This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).
STATE OF MINNESOTA IN COURT OF APPEALS A24-1313
Ingrid Alexander, Respondent,
vs.
City of Minneapolis, Appellant,
and
Matrix Development LLC, Appellant.
Filed May 5, 2025 Appeal dismissed Bentley, Judge
Hennepin County District Court File No. 27-CV-23-12927
Thomas F. DeVincke, Patrick B. Steinhoff, Malkerson Gunn Martin LLP, Minneapolis, Minnesota (for respondent)
Kristyn Anderson, City of Minneapolis Attorney, Tracey N. Fussy, J. Haynes Hansen, Assistant City Attorneys, Minneapolis, Minnesota (for appellant City of Minneapolis)
Mark Thieroff, Siegel Brill, P.A., Minneapolis, Minnesota (for appellant Matrix Development, LLC)
Considered and decided by Harris, Presiding Judge; Ede, Judge; and Bentley, Judge. NONPRECEDENTIAL OPINION
BENTLEY, Judge
The issue in this appeal is whether a justiciable controversy is presented.
Respondent Ingrid Alexander sued appellants Matrix Development LLC and the City of
Minneapolis to obtain a declaration that the city’s approval of four variances for Matrix
was unlawful. The city and Matrix jointly moved for summary judgment, arguing that the
district court lacked subject-matter jurisdiction. They argued that there was no justiciable
controversy because the city had amended its zoning code so the variances were no longer
required. The district court denied their motion for summary judgment, and they brought
this interlocutory appeal. Then, after the parties filed their principal briefs, the city again
amended its zoning code. The amendment applies retroactively and provides that “[a]ny
zoning approval . . . that becomes unnecessary through the adoption of less restrictive
regulations is void.” Minneapolis, Minn., Ordinance No. 2024-044 §§ 1-2 (November 20,
2024). Because the plain language of the most recent amendment establishes that the
variances Alexander challenges are void, we conclude that this appeal does not present a
justiciable controversy. We therefore lack subject-matter jurisdiction and must dismiss the
appeal.
FACTS
Matrix owns two adjacent properties in Minneapolis that comprise the site of its
development project. In October 2022, it applied for four setback variances in connection
with the project, as required by the zoning code in effect at that time (the 1999 zoning
code). See Minneapolis, Minn. Code of Ordinances (MCO) § 552.810 (2020)). The city
2 granted final approval of the variances in January 2023. Then, in May 2023, the city
adopted a new zoning code (the 2023 zoning code). See Minneapolis, Minn., Ordinance
No. 2023-032 (May 30, 2023). Relevant here, the 2023 zoning code reclassified the project
site’s primary zoning district and updated the applicable setback requirements such that a
project like Matrix’s would no longer require the four variances. See MCO §§ 530.10,
530.300-360, 540.880 (2023)). The relevant section of the 2023 zoning code took effect on
July 1, 2023. Minneapolis, Minn., Ordinance No. 2023-032 (May 30, 2023) (codified at
MCO § 520.40(a)-(b) (2023)). 1 Shortly thereafter, Matrix began construction on its project,
which had an expected completion date of July 2024.
Alexander owns a property adjacent to the project site. In August 2023, she brought
an action in district court under Minn. Stat. §§ 462.361, 555.01-.16 (2024), seeking review
1 The 2023 zoning code included the following scope-of-regulation provision:
(a) In general. All uses of land or structures, all alterations, expansions or relocations of existing structures, and all expansions, relocations or intensifications of existing uses shall be subject to all applicable regulations of this zoning ordinance.
(b) Exceptions. Buildings and uses that require a land use application under the 1999 zoning code will be regulated in accordance with the 1999 zoning code when a complete land use application is submitted prior to July 1, 2023. In all other instances, where a building permit (or grading or earth retention permit for construction of a building) has been issued and all required environmental approvals have been received for the establishment, construction, alteration, expansion, relocation, or intensification of any structure or use prior to the effective date of this zoning ordinance, such action may be completed in accordance with the regulations of the 1999 zoning code, provided the use is established, or construction or
3 of the city’s decision to grant Matrix’s variance requests. Alexander alleged that the city’s
decision was “arbitrary, capricious, unreasonable and contrary to law” and sought a
declaratory judgment to that effect. In their joint answer, Matrix and the city asserted
mootness as an affirmative defense, arguing that the 2023 zoning code applied to Matrix’s
project. They asserted that the action was moot because Matrix’s project could
“proceed . . . without the variances that [Alexander] is complaining about” under the 2023
zoning code.
The parties then filed cross-motions for summary judgment. Alexander sought
summary judgment in her favor, arguing that the city lacked the authority to grant Matrix’s
variances and that its decision was contrary to the statutory requirements for a variance.
