Integrity Constr. II, Inc. v. Severino Constr., Inc.

Ohio Court of Appeals·Decided August 13, 2026·No. 25AP-138·Published

Opinion

IN THE COURT OF APPEALS OF OHIO

TENTH APPELLATE DISTRICT

Integrity Construction II, Inc., :

Plaintiff-Appellee, : No. 25AP-138 (C.P.C. No. 23CV-1981)

v. :

(REGULAR CALENDAR)

Severino Construction, Inc. et al., :

Defendants-Appellants. :

D E C I S I O N

Rendered on August 13, 2026

On brief: Thomas Law, LLC, Ryan L. Thomas, and Megan A. Porter, for appellee. Argued: Megan A. Porter.

On brief: Hahn Loeser & Parks LLP, Gregory A. Thompson, Aaron S. Evenchik, and Samantha L. Shamhart, for appellants. Argued: Gregory A. Thompson.

APPEAL from the Franklin County Court of Common Pleas DINGUS, J.

{¶ 1} Defendants-appellants, James Severino, Jr. and J. Severino Construction, Inc. (collectively “Severino” or “Subcontractor”), appeal a judgment of the Franklin County Court of Common Pleas that denied Severino’s motion to stay proceedings and compel arbitration against plaintiff-appellee, Integrity Construction II, Inc. (“Integrity” or “Lower- Tier Subcontractor”). For the reasons that follow, we affirm. I. Facts and Procedural History {¶ 2} The litigation underlying this appeal arose from a construction project for a housing development. The project owner was Brynwood Reserve LLC (“Owner”). The general contractor for the project was Metro Development II, LLC (“Metro” or “Contractor”). In December 2021, Metro engaged Severino as a subcontractor for the project, and it entered an agreement for Severino to clear and grade the land and install sanitary sewer lines, water lines, and storm sewer lines.

{¶ 3} The agreement between Metro and Severino was entitled “Subcontract Agreement,” and it referred to the contract between Metro and the Owner as the “Prime Contract.” The Prime Contract itself was not included in the record before the court. The Subcontract Agreement included various general terms and conditions, and it attached specific requirements regarding the scope of work, specifications, and schedule requirements as exhibits to the contract. The general terms of the Subcontract Agreement provided that the obligations under the Prime Contract would flow down from both the Owner to Severino and from Metro to Severino:

Subcontractor binds itself to Contractor and Owner and is obligated to Contractor and Owner in the same manner and to the same extent that Contractor is bound and obligated to Owner under the Prime Contract.

(Subcontract Agreement, Section 1.1 at 1.) The Subcontract Agreement also provided that the Owner’s rights against Metro under the Prime Contract would flow down to the Owner against Severino and to Metro against Severino:

All rights which Owner may exercise and enforce against Contractor may be exercised and enforced by Owner against Subcontractor. . . ... Contractor shall have the same rights and privileges against Subcontractor as the Owner in the Prime Contract has against Contractor.

Id. The Subcontract Agreement further obligated Severino to incorporate the terms of the Subcontract Agreement in any future contracts with lower-tier subcontractors: “Subcontractor shall bind lower tier subcontractors and suppliers to full compliance with the Contract Documents.” Id.

{¶ 4} A section of the Subcontract Agreement governing disputes included a clause giving Metro the unilateral right to decide whether disputes with Severino should be resolved through arbitration or litigation:

BINDING DISPUTES RESOLUTION. If a dispute arises between Contractor, and Subcontractor as to this Agreement or Subcontractor’s Work that concerns only the parties hereto or other subcontractors on the Project, Subcontractor shall give Contractor written notice within three (3) days after the

No. 25AP-138 3

occurrence of the event giving rise to said claims. Otherwise, such claims will be deemed waived. Contractor shall have the right, in its sole and exclusive discretion, to elect whether the dispute will then be decided by arbitration or litigation . . .

(Subcontract Agreement, Section 6.1 at 7.)

