Intelligent Investments, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedSeptember 15, 2025
Docket18-1221
StatusPublished

This text of Intelligent Investments, Inc. v. United States (Intelligent Investments, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intelligent Investments, Inc. v. United States, (uscfc 2025).

Opinion

In the United States Court of Federal Claims

INTELLIGENT INVESTMENTS, INC.,

Plaintiff, No. 18-1221 v. (Filed: September 15, 2025) THE UNITED STATES,

Defendant.

William J. Fleischaker, Fleischaker & Williams, Joplin, Missouri, for Plaintiff. Matthew Lewis, Trial Attorney, Elizabeth M. Hosford, Assistant Director, Patricia M. McCarthy, Director, Commercial Litigation Branch, Brett A. Shumate, Assistant Attorney General, Civil Division, United States Department of Justice, Washington, D.C., for Defendant. OPINION AND ORDER HADJI, Judge. Plaintiff Intelligent Investments, Inc. (the Contractor or Plaintiff) seeks $4,905,667.71 in damages stemming from the United States Army Corps of Engineers’ termination for convenience (T4C) of its contract to perform debris hauling and cleanup in Joplin, Missouri. See generally ECF 1. The Government argues that the Contractor’s claim is largely meritless because it should have used an inventory basis of accounting instead of the total cost basis, which negates most of its claim, and that under any accounting method, the claim is overstated because it seeks recovery of unallowable costs. ECF 93 at 7-8. Before the Court is the Government’s Motion for Partial Summary Judgment (ECF 93), requesting the Court to find as a matter of law that: (1) the inventory basis of accounting is the proper basis for the Contractor’s claim; or, in the alternative, (2) that certain claimed costs are unrecoverable. For the reasons explained below, the Court declines to grant summary judgment as to the method of accounting, grants summary judgment as to certain claimed costs, and defers addressing the claimed profit. Accordingly, the Government’s Motion for Partial Summary Judgment is DENIED IN PART, GRANTED IN PART, and DEFERRED IN PART. BACKGROUND In May 2011, a Category 5 tornado ripped through the city of Joplin, Missouri. Gov’t App. at 157, ECF 93-1. As part of the recovery efforts, the Army Corps issued three requests for proposals (RFP), seeking contractors to clean up debris. Gov’t App. at 158. As outlined in the RFPs, the contract was for removal and hauling of debris from public property to local dump sites. Gov’t App. at 24, 158. The contract was to be paid on a fixed price per ton of debris based on the type of debris and the distance hauled. Gov’t App. at 23. In June, after the Contractor submitted its proposal, the Army Corps awarded contract number W912DQ-11-C-4020 (the Contract) to the Contractor. Gov’t App. at 19. The Contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-2, Termination for Convenience of the Government (Fixed-Price) (May 2004) (hereinafter, T4C Clause). 1 See Gov’t App. at 63. The Contract was not to exceed $40 million with two options of $20 million. Gov’t App. at 19. To fulfill the Contract, the Contractor subcontracted and entered into a teaming agreement with DRC Emergency Services, LLC (DRC). Gov’t App. at 1-15. DRC then subcontracted with Cahaba Disaster Recovery. Gov’t App. at 160. On July 5, 2011, before work began, the Contractor submitted a request for equitable adjustment (REA) citing changes in condition, to include those that made segregation of debris containing asbestos more challenging. Gov’t App. at 70-71. On July 11, 2011, the Army Corps issued the full notice to proceed, and the Contractor and its subcontractors commenced work thereafter. Gov’t App. at 72, 159. Throughout performance, the Army Corps modified the Contract several times. Gov’t App. at 74, 92, 113. Notably, the Army Corps issued unilateral modification P00001, which reduced the not-to-exceed amount from $40 million to $30 million. Gov’t App. at 74. The Army Corps further modified the Contract to contemplate the management of asbestos contaminated material. Gov’t App. at 113. During the performance period, the Contractor entered a second subcontract with DRC. Gov’t App. at 16-18. On August 19, 2011, the Army Corps issued a notice of T4C pursuant to the T4C Clause. Gov’t App. at 135-36. On the same day, the Army Corps also issued unilateral modification P00006 to decrease the not-to-exceed amount from $30 million to $10.25 million. Gov’t App. at 137-38. In September 2011, the Contractor submitted a supplemental REA, which it characterized as “an offer of compromise.” Gov’t App. at 146. The Army Corps then issued unilateral modification P00007 outlining the termination and modifying the not-to-exceed amount from $10,250,000 to $8,899,570.97. Gov’t App. at 139-40. Thereafter the Contractor engaged Excell Consulting International, LLC, see

