor and on the amount of *662 the check, which was the exact amount owed to RZS for the alarm units, as evidence that the check was issued for payment for the alarm units, not as payment for an outstanding debt. (Id. at 11, 13, 27.) The Bankruptcy Court also cited the Bank’s and the debtor’s failure to offer convincing evidence that the two-party check was issued in partial satisfaction of the outstanding debt. (Id. at 31, 51.)

In May 2002, Railworks declared the debtor in default of its contract for work on the project. Pursuant to a performance bond, the United States Fidelity & Guaranty Co. and Fidelity & Guaranty Insurance Co. (collectively “the sureties”) retained Heckler Electric to complete the electrical subcontracting for the Jackson project. On June 12, 2002, the debtor filed its Chapter 11 petition. 2 The Bank contends that it has a first priority, perfected security interest in all of the debtor’s assets (the “non-cash collateral”) and the debtor’s accounts receivable (the “cash collateral”), in connection with a $1.6 million loan the Bank extended to the debtor. 3 Sometime after the filing of the debtor’s petition, the debtor and the Bank entered into negotiations to allow the debtor to access the cash collateral.

On October 24, 2002, the NYCTA sent a letter to RZS instructing RZS to deliver the alarm units to the Jackson project. On November 5, 2002, the debtor sent a letter to RZS stating that the alarm units were property of the debtor’s estate and that failure to deliver them to the debtor would amount to conversion for which RZS would be held liable. Faced with competing claims for the property, RZS did not deliver the alarm units to either party. In December 2002, the debtor, the Bank, the creditors’ committee and the sureties signed a Stipulation (the “Stipulation”) that provided, inter alia, that the debtor could use the cash collateral for six months from the date the Stipulation was “So Ordered.” In exchange, the debtor agreed to use its best efforts to get authorization from the Bankruptcy Court to sell the alarm units and to turn over the proceeds from such sale to the Bank. The Bank took the position that it had a lien on the alarm units, but agreed to allow transfer of them free and clear of its lien. Finally, the Stipulation provided, “This Stipulation is subject to and conditioned upon approval of the Court.” The Bankruptcy Court never approved this Stipulation. (Tr. at 51.)

In contemplation of Bankruptcy Court approval of the Stipulation, the debtor and the sureties entered into an agreement, which was not included in the Stipulation, whereby the sureties agreed to pay the debtor $110, 550 in exchange for the alarm units, which were valued at $102,500, and other equipment valued at $8,050. Although the sureties believed that Rail-works had issued the two-party check solely to pay for the alarm units, the sureties were apparently willing to remit the funds because RZS’s failure to deliver them to the Jackson project was causing costly delays. According to the sureties, they originally contemplated issuing a two-party check payable to the debtor and the Bank in connection with this agreement.

On December 30, 2002, the Stipulation was presented to the Bankruptcy Court to be “So Ordered.” The Internal Revenue *663 Service (“IRS”) requested revisions and the presentment date was adjourned to January 22, 2003. On January 16, 2003, the sureties wired $110,550 to the debtor, who subsequently used the funds in its operations. The Stipulation was not presented on January 22, 2003. Instead, on February 21, 2003, the Bank moved by an Order to Show Cause for, inter alia, an Order compelling the payment of $110,550 from the debtor’s estate. At the hearing on the matter, the Bank argued that it had a lien on the alarm units because they were property of the estate and the Bank should have received the sale proceeds pursuant to the Stipulation. 4 Even if there was no lien on the alarm units, the Bank argued, the Stipulation was a contract that required the debtor to remit the proceeds it received from the sureties to the Bank.

The Bankruptcy Court concluded that the Bank did not have a lien on the alarm units because they were never property of the estate. Accordingly, it refused to “So Order” the Stipulation because the debtor did not have the right to sell the alarm units. Furthermore, the Bankruptcy Court held, the Stipulation was not an enforceable contract because it was never “So Ordered”; because the funds were already paid by the sureties to the debtor and subsequently spent without an enforceable contract in place, the debtor was not required to remit the funds to the Bank. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calpine Corp. v. Bank of New York
895 A.2d 880 (Court of Chancery of Delaware, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
308 B.R. 659, 2004 U.S. Dist. LEXIS 7714, 2004 WL 943602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interchange-bank-v-warde-electric-contracting-inc-in-re-warde-electric-nysd-2004.