Her arguments were predicated on an assumption that the 1999 zoning code applied to
Matrix’s project. In the city and Matrix’s joint motion for summary judgment, they
challenged that assumption, arguing that Alexander’s claim was nonjusticiable because the
variances that the city granted Matrix were unnecessary under the 2023 zoning code.
Alternatively, they maintained that the city acted within its authority and in accordance
with the zoning code when it granted Matrix’s variances.
In an order dated July 22, 2024, the district court denied the city and Matrix’s motion
for summary judgment and granted Alexander’s motion for summary judgment. The
excavation is begun within ninety (90) days of such date and proceeds on a continuous basis toward completion, and subject thereafter to the regulations of Chapter 545, Article VI, Nonconforming Uses and Structures.
MCO § 520.40(a)-(b) (2023).
4 district court determined that Alexander’s claim was not moot because Matrix’s application
for the variances was regulated by the 1999 zoning code. On the merits of Alexander’s
claim, the district court determined that there were no genuine issues of material fact and
that, as a matter of law, the city’s decision to grant Matrix’s variances lacked a rational
basis. The district court ordered “an evidentiary hearing on an appropriate remedy as
opposed to ordering removal of the offending structures.”
Matrix and the city appealed from the denial of their motion for summary judgment.
Alexander moved for this court to dismiss the appeal as premature, but by order of a special
term panel, we denied Alexander’s motion to dismiss because the appeal raises a
jurisdictional issue. The special term panel noted that, because a motion to dismiss for lack
of jurisdiction is immediately appealable, the district court’s order denying appellants’
motion for summary judgment based on lack of justiciability is immediately appealable.
Then, on November 20, 2024, after Matrix and the city filed this appeal but before
oral arguments, the city amended the provision of the zoning code that sets forth the scope
of the 2023 zoning code (the 2024 amendment). Minneapolis, Minn. Ordinance No.
Free access — add to your briefcase to read the full text and ask questions with AI
This opinion is nonprecedential except as provided by Minn. R. Civ. App. P. 136.01, subd. 1(c).
STATE OF MINNESOTA IN COURT OF APPEALS A24-1313
Ingrid Alexander, Respondent,
vs.
City of Minneapolis, Appellant,
and
Matrix Development LLC, Appellant.
Filed May 5, 2025 Appeal dismissed Bentley, Judge
Hennepin County District Court File No. 27-CV-23-12927
Thomas F. DeVincke, Patrick B. Steinhoff, Malkerson Gunn Martin LLP, Minneapolis, Minnesota (for respondent)
Kristyn Anderson, City of Minneapolis Attorney, Tracey N. Fussy, J. Haynes Hansen, Assistant City Attorneys, Minneapolis, Minnesota (for appellant City of Minneapolis)
Mark Thieroff, Siegel Brill, P.A., Minneapolis, Minnesota (for appellant Matrix Development, LLC)
Considered and decided by Harris, Presiding Judge; Ede, Judge; and Bentley, Judge. NONPRECEDENTIAL OPINION
BENTLEY, Judge
The issue in this appeal is whether a justiciable controversy is presented.
Respondent Ingrid Alexander sued appellants Matrix Development LLC and the City of
Minneapolis to obtain a declaration that the city’s approval of four variances for Matrix
was unlawful. The city and Matrix jointly moved for summary judgment, arguing that the
district court lacked subject-matter jurisdiction. They argued that there was no justiciable
controversy because the city had amended its zoning code so the variances were no longer
required. The district court denied their motion for summary judgment, and they brought
this interlocutory appeal. Then, after the parties filed their principal briefs, the city again
amended its zoning code. The amendment applies retroactively and provides that “[a]ny
zoning approval . . . that becomes unnecessary through the adoption of less restrictive
regulations is void.” Minneapolis, Minn., Ordinance No. 2024-044 §§ 1-2 (November 20,
2024). Because the plain language of the most recent amendment establishes that the
variances Alexander challenges are void, we conclude that this appeal does not present a
justiciable controversy. We therefore lack subject-matter jurisdiction and must dismiss the
appeal.
FACTS
Matrix owns two adjacent properties in Minneapolis that comprise the site of its
development project. In October 2022, it applied for four setback variances in connection
with the project, as required by the zoning code in effect at that time (the 1999 zoning
code). See Minneapolis, Minn. Code of Ordinances (MCO) § 552.810 (2020)). The city
2 granted final approval of the variances in January 2023. Then, in May 2023, the city
adopted a new zoning code (the 2023 zoning code). See Minneapolis, Minn., Ordinance
No. 2023-032 (May 30, 2023). Relevant here, the 2023 zoning code reclassified the project
site’s primary zoning district and updated the applicable setback requirements such that a
project like Matrix’s would no longer require the four variances. See MCO §§ 530.10,
530.300-360, 540.880 (2023)). The relevant section of the 2023 zoning code took effect on
July 1, 2023. Minneapolis, Minn., Ordinance No. 2023-032 (May 30, 2023) (codified at
MCO § 520.40(a)-(b) (2023)). 1 Shortly thereafter, Matrix began construction on its project,
which had an expected completion date of July 2024.
