Integrated Logistics Support Systems International, Inc. v. United States

42 Cont. Cas. Fed. 77,385, 42 Fed. Cl. 30, 1998 U.S. Claims LEXIS 235, 1998 WL 710634
CourtUnited States Court of Federal Claims
DecidedSeptember 30, 1998
DocketNo. 97-166C
StatusPublished
Cited by32 cases

This text of 42 Cont. Cas. Fed. 77,385 (Integrated Logistics Support Systems International, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Integrated Logistics Support Systems International, Inc. v. United States, 42 Cont. Cas. Fed. 77,385, 42 Fed. Cl. 30, 1998 U.S. Claims LEXIS 235, 1998 WL 710634 (uscfc 1998).

Opinion

ORDER

MILLER, Judge.

This matter is before the court on defendant’s motion pursuant to RCFC 12(b)(4) to dismiss Count IV of plaintiffs complaint for failure to state a claim upon which relief can be granted. At issue are 1) whether defendant’s motion demonstrates that the facts alleged in Count IV support a claim seeking just compensation pursuant to the Fifth Amendment’s takings clause and 2) whether the facts alleged' asserting an implied-in-fact contract entitle plaintiff to relief. Argument is deemed unnecessary.

FACTS

The facts stated herein are drawn from plaintiffs complaint, unless otherwise noted. On May 16, 1989, the United States Navy awarded Integrated Logistics Support Systems International, Inc. (“plaintiff”), a contract for the design, procurement, and installation of a warehousing system for F-18 spare parts and support equipment to assist the Kuwait Air Force (the “KAF”). The contract recited that performance would occur in two segments. Plaintiff’s performance of the first segment proceeded unimpeded until the 1990 Iraqi invasion of Kuwait, which precipitated the Persian Gulf War. These events interrupted contract performance and resulted in the destruction of the KAF’s project facilities at the work site in Kuwait, thus preventing plaintiff from utilizing logistic support material and equipment procured by plaintiff for both segments.

The onset of the war substantively changed the timing and scope of the second segment. In the aftermath of the conflict, on October 1, 1992, plaintiff, the Navy, and the KAF met to discuss performance of the second segment. The Navy and the KAF advised plaintiff that completion was required within 90 days after receiving notice to proceed and impressed upon plaintiff that time [32]*32was of the essence. Plaintiff procured the materials1 necessary to perform the project with these concerns in mind.

These materials were those necessary to support and equip the workforce and to deliver the required F-18 spare parts warehouse logistics system. Based on its discussions with the Navy and the KAF and visits to the work site, plaintiff procured materials to accommodate working in a “bare base environment.” Compl. filed Mar. 14, 1997, U14. Plaintiffs work site consequently lacked necessary facilities, such as water, electricity, office space, and lighting, and confronted dangerous conditions, including unexploded ordnance from the war and a harsh desert climate. Plaintiffs procurement efforts to mitigate these conditions were motivated in part to ensure compliance with U.S. Government safety and health requirements for its workforce.

On November 15, 1992, the KAF wrote to the Navy requesting that the Navy direct plaintiff to commence work immediately on the project, and the Navy alerted plaintiff accordingly. By letter dated December 14, 1992, the Navy informed the KAF that plaintiffs performance was imminent. Pursuant to the Navy’s and the KAF’s direction to proceed, plaintiff submitted its cost and pricing data to the Navy identifying $1,046,224.00 of material purchased for work under the second segment of the contract.

The Navy issued Letter Contract No. 0140-92-C-AC73 2 on June 15, 1993, to provide funding and coverage for the second segment of work. This obligated plaintiff to provide materials, supplies, equipment, and hardware “necessary for the furnishing of the required services.” In reliance upon the representations of the Navy and the KAF that performance must be completed within 90 days, plaintiff allegedly incurred costs of at least $2,281,687.00 in procuring items necessary for performance.

During May and June 1993, a dispute arose between the parties regarding the condition of the project site and the materials necessary for contract performance. The Navy and the KAF contended that the work site was not bare base and that the materials purchased by the plaintiff to accommodate the extraordinary conditions of the work site were not necessary for contract performance. Specifically, the Navy and the KAF asserted that the work site afforded plaintiff adequate office space and power and that the work site had been completely swept of ordnance. Plaintiff not only disagreed with this characterization of the work site, but also maintained that, unless all materials purchased by plaintiff were shipped to Kuwait and utilized, plaintiff would not be able to perform the contract within the mandatory 90-day deadline.

