Inland Service Corp. v. United States

30 Cont. Cas. Fed. 70,339, 231 Ct. Cl. 974, 25 Wage & Hour Cas. (BNA) 1017, 1982 U.S. Ct. Cl. LEXIS 489, 1982 WL 19289
United States Court of Claims·Decided September 10, 1982·No. No. 437-81C·Published·Cited by 2 cases

Opinion

Plaintiff, Inland Service Corporation,* sues the United States to recover "liquidated damages” assessed by defendant pursuant to the Contract Work Hours and Safety Standards Act (the Act), 40 U.S.C. § 327 and ff, as a penalty for violating provisions contained in the Act. We have jurisdiction, 40 U.S.C. § 330(c); 28 U.S.C. § 1499. Defendant moves for summary judgment on the grounds that the [975] decision of the Secretary of Labor is supported by substantial evidence and is not arbitrary or capricious. There is no triable issue of fact. For the reasons that follow, we grant defendant’s motion and dismiss the petition, without oral argument.

Facts

Plaintiff was the prime contractor on the Department of Army contract DABT 23-76-C-0647 for garbage and waste collection at Fort Knox, Kentucky, executed on June 3, 1976, to run from July 1, 1976, to June 30, 1979. The contract was subject to both the Service Contract Act, 41 U.S.C. §351 and ff, and the Contract Work Hours and Safety Standards Act. Though violations of both acts are present in this case, only those penalties assessed pursuant to the latter Act are the subject of this case.

During the contract period, an investigation by the Department of Labor (dol) disclosed that employees were credited with fewer work hours on time records after March 1, 1978, than for identical assignments prior to that time. Employee interviews revealed that they worked through their 30 minute lunch breaks and up to 40 minutes beyond their 8-hour work day. These extra hours were not recorded on certified payrolls as required by the applicable regulations. Based on certain assumptions regarding the amount of time each employee worked from March 1, 1978, to February 22, 1979, as uncompensated overtime, back wages were initially calculated by the dol at $30,229.52. Mr. Weldon Smith, president of Inland Service Corporation, objected to the dol’s calculation of uncompensated work-time and provided a statement signed by 22 employees which stated that they had been fully compensated for all hours worked. This statement prompted reinterviews by the dol, and based upon additional information thereby obtained and further consultations with Mr. Smith, the estimate of uncompensated worktime was considerably reduced and total back wages recomputed at $10,112.16, apparently a compromise figure. Plaintiff agreed to and did in fact pay this recomputed sum. Along with this recomputed figure, the dol calculated 1,252 violations of the Contract Work Hours and Safety Standards Act for a total of $12,520 [976] in liquidated damages under the terms of 40 U.S.C. § 328(b)(2). That section provides in pertinent part:

In the event of violation of the [Act], the contractor * * * shall be liable to such affected employee for his unpaid wages and shall, in addition be liable to the United States * * * for liquidated damages * * *. Such liquidated damages shall be computed, with respect to each individual employed as a laborer * * *, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of eight hours or in excess of the standard workweek of forty hours without payment of the overtime wages required by [the Act]* * *.

In a letter dated March 21, 1980, the dol advised the Army that liquidated damages might be appropriate. Army contracting officer, Gladys Clark, wrote plaintiff on May 20, 1980, stating that liquidated damages of $12,520 were to be assessed. Plaintiff responded in a letter dated May 27,1980, asserting that violations of the Act occurred notwithstanding the exercise of due care. Contracting officer Clark rejected this assertion, and on June 2, 1980, made specific findings and concluded that liquidated damages of $12,520 were required.

The contracting officer’s findings incorporated those findings made by the dol in its investigation of the instant contract and working conditions thereunder. That investigation found the violations to have begun when a new manager was hired and different managerial practices took effect.

On July 15, 1980, Major Ronald S. Frankel, representing the Secretary of the Army, issued a final order affirming the contracting officer’s determination of liquidated damages. The Secretary’s final order was issued under the provisions of 40 U.S.C. § 330(c) which provides in part:

Any contractor * * * aggrieved by the withholding of a sum as liquidated damages as provided in [the Act] * * * shall have the right * * * to appeal to the head of the agency of the United States * * *. Such agency head * * * shall have authority to review the administrative determination of liquidated damages and to issue a final order affirming such determination; or, if it is found that the sum determined is incorrect or that the contractor * * * violated the [Act] * * * inadvertently notwithstanding the exercise of due care on his part and that of [977] his agents, recommendations may be made to the Secretary [of Labor] that an appropriate adjustment in liquidated damages be made, or that the contractor * * * be relieved of liability for such liquidated damages.

In a letter dated May 20,1981, the Secretary of the Army advised plaintiff of his final order. The petition in this court, seeking review of that order, followed.

I

Defendant’s initial contention is that the decision of the Secretary of the Army is entitled to finality. Section 330(c) provides that the instant order will be entitled to finality with respect to findings of fact "if such findings are supported by substantial evidence.” Under the terms of section 330(c), relief is granted the contractor only if (1) the liquidated damages sum is found incorrect, or (2) he is able to show that he violated the Act "inadvertently notwithstanding the exercise of due care on his part and that of his agents.” (Emphasis supplied.) There is no contention that the liquidated damages is incorrectly computed, therefore, our task is to assess whether the Secretary of the Army’s determination that the contractor and/or his agents did not exercise due care is supported by substantial evidence. We conclude that it was.

Free access — add to your briefcase to read the full text and ask questions with AI

Inland Service Corp. v. United States, 30 Cont. Cas. Fed. 70,339, 231 Ct. Cl. 974, 25 Wage & Hour Cas. (BNA) 1017, 1982 U.S. Ct. Cl. LEXIS 489, 1982 WL 19289 (cc 1982).

30 Cont. Cas. Fed. 70,339 (Inland Service Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shook v. United States
38 Cont. Cas. Fed. 76,424 (Court of Claims, 1992)
Whelan Security Co. v. United States
32 Cont. Cas. Fed. 73,274 (Court of Claims, 1985)