Alexander owns a property adjacent to the project site. In August 2023, she brought
an action in district court under Minn. Stat. §§ 462.361, 555.01-.16 (2024), seeking review
1 The 2023 zoning code included the following scope-of-regulation provision:
(a) In general. All uses of land or structures, all alterations, expansions or relocations of existing structures, and all expansions, relocations or intensifications of existing uses shall be subject to all applicable regulations of this zoning ordinance.
(b) Exceptions. Buildings and uses that require a land use application under the 1999 zoning code will be regulated in accordance with the 1999 zoning code when a complete land use application is submitted prior to July 1, 2023. In all other instances, where a building permit (or grading or earth retention permit for construction of a building) has been issued and all required environmental approvals have been received for the establishment, construction, alteration, expansion, relocation, or intensification of any structure or use prior to the effective date of this zoning ordinance, such action may be completed in accordance with the regulations of the 1999 zoning code, provided the use is established, or construction or
3 of the city’s decision to grant Matrix’s variance requests. Alexander alleged that the city’s
decision was “arbitrary, capricious, unreasonable and contrary to law” and sought a
declaratory judgment to that effect. In their joint answer, Matrix and the city asserted
mootness as an affirmative defense, arguing that the 2023 zoning code applied to Matrix’s
project. They asserted that the action was moot because Matrix’s project could
“proceed . . . without the variances that [Alexander] is complaining about” under the 2023
zoning code.
The parties then filed cross-motions for summary judgment. Alexander sought
summary judgment in her favor, arguing that the city lacked the authority to grant Matrix’s
variances and that its decision was contrary to the statutory requirements for a variance.
Her arguments were predicated on an assumption that the 1999 zoning code applied to
Matrix’s project. In the city and Matrix’s joint motion for summary judgment, they
challenged that assumption, arguing that Alexander’s claim was nonjusticiable because the
variances that the city granted Matrix were unnecessary under the 2023 zoning code.
Alternatively, they maintained that the city acted within its authority and in accordance
with the zoning code when it granted Matrix’s variances.
In an order dated July 22, 2024, the district court denied the city and Matrix’s motion
for summary judgment and granted Alexander’s motion for summary judgment. The
excavation is begun within ninety (90) days of such date and proceeds on a continuous basis toward completion, and subject thereafter to the regulations of Chapter 545, Article VI, Nonconforming Uses and Structures.
MCO § 520.40(a)-(b) (2023).
4 district court determined that Alexander’s claim was not moot because Matrix’s application
for the variances was regulated by the 1999 zoning code. On the merits of Alexander’s
claim, the district court determined that there were no genuine issues of material fact and
that, as a matter of law, the city’s decision to grant Matrix’s variances lacked a rational
basis. The district court ordered “an evidentiary hearing on an appropriate remedy as
opposed to ordering removal of the offending structures.”
Matrix and the city appealed from the denial of their motion for summary judgment.
Alexander moved for this court to dismiss the appeal as premature, but by order of a special
term panel, we denied Alexander’s motion to dismiss because the appeal raises a
jurisdictional issue. The special term panel noted that, because a motion to dismiss for lack
of jurisdiction is immediately appealable, the district court’s order denying appellants’
motion for summary judgment based on lack of justiciability is immediately appealable.
Then, on November 20, 2024, after Matrix and the city filed this appeal but before
oral arguments, the city amended the provision of the zoning code that sets forth the scope
of the 2023 zoning code (the 2024 amendment). Minneapolis, Minn. Ordinance No. 2024-
044 (Nov. 20, 2024) (codified at MCO § 520.40 (2024)). The provision as amended reads,
in relevant part:
(b) Exceptions. A complete land use application submitted prior to July 1, 2023, shall be reviewed utilizing the zoning regulations and review processes in place at the time the complete application was submitted and buildings or uses may be established and completed in accordance with the regulations of the 1999 zoning code . . . . An applicant may avail themselves of less restrictive requirements provided by the zoning regulations in effect on July 1, 2023, or later. Any zoning approval granted by the city planning commission,
5 board of adjustment or city council that becomes unnecessary through the adoption of less restrictive regulations is void, and the building or use is no longer subject to the former regulations.
Id. (emphasis added). The 2024 amendment was “effective retroactively from . . . July 1,
2023.” Id.