On June 24,1993, Lieutenant Colonel Faisal M. Ali of the KAF liaison office in Philadelphia, Pennsylvania, wrote to D.F. Young, Inc., Kuwait’s forwarding agent in Baltimore, Maryland, with instructions to hold all shipment of plaintiffs materials. At approximately the same time, the Navy issued Modification P00001 to the contract identifying a list of materials that the Navy considered “ ‘necessary to accomplish the statement of work.’ ” Compl. 1122. Notwithstanding the dispute endangering contract performance, plaintiff decided to commence performance of the second segment with the understanding that 1) the forwarding agent would be permitted to release all materials awaiting shipment to Kuwait, and 2) plaintiff would charge the Navy only for the materials actually required to perform work under the contract.

According to plaintiff, upon its arrival at the work site, the Navy and the KAF recanted their previous position and acknowledged that the site lacked the necessary shelter, power, and water to support the project’s operation. Plaintiff commenced and completed performance within the 90-day period, utilizing all the materials purchased for use under the second segment. On October 6, 1993, plaintiff wrote to the Navy, again reiterating its understanding that plaintiff would be compensated for all materials necessary to [33]*33perform the contract. On November 18, 1993, the Navy and the KAF inspected and accepted plaintiffs work product. The Navy then issued the DD250 form on November 24, 1993, memorializing its acceptance without reservation.

Plaintiff contends that in addition to incurring the costs of the aforementioned materials, plaintiff incurred unreimbursed labor costs, consulting costs, and other costs at a minimum of $1,598,418.00 necessary to complete performance. On May 5,1994, plaintiff submitted a certified claim seeking recovery of its costs. The contracting officer issued a final decision on March 15, 1996, denying reimbursement of the costs claimed, including at least $3,114,483.00 of the costs plaintiff incurred during the course of performance. The decision relied, in part, on the Navy’s position that plaintiffs costs were not “reasonably incurred and not necessary to perform the contract.” Compl. 1133. The materials furnished by plaintiff to perform the contract were consumed during the course of performance, were incorporated into the KAF’s facility and are currently in use, or are being held in a restricted area where plaintiff has no legal right to inspection or appropriation.

On March 14, 1997, plaintiff filed a complaint alleging, inter alia, breach of contract and, in the alternative, a compensable taking of its property. After a year of discovery, defendant moved to dismiss plaintiffs taking claim and any claim based upon allegations of an implied-in-fact contract.

DISCUSSION

When considering a motion to dismiss for failure to state a claim pursuant to RCFC 12(b)(4), the court will follow “the accepted rule that a complaint should not be dismissed ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clear Creek Community Services District v. United States
132 Fed. Cl. 223 (Federal Claims, 2017)
Sonoma Apartment Associates v. United States
124 Fed. Cl. 595 (Federal Claims, 2015)
Keehn v. United States
110 Fed. Cl. 306 (Federal Claims, 2013)
Century Exploration New Orleans, Inc. v. United States
103 Fed. Cl. 70 (Federal Claims, 2012)
Henry Housing Ltd. Partnership v. United States
95 Fed. Cl. 250 (Federal Claims, 2010)
Barlow & Haun, Inc. v. United States
87 Fed. Cl. 428 (Federal Claims, 2009)
Consumers Energy Co. v. United States
84 Fed. Cl. 152 (Federal Claims, 2008)
Tamerlane Ltd. v. United States
80 Fed. Cl. 724 (Federal Claims, 2008)
St. Christopher Associates, L.P. v. United States
75 Fed. Cl. 1 (Federal Claims, 2006)
La Gloria Oil & Gas Co. v. United States
72 Fed. Cl. 544 (Federal Claims, 2006)
Pacific Gas & Electric Co. v. United States
70 Fed. Cl. 766 (Federal Claims, 2006)
Klamath Irrigation District v. United States
67 Fed. Cl. 504 (Federal Claims, 2005)
System Fuels, Inc. v. United States
65 Fed. Cl. 163 (Federal Claims, 2005)
Boston Edison Co. v. States
64 Fed. Cl. 167 (Federal Claims, 2005)
Allegre Villa, Ltd. Partnership v. United States
60 Fed. Cl. 11 (Federal Claims, 2004)
Commonwealth Edison Co. v. United States
56 Fed. Cl. 652 (Federal Claims, 2003)
Detroit Edison Co. v. United States
56 Fed. Cl. 299 (Federal Claims, 2003)
Pi Electronics Corp. v. United States
55 Fed. Cl. 279 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,385, 42 Fed. Cl. 30, 1998 U.S. Claims LEXIS 235, 1998 WL 710634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/integrated-logistics-support-systems-international-inc-v-united-states-uscfc-1998.