Ingham County v. Strojny (In re Strojny)

337 B.R. 150, 2006 Bankr. LEXIS 38
CourtUnited States Bankruptcy Court, W.D. Michigan
DecidedJanuary 5, 2006
DocketBankruptcy No. GT 04-13254; Adversary No. 05-80378
StatusPublished
Cited by5 cases

This text of 337 B.R. 150 (Ingham County v. Strojny (In re Strojny)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingham County v. Strojny (In re Strojny), 337 B.R. 150, 2006 Bankr. LEXIS 38 (Mich. 2006).

Opinion

OPINION REGARDING DISCHARGEABILITY OF DEBT

JAMES D. GREGG, Bankruptcy Judge.

I.JURISDICTION

This court has jurisdiction over this bankruptcy case. 28 U.S.C. § 1334. This bankruptcy case and all related proceedings have been referred to this bankruptcy court for decision. 28 U.S.C. § 157(a) and L.R. 83.2(a) (W.D.Mieh.). This adversary proceeding is to determine the discharge-ability of a debt and is therefore a core proceeding. 28 U.S.C. § 157(b)(2)(I). This opinion constitutes the court’s findings of fact and conclusions of law required to be made after the conclusion of the Plaintiffs proofs. Fed. R. Bankr. P. 7052(c).

II.ISSUES

Does the Debtor owe the Plaintiff a nondisehargeable debt under 11 U.S.C. § 523(a)(2)(A), (a)(4) and/or (a)(6)? Under Fed. R. Bankr. P. 7052(c), should the court determine the dischargeability of the debt at the conclusion of the Plaintiffs eviden-tiary proofs?

III.FACTS

On November 14, 2000, Michael J. Stro-jny, d/b/a Allied Land Services, a sole proprietorship, (“Debtor”), submitted a bid to the Ingham County Parks Department pertaining to the so-called Hawk Island Project. Exh. 1. Subsequently, an Agreement (“contract”) between the Ingham County Parks Department (“Ingham County”) and the Debtor was executed. The Debtor signed the contract on January 10, 2001; Ingham County signed the contract on March 27, 2001. The original contract was for “Beach Dredging and Grading” in the amount of $329,600.00. Exh. 1. In accordance with the contract, the Debtor obtained a Performance Bond from the National American Insurance Company. The Debtor also obtained a Payment Bond from the same insurance company. Exh. 1.

In accordance with Change Order No. 1, dated April 24, 2001, the amount of the contract was reduced to $259,600.00. Subsequently, in accordance with Change Order No. 2, dated September 26, 2001, the contract price was increased to the final amount of $264,600.00. Exh. 2.

As work was completed by the Debtor, the contract provided for progress payments. In accordance with the first Application for Payment submitted on March 1, 2001 by the Debtor, and approved by the Ingham County Project Manager, the Debtor received $48,865.50. Exh. 3. The second Application for Payment was submitted on April 4, 2001 by the Debtor. The application was approved by the Ing-ham County Project Manager on April 13, 2001, in the amount of $61,986.15. When read together, the amounts on the first and second Applications for Payment are consistent. Exh. 4.

[154]*154The third Application for Payment was submitted by the Debtor on May 5, 2001. The Ingham County Project Manager approved the payment, on May 21, 2001, in the amount of $78,678.00. Exh. 5. Comparing the second and third Applications for Payment, it is readily apparent that a mistake in the calculations occurred. On the third payment, the line for “less previous payments” was stated to be $61,986.15. A quick perusal of the second Application for Payment discloses that the Debtor had previously received $110,851.65. The Debtor erroneously carried over the “amount due this application” from the second application to the “less previous payments” in the third application.1 This resulted in a $48,865.50 difference.

Without question, the Debtor made a mistake in calculating the amount due in the third Application for Payment. To further compound the Debtor’s mistake, the Ingham County Project Manager failed to identify the mistake.2

This mistake was carried over to the fourth Application for Payment, Exh. 6, the fifth Application for Payment, Exh. 7, and the final Application for Payment, Exh. 8. In each instance, both the Debtor and the Ingham County Project Manager failed or neglected to recognize the mistake.

In accordance with the testimony of Robert C. Moore, Ingham County Director of Parks, it was the Ingham County Project Manager’s responsibility to review and approve all progress payments. Moore testified that it was not Moore’s responsibility. He further stated that Ingham County did not have financial controls to determine when a contractor, such as the Debtor, had been fully paid in regard to a given contract. Ingham County only maintained records of the funds paid bn the entire project, which often consists of numerous separate contracts. Because Ingham County did not keep track of the payments, it failed or neglected to realize that the Debtor had been overpaid.

After all payments to the Debtor had been made, Ingham County realized that a mistake had been made. Total payments received by the Debtor equaled $313,465.40. Exh. 9. Regretfully for Ing-ham County, it released the Performance Bond and the Payment Bond and could not make any claim thereunder.

On August 27, 2002, the Ingham County Project Manager sent the Debtor a letter requesting reimbursement of the $48,865.50 overpayment within fourteen days. Exh. 13. In that letter, the Ingham County Project Manager identified the miscalculation which occurred, in accordance with the second and third Applications for Payment. Moore, who had over[155]*155all supervisory authority over the project, believed that a “clerical error” had occurred. He originally assumed that the Project Manager had made an error. Later, based upon subsequent events, Moore changed his opinion and came to believe that the Debtor had engaged in fraudulent conduct.

After telephone conversations between the parties, the Debtor stated he intended to reimburse the overpayment by obtaining a loan from National City Bank. Exh. 14. The Debtor requested forty-five days for the loan to be approved. Id. Shortly thereafter, by correspondence dated October 11, 2002, the attorneys for Ingham County sent the Debtor a letter setting forth Ingham County’s understanding of the repayment terms. Exh. 15.

Although the Debtor intended to reimburse the overpayment, and he was successful in subsequently procuring a loan, his business was in trouble. Rather than utilizing the loan proceeds to repay Ing-ham County, the Debtor was forced to pay other business bills in a futile attempt to keep his business alive. Therefore, Ing-ham County was not paid.

On or about February 27, 2003, Ingham County filed a Complaint against the Debt- or in the State of Michigan, Circuit Court for the County of Ingham, seeking judgment for $48,865.50. Exh. 10. The Debt- or, representing himself, filed an answer on or about May 1, 2003. This pro se answer set forth a number of asserted affirmative defenses, none of which were legally valid. Apparently, the Debtor subsequently recognized that his defenses were of little, if any, weight. At a state court hearing on August 20, 2003, the Debtor stipulated to a judgment in the principal sum of $48,865.50. Exh. 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
337 B.R. 150, 2006 Bankr. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingham-county-v-strojny-in-re-strojny-miwb-2006.