DECISION
“The presence of a justiciable controversy is ‘essential to [a court’s] exercise of
jurisdiction.’” Cruz-Guzman v. State, 916 N.W.2d 1, 7 (Minn. 2018) (quoting Bicking v.
City of Minneapolis, 891 N.W.2d 304, 308 (Minn. 2017)). To be justiciable, a controversy
must “involve[] definite and concrete assertions of right.” Kahn v. Griffin, 701 N.W.2d
815, 821 (Minn. 2005). “Merely possible or hypothetical injury” will not suffice. Id.
Whether a court has subject-matter jurisdiction over a controversy and whether a case is
moot are issues of law that we review de novo. Snell v. Walz, 985 N.W.2d 277, 283 (Minn.
2023) (mootness). “[L]ack of subject matter jurisdiction may be raised at any time by the
parties or sua sponte by the court, and cannot be waived by the parties.” Dead Lake Ass’n
v. Otter Tail County, 695 N.W.2d 129, 134 (Minn. 2005).
Here, whether we have subject-matter jurisdiction over this action turns on an
interpretation of the city’s zoning code. We review de novo “[t]he interpretation of an
existing ordinance,” RDNT, LLC v. City of Bloomington, 861 N.W.2d 71, 75 (Minn. 2015)
(quotation omitted), and the application of an ordinance to undisputed facts, City of Morris
v. Sax Investments, Inc., 749 N.W.2d 1, 5 (Minn. 2008). Where the plain language of an
ordinance is clear and unambiguous, we enforce the language of the ordinance. See Nelson
6 v. Nelson, 866 N.W.2d 901, 903 (Minn. 2015) (stating that we enforce the plain language
of a statute). As an appellate court, we also “apply the law as it exists at the time [that we]
rule on a case, even if the law has changed since a lower court ruled on the case.” Interstate
Power Co. v. Nobles Cnty. Bd. of Comm’rs, 617 N.W.2d 566, 575 (Minn. 2000).
The 2024 amendment is “the law as it exists at the time” that we consider this appeal.
Id. We therefore must determine whether Alexander’s action is justiciable in light of that
amendment. Our recent decision in Murphy v. City of Minneapolis, in which we interpreted
and applied the 2024 amendment, instructs that a live controversy no longer exists. ___
N.W.3d ___, ___, 2025 WL 1021742, at *10 (Minn. App. Apr. 7, 2025).
In Murphy, the city granted two variances to a developer seeking to build a mixed-
use building. 2025 WL 1021742, at *1. Murphy, whose home is located near the project
site, sought judicial review of the city’s decision to grant those variances in connection
with the project. Id. One of those variances became unnecessary under the 2023 zoning
code, which took effect after the city granted the variances. Id. at *10. On appeal, we
considered whether Murphy’s challenge to that variance presented a justiciable
controversy, which required us to assess the effect of the 2024 amendment on his challenge.
Id. at *9-10. Relying on the plain text of the amendment—that “[a]ny zoning approval
granted by the . . . city council that becomes unnecessary through the adoption of less
restrictive regulations is void”—we concluded that the challenged variance in Murphy was
void. Id. at *10 (quoting MCO § 520.40(b) (2024)). And, as a result, we held that “the
reasonableness of the city’s actions in granting the variance is a nonjusticiable issue.” Id.
The same reasoning applies here.
7 The 2024 amendment renders the variances at issue here void. As in Murphy, there
is no dispute that the setback requirements in the 2023 zoning code that are applicable to
Matrix’s project are “less restrictive” than the requirements in the 1999 zoning code.
Alexander did not dispute in the district court proceedings or on appeal that, if the 2023
zoning code applies, Matrix would not need the variances it sought to proceed with its
project as planned. And because the variances have now become “unnecessary through the
adoption of” the 2023 zoning code, they are void. Id.; see Minneapolis, Minn., Ordinance
No. 2024-044, at §§ 1-2 (November 20, 2024). It follows that “the reasonableness of the
city’s actions in granting the variance[s]” presents a “nonjusticiable issue.” Murphy, 2025
WL 1021742, at *10.
We conclude that we lack subject-matter jurisdiction over this case and therefore
dismiss the appeal. See Farm Bureau Mut. Ins. Co. v. Schwan, 687 N.W.2d 388, 391 (Minn.
2004) (holding that if “an event occurs pending appeal that makes a decision on the merits
unnecessary[,] . . . the issue must be dismissed as moot” (quotation omitted)). Because we
dismiss the appeal, and given its interlocutory nature, we do not grant any relief with
respect to the district court proceedings. The parties may seek appropriate relief in the
district court in light of this opinion and the 2024 amendment.
Appeal dismissed.