Insulation Supply v. Anderson Medical Center

CourtCourt of Appeals of South Carolina
DecidedApril 27, 2005
Docket2005-UP-300
StatusUnpublished

This text of Insulation Supply v. Anderson Medical Center (Insulation Supply v. Anderson Medical Center) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Insulation Supply v. Anderson Medical Center, (S.C. Ct. App. 2005).

Opinion

PREHEARING REPORT

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Insulation Supply Company, Inc.,        Respondent,

v.

Anderson Area Medical Center, Inc.,        Appellant.


Appeal From Anderson County
Alexander S. Macaulay, Circuit Court Judge


Unpublished Opinion No. 2005-UP-300
Submitted April 1, 2005 – Filed April 27, 2005


AFFIRMED


Stephen M. Reams, of Atlanta and Todd R. Davidson and  D. Michael Henthorne, both of Anderson, for Appellant.

Todd Raymond Ellis, Smith Ellis & Stuckey, PA, of Columbia, for Respondent.

PER CURIAM:  Anderson Area Medical Center, Inc. appeals the trial court’s judgment in favor of Insulation Supply Company, Inc. (“ISC”) in a collection action for work completed at the behest of ISC by its subcontractor, Aesthetic Designs, Inc. (“ADI”).  Anderson Medical argues the trial court erred in (1) allowing ISC to recover because ISC was not properly licensed and (2) in calculating the recovery amount.  We affirm.1

FACTUAL/PROCEDURAL BACKGROUND

In July 2000, Anderson Medical’s facility was facing action by the South Carolina Department of Health and Environmental Control (DHEC) regarding fireproofing and fire-stopping concerns.  To avoid being fined or closed, Anderson Medical needed to repair areas of insufficient or failed fireproofing and fire-stopping material at its Health Campus facility.  Anderson Medical’s general contractor, Beers Construction, did not come back and remedy the fireproofing problems when initially demanded.  Anderson Medical then contacted ISC about performing the work.  

ISC is an insulation company that had previously contracted with Anderson Medical on over forty projects since 1996 for the installation and removal of insulation and asbestos as well as, through a subcontractor, for fireproofing services.  Tripp Morris, the vice-president of projects at ISC, testified he met with Anderson Medical representative Mr. Chapman, toured the area where the problems existed, and was asked to begin work on the project right away, or that day if possible.  Morris informed Chapman that ISC did not perform fireproofing work but subbed out that type of work, that ISC’s regular fireproofing subcontractor was unavailable and that ISC did not have its own crews available to start the work immediately.  Chapman asked Morris to find someone to get on the job so Anderson Medical could avoid DHEC sanctions.  Morris then suggested to Chapman that a good candidate for the job would be Charles Chason, owner of ADI.  Morris informed Chapman that ADI was a general carpentry contractor that had no fireproofing experience, but Chason was reputable, and the company was based there in Anderson so it would cut down on hotel and per diem charges of employees that would be incurred if they used ISC’s employees. 

Morris, Chason and Chapman met at the Health Campus facility where Chapman reiterated the need to get the job started and asked for a proposal.  On July 22, 2000, Morris forwarded to Anderson Medical ADI’s proposal to ISC.  The proposal set forth ADI’s hourly rates and provided ISC would supply all fireproofing materials and application equipment while ADI would supply all labor for the repair work and all labor and materials to clean the work areas.  Morris told Chapman ISC would charge Anderson Medical cost plus 20% to perform the work.  The plan was for ISC and ADI to begin work on the deficient areas so that Anderson Medical would not be fined, and to work until the project’s general contractor, Beers Construction, could come back in and complete the work.  ADI was told to proceed with the project. 

At the beginning of the project, Morris was at Anderson Medical twice a week to oversee the work and to ensure ADI met the hospital’s requirements.  Whenever he made site visits, he would check the areas worked on for deficiencies and make sure there were no problems and that Anderson Medical was satisfied.  Between November 2000 and March 2001, ISC sent three invoices to Anderson Medical demanding payment of a total of $294,829 for the work performed.  After DHEC apparently became satisfied with the progress on the fireproofing problems, Anderson Medical terminated ISC and ADI’s work on the project, but refused to pay the submitted invoices.  Thereafter, in January 2002, Beers Construction and its fireproofing contractor undertook the remaining remedial repairs. 

ISC brought suit against Anderson Medical alleging causes of action of breach of their agreement and quantum meruit.  The trial court, sitting without a jury, determined the charges of ISC, with an adjustment for some misapplication, were reasonable and proper and ordered Anderson Medical to pay $278,909.19.  Anderson Medical filed a motion to alter or amend pursuant to Rule 59(e), SCRCP, arguing ISC failed to abide by South Carolina contractor licensing requirements because ADI held only a Group Two license and ISC failed to supervise ADI as required by S.C. Code Ann. § 40-11-270, thereby precluding recovery in this case.  The trial court denied Anderson Medical’s motion to alter or amend and this appeal followed. 

STANDARD OF REVIEW

In an action at law, tried without a jury, the appellate court’s jurisdiction is limited to the correction of errors of law and the trial judge’s findings of fact will not be disturbed on appeal unless found to be without evidence that reasonably supports his findings.  Kemp V. Rawlings, 358 S.C. 28, 34, 594 S.E.2d 845, 848 (2004).  The trial judge’s findings are equivalent to those of a jury in an action at law.  King v. PYA/Monarch, Inc., 317 S.C. 385, 389, 453 S.E.2d 885, 888 (1995).

LAW/ANALYSIS

I.                  South Carolina Contractor’s Licensing Statutes

Anderson Medical first contends the trial court erred in ruling ISC could recover where ISC failed to abide by the requirements imposed by the licensing statutes.  In particular, Anderson Medical asserts ADI lacked the required license for a job of that magnitude and ISC failed to provide the supervision required by law.  Thus, it argues ISC is precluded from bringing an action in either law or equity to enforce the provisions of the agreement.  We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patterson v. Reid
456 S.E.2d 436 (Court of Appeals of South Carolina, 1995)
King v. PYA/Monarch, Inc.
453 S.E.2d 885 (Supreme Court of South Carolina, 1995)
Crestwood Golf Club, Inc. v. Potter
493 S.E.2d 826 (Supreme Court of South Carolina, 1997)
Kemp v. Rawlings
594 S.E.2d 845 (Supreme Court of South Carolina, 2004)
Watson & Howell Builders v. Billingsley
424 S.E.2d 43 (Court of Appeals of South Carolina, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Insulation Supply v. Anderson Medical Center, Counsel Stack Legal Research, https://law.counselstack.com/opinion/insulation-supply-v-anderson-medical-center-scctapp-2005.