1 The T4C Clause states that the Government “may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest” and outlines reimbursable costs. FAR 52.249-2(a), (g). 2 Gov’t App. at 1242, and decided to reconfigure its September REA into a T4C settlement proposal. Gov’t App. at 149. In May 2012, Kevin Lynch, the Army Corps Claims Manager, sent the Contractor the standard forms for inventory basis and total cost basis with a note stating: “I would encourage you to read FAR part 49, choose a Standard Form 1400 series on which to capture your settlement proposal, and to seek professional assistance if necessary.” Gov’t App. at 1422. Mr. Lynch also noted that Nicholas Deguire would serve as the Terminating Contracting Officer (TCO). Id. The Contractor informed Mr. Lynch that it would submit its settlement proposal on a total cost basis and withdrew its July 2011 and September 2011 REAs. Gov’t App. at 155. On August 17, 2012, the Contractor submitted its T4C settlement proposal to the TCO, requesting $4,670,264.79 beyond what had already been paid. Gov’t App. at 157-68. In response, the TCO noted that, on account of an ongoing fraud investigation, the Army Corps was unable to negotiate or settle the proposal at that time. Gov’t App. at 1172. He advised that the Army Corps would hold the claim and process it once it regained settlement authority. Id. However, the Army Corps still submitted the settlement proposal to the Defense Contract Audit Agency (DCAA) for auditing. Gov’t App. at 1419. In June 2013, the Contractor submitted a supplement to the T4C settlement proposal. Gov’t App. at 1207. The supplement added $235,402.92 for additional termination costs and professional and consultant fees. Id. Subsequently, DCAA informed the TCO that it did not consider the settlement proposal adequate for audit because it was calculated on a total cost basis, rather than an inventory basis. Gov’t App. at 1404. DCAA also noted that the total cost basis may be used if the TCO approves in advance. Id. In light of DCAA’s guidance, TCO Deguire requested that the Contractor resubmit its settlement proposal using the inventory basis, which the Contractor has declined to do. Gov’t App. at 1419. Following the fraud investigation by the Army Criminal Investigation Division, in June of 2016, the CEO and President of Intelligent Investments, Raul Gonzales, was indicted in the United States District Court for the Western District of Missouri on one count of conspiracy to defraud the United States, three counts of making a false claim, three counts of disaster fraud, and three counts of making a false document related to the Contract. Gov’t App. at 1440-52. Mr. Gonzales was later found not guilty on all counts. United States v. Gonzales, Case No. 16-5019, ECF 123 (W.D. Mo. 2018). To date, TCO Deguire has not issued a decision on the Contractor’s claim. Based on the ongoing disagreement as to the terms of the T4C settlement proposal, the Contractor brought this Contract Disputes Act (CDA) claim on August 15, 2018. ECF 1 at 1. On October 28, 2024, the Government filed the instant Motion for Partial Summary Judgment (ECF 93).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Bruesewitz v. Wyeth LLC
131 S. Ct. 1068 (Supreme Court, 2011)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
OK's Cascade Co. v. United States
97 Fed. Cl. 635 (Federal Claims, 2011)
Lathan Co. v. United States
36 Cont. Cas. Fed. 75,842 (Court of Claims, 1990)
Corban Industries, Inc. v. United States
37 Cont. Cas. Fed. 76,180 (Court of Claims, 1991)
Dubin v. United States
599 U.S. 110 (Supreme Court, 2023)
Quintana-Dieppa v. Department of the Army
130 F.4th 1 (First Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
Intelligent Investments, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intelligent-investments-inc-v-united-states-uscfc-2025.