{¶ 5} After Severino entered the Subcontract Agreement with Metro, Severino engaged Integrity as a Lower-Tier Subcontractor to perform a portion of Severino’s work. Severino and Integrity formed three different agreements (the “Lower-Tier Agreements”). Specifically, on January 11, 2022, Integrity emailed two written proposals: one for work on underground utilities including water mains, storm sewers, and sanitary sewers, and another for topsoil removal, site grading, and topsoil replacement. Severino signed the utility work proposal on January 20, 2022, circled the estimate for sanitary sewer work, and added the handwritten note “Sanitary Sewer” above his signature. (Jan. 20, 2022 Sanitary Sewer Lower-Tier Agreement at 2.) He signed the topsoil and grading proposal the same day and added the handwritten note: “Dirt Work Per Metro Contract Doc.” above his signature. (Jan. 20, 2022 Earthwork Lower-Tier Agreement at 2.) A few months later, Severino entered an agreement with Integrity to complete the installation of storm sewers. On May 3, 2022, Severino signed another copy of Integrity’s January 2022 utility work proposal, this time circling the estimate for storm sewers, crossing out other estimates, and adding a handwritten note: “All Terms of Metro Development Contract Apply to Storm Sewer.” (May 3, 2022 Storm Sewer Lower-Tier Agreement at 1.)

{¶ 6} Later in 2022, a dispute arose between Severino and Integrity regarding payment for Integrity’s work on the project. Integrity sued Severino for breach of contract, unjust enrichment, fraud, and conversion, alleging that Severino failed to fully compensate Integrity for its work. In response, Severino filed a motion to compel arbitration pursuant to the terms of Severino’s Subcontract Agreement with Metro. Severino included an affidavit stating that Severino had incorporated the terms of the Subcontract Agreement by reference into the Lower-Tier Agreements with Integrity, and that Severino provided a copy of the Subcontract Agreement to Integrity in January 2022.

{¶ 7} At a subsequent evidentiary hearing before a magistrate, Severino’s witness admitted that Severino did not provide the full Subcontract Agreement to Integrity, and instead only provided a few of the documents that were attached to the contract outlining the scope of work and schedule for the earthwork and utility work. The parties ultimately did not dispute that Severino failed to offer a copy of the full Subcontract Agreement to Integrity, and that Integrity failed to ask for a copy.

{¶ 8} The magistrate denied Severino’s motion to compel arbitration. The magistrate’s decision assumed, for the sake of argument, that Severino’s handwritten additions to the Lower-Tier Agreements with Integrity were adequate to incorporate the terms of the Subcontract Agreement by reference. Even with such an assumption, the magistrate held that Severino’s handwritten terms in the Lower-Tier Agreements were not adequate to allow Severino to stand in Metro’s shoes and enforce Metro’s arbitration provision in the Subcontract Agreement against Integrity.

{¶ 9} Severino filed objections to the magistrate’s decision. After considering the parties’ briefs and reviewing the magistrate’s decision de novo, the trial court overruled Severino’s objections and denied the motion to compel arbitration. Severino filed a timely notice of appeal, and the matter is now before this court. II. Assignments of Error {¶ 10} Severino has failed to specify an assignment or assignments of error, but it presents the following arguments for our review:

[I.] The Trial Court Erred in Finding that the Arbitration Provision in the Metro Contract Does Not Apply to Integrity.

[II.] The Trial Court Failed to Address Gibbons-Grable, Which Defeats the Notion that Only Metro Could Compel Arbitration.

[III.] The Trial Court Erred When It Improperly Shifted Integrity’s Burden to Overcome Arbitrability to Severino.

[IV.] Because All of Integrity’s Claims Are Subject to Arbitration, They Should Have Been Stayed Pending Arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Integrity Constr. II, Inc. v. Severino Constr., Inc., (Ohio Ct. App. 2026).

Integrity Constr. II, Inc. v. Severino Constr., Inc. (Integrity Constr. II, Inc. v. Severino Constr., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Hudson v. John Hancock Financial Servs., 06ap-1284 (12-27-2007)
2007 Ohio 6997 (Ohio Court of Appeals, 2007)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Volovetz v. Tremco Barrier Solutions, Inc.
2016 Ohio 7707 (Ohio Court of Appeals, 2016)
BANK OF NEW YORK MELLON v. RHIEL, Trustee.
2018 Ohio 5087 (Ohio Supreme Court, 2018)
Tera, L.L.C. v. Rice Drilling D, L.L.C.
2024 Ohio 1945 (Ohio Supreme Court, 2024)
Rice v. Stuckey
2025 Ohio 2242 (Ohio Court of Appeals, 2025)