Indianapolis-Marion County Public Library v. Shook, LLC

835 N.E.2d 533, 2005 WL 2560211
CourtIndiana Court of Appeals
DecidedOctober 13, 2005
DocketNo. 06A01-0411-CV-488
StatusPublished
Cited by12 cases

This text of 835 N.E.2d 533 (Indianapolis-Marion County Public Library v. Shook, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indianapolis-Marion County Public Library v. Shook, LLC, 835 N.E.2d 533, 2005 WL 2560211 (Ind. Ct. App. 2005).

Opinion

OPINION

BAKER, Judge.

This interlocutory appeal stems from the saga regarding the renovation of the Indianapolis-Marion County Public Library (the Library). In this particular chapter, the appellant-defendant Library appeals the trial court's order denying its motion to dismiss the breach of contract action that was brought by the appellee-plaintiff Shook, LLC (Shook), a general contractor that the Library retained to build a garage for its facility. Specifically, the Library maintains that its motion should have been granted because Shook prematurely filed its breach of contract action against it in the trial court. In the alternative, the Library asserts that the trial court abused its discretion when it did not transfer this action to a county of preferred venue. Finding that the trial court properly denied the Library's motion to dismiss the action, and concluding that there was no abuse of discretion in refusing to transfer the case to another venue, we affirm.

FACTS

On October 28, 2002, the Library awarded a construction contract to Shook for the purpose of building a parking garage adjoining the central library in downtown Indianapolis. Shook commenced work at the site in March 2008. The agreement between the parties consisted of the following documents: Standard Form of Agreement Between Owner and Contractor (Agreement), General Conditions of the Contract for Construction (General Conditions), and Modifications and Supplemental Conditions (Supplemental Conditions).

[536]*536At issue here is Supplemental Condition J, which governed the resolution of claims and disputes between the parties. In relevant part, this condition provided:

If Contractor has a dispute with Owner regarding the application or interpretation of any provision of this Agreement or the breach thereof, the Contractor shall, within ten (10) days after such dispute arises, submit its claim, in writing, to Owner attaching all supporting documentation. Should Owner request additional documentation or information, Contractor shall provide such documentation and/or information promptly. Within thirty (30) days after receiving contractor's written claim and all requested documentation and information, Owner shall respond with its position and proposed resolution of the dispute.... As a condition precedent to initiating any court or arbitration proceeding as provided for in this Article, Contractor must first comply with the provisions set forth herein.

Appellee's App. p. 215. Also, onee the thirty-day period described in the above condition expired, Shook was entitled to send a forum request letter triggering a ten-day period within which the Library could identify the proper forum for litigation or arbitration and venue where Shook could pursue its claims. This ten-day forum period is specifically established in Supplemental Condition J:

Contractor must make a written request to Owner to determine whether the dispute shall be submitted to a court or to arbitration. Owner shall respond to the contractor's request within ten (10) business days after receipt thereof. Owner's response shall identify whether the matter will be submitted to a court or to arbitration.

Appellee's App. p. 216. If the ten-day period expired with no response from the Library, Supplemental Condition J also expressly permitted Shook to "initiatle] any court or arbitration proceeding as provided for in this Article" Appellee's App. p. 215. In addition to providing a payment schedule for the work that Shook had completed for the Library, the Agreement also entitled Shook to monetary compensation and time extensions for additional work that had to be performed.

Although it began as a relatively mundane short story, the relationship of the parties soon exploded into quite the novel with many a subplot. In particular, Shook asserted that it incurred additional costs as a result of a revised traffic control plan that had to be implemented. Shook also maintained that the Library had issued a major structural design change, that extra work had to be performed because of storm damage, that there was active interference with the construction efforts by Library representatives, and that there were additional heating and work suspension costs associated with the project.

Also, during the course of the construction project, various Library representatives discovered numerous defects with the garage structure. The Library maintained that the defects were caused by Shook and that Shook's breaches of the Agreement substantially impacted the parking garage's structural integrity. As a result of an inspection, the Library provided a "Notice of Default" to Shook's bonding company in a letter dated March 19, 2004, regarding a number of significant problems that the Library encountered as a result of the construction. In particular, this notice alleged the following defects:

1. Failure to follow plans and specifications;
2. Placement of reinforcing steel, including stirrups, in violation of American Concrete Institute Code, [537]*537Plans and Specifications, and Field Directives; and
3. Visible voids in concrete in critical areas.

Appellant's App. p. 198-200. As a result of these alleged defects, the Library suspended Shook from working on the garage on or about May 6, 2004. During this period, the Library continued its investigation and inspections in order to determine the extent of the defects. Eventually, the Library issued a directive to Shook that allowed the company to become involved in the necessary repair and remediation process.

At some point, Shook submitted a spreadsheet to the trial court summarizing twenty-five claims that were at issue and identifying the date that the Library had rejected each of its claims. The fourth column of this claim rejection spreadsheet was entitled "Shook Comment on Library Response." That column noted correspondence and other documents reflecting the Library's rejection of each of Shook's claims. The Library rejected Shook's claims at least thirty days prior to June 1, 2004, the date that Shook submitted a forum request letter.

On June 1, 2004, Shook sent the Library a letter summarizing the twenty-five previously rejected claims, requesting that the Library identify a forum in which those claims could be pursued. The final paragraph of Shook's letter stated in its entirety:

Shook requests that the Library indicate whether Shook's claims, to the extent they are disputed by the Library, "shall be submitted to a court or to arbitration."

Appellee's App. p. 116. The ten business-day period expired on June 15, 2004, without the Library having made any forum and venue selection. Hence, on June 22, 2004, Shook filed a complaint in the trial court against the Library, claiming that it had failed to pay claims that were due in exeess of $1.75 million. The claims asserted in this lawsuit mirrored those that had been previously rejected in the letter that Shook had sent on June 1, 2004. Shook's complaint also sought damages from the Library on the grounds that it had engaged in obdurate behavior.

On June 30, 2004, the Library issued a letter in response to Shook's correspondence of June 1, 2004. The letter recognized that Shook's correspondence of June 1 was a summary of claims that had been previously rejected by the Library.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
835 N.E.2d 533, 2005 WL 2560211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indianapolis-marion-county-public-library-v-shook-llc-indctapp-2005.