Brant Construction, LLC and Dune Harbor, LLC v. Circle Electric, Inc. DeBoer Egolf Corp. Auditor, Porter County, Indiana First National Bank of Illinois and Wachovia Financial Srvcs., Inc.

CourtIndiana Court of Appeals
DecidedMay 24, 2013
Docket64A03-1204-CC-159
StatusUnpublished

This text of Brant Construction, LLC and Dune Harbor, LLC v. Circle Electric, Inc. DeBoer Egolf Corp. Auditor, Porter County, Indiana First National Bank of Illinois and Wachovia Financial Srvcs., Inc. (Brant Construction, LLC and Dune Harbor, LLC v. Circle Electric, Inc. DeBoer Egolf Corp. Auditor, Porter County, Indiana First National Bank of Illinois and Wachovia Financial Srvcs., Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brant Construction, LLC and Dune Harbor, LLC v. Circle Electric, Inc. DeBoer Egolf Corp. Auditor, Porter County, Indiana First National Bank of Illinois and Wachovia Financial Srvcs., Inc., (Ind. Ct. App. 2013).

Opinion

Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any May 24 2013, 8:48 am court except for the purpose of establishing the defense of res judicata, collateral estoppel, or the law of the case.

ATTORNEY FOR APPELLANTS: ATTORNEY FOR APPELLEE CIRCLE R ELECTRIC, INC.: MICHAEL L. MUENICH Griffith, Indiana MATTHEW J. HAGENOW Newby, Lewis, Kaminski & Jones, LLP LaPorte, Indiana

IN THE COURT OF APPEALS OF INDIANA

BRANT CONSTRUCTION, LLC; and ) DUNE HARBOR, LLC, ) ) Appellants/Cross-Appellees/Defendants, ) ) vs. ) No. 64A03-1204-CC-159 ) CIRCLE R ELECTRIC, INC.; DeBOER ) EGOLF CORPORATION; AUDITOR, ) PORTER COUNTY, INDIANA; FIRST ) NATIONAL BANK OF ILLINOIS; and ) WACHOVIA FINANCIAL SERVICES, INC., ) ) Appellees/Cross-Appellants/Plaintiffs. )

APPEAL FROM THE PORTER SUPERIOR COURT The Honorable Mary R. Harper, Judge Cause No. 64D05-0907-CC-7800

May 24, 2013

MEMORANDUM DECISION - NOT FOR PUBLICATION

BRADFORD, Judge Appellee/Cross-Appellant/Plaintiff Circle R Electric, Inc. (“Circle R”) contracted

to do work on land owned by Appellant/Cross-Appellee/Defendant Dune Harbor, LLC

(“Dune Harbor”) on a project for which Appellant/Cross-Appellee/Defendant Brant

Construction, LLC (“Brant”) served as the general contractor. Circle R contracted with

both Dune Harbor (“the Dune Harbor Contract”) and Brant (“the Brant Contracts”) and

performed work pursuant to the contracts. Dune Harbor subsequently experienced

financing problems and Circle R was not paid. Dune Harbor failed to pay Circle R

approximately $43,810 for work performed on the Project, and Brant failed to pay Circle

R approximately $26,350.

Circle R filed suit against Dune Harbor and Brant, later amending its complaint to

include DeBoer Egolf Corporation, which had filed mechanic’s liens against Dune

Harbor’s property. Dune Harbor and Brant moved for summary judgment on the bases

that (1) Circle R had not sought arbitration as required by the contracts and (2) payment

to Circle R was not due pursuant to the Brant Contracts because Dune Harbor had never

paid Brant. The trial court entered summary judgment in favor of Circle R. Dune Harbor

and Brant now appeal, contending that the trial court erred in not enforcing the arbitration

clauses and the contingent payment clauses of the Brant Contracts. Concluding that the

trial court should have enforced the arbitration clauses of the Brant Contracts, we reverse

the trial court’s entry of summary judgment in favor of Circle R as against Brant. We

affirm the trial court’s entry of summary judgment in favor of Circle R as against Dune

Harbor and remand for the calculation of attorneys’ fees.

FACTS AND PROCEDURAL HISTORY

2 Dune Harbor owned and was developing the Dune Harbor Marina project (“the

Project”) in 2006 and 2007 before financing was withdrawn. Brant acted as general

contractor and construction manager for the Project. In February of 2006, Dune Harbor

entered into contracts with some subcontractors on the Project, including Circle R and

DeBoer Egolf. Dune Harbor is identified as “Owner” in the Dune Harbor Contract, and

Brant, although not a party, is identified as Dune Harbor’s “Construction Manager.” The

Dune Harbor Contract provides, in part, as follows:

6. Contract Sum Owner shall pay Subcontractor for the performance of the work, subject to additions and deductions by change order as hereinafter provided, the Contract Sum as specified in Item 1.a.(6) above, upon the terms and conditions hereinafter set forth. 7. Progress Payments (Also see Exhibit “A” – Billing Instructions, incorporated herein by reference) Owner agrees to pay Subcontractor, on account of the Contract Sum, progress payments for actual work performed to the satisfaction of the Construction Manager. Owner may, at his discretion, withhold from progress payments due Subcontractor; final payment to be made by Owner to Subcontractor upon acceptance by Owner.

Appellants’ App. p. 34.

The Dune Harbor Contract also contains the following clauses:

13. Disputes In case of any dispute between the Subcontractor and Construction Manager, Subcontractor agrees to be bound to Construction Manager to the same extent that Construction Manager is bound to Owner by the terms of the Contract Documents[1] and by any and all decisions, interpretations, or determinations made thereunder by the persons so authorized in the Contract Documents. Subcontractor further agrees to be bound to Construction Manager to the same extent the Construction

1 “The Contract Documents shall consist of this Agreement, the General Contract between Construction Manager and Owner (identified in item 1.a. (4) and the general and Special Conditions of the General Contract between Owner and Construction Manager (if any).” Appellants’ App. p. 34.

3 Manager is bound to Owner by the final decision of a court of competent jurisdiction, whether or not Subcontractor is a party to such proceedings. …. 14. Arbitration If at any time any controversy should arise between the Construction Manager and Subcontractor with respect to any matter or thing involved in the Contract Documents o[r] the performance thereof, which controversy is not controlled or determined by paragraph 13 hereof or other provisions of the Contract Documents, then the decision of the Construction Manager shall be followed by the Subcontractor, and said controversy shall be ultimately resolved as follows: a. The Subcontractor shall conclusively be bound by and abide by the Construction Manager’s decision, unless the Subcontractor shall commence arbitration proceedings as hereinafter provided within ninety (90) days following such decision. b. If the Subcontractor decided to appeal from the decision of the Construction Manager, then the controversy shall be decided by arbitration in accordance with the rules of the American Arbitration Association, and the decision of the Arbitrator shall be final and binding on both parties.

Appellants’ App. p. 36.

Finally, the Dune Harbor Contract contains the following provision regarding

attorneys’ fees:

31. Attorneys’ Fees In the event either party to this Agreement employs attorneys or incurs other expenses it may deem necessary to protect or enforce their rights under the Contract Documents, then the non-prevailing party in such dispute agrees to reimburse such expenses to the prevailing party, including, but not limited to, attorney’s [sic] fees incurred by the prevailing party.

Appellants’ App. p. 40.

Between October 23, 2006, and May 7, 2007, and for certain specific work, Circle

R entered into the Brant Contracts, contracts to which Dune Harbor was not a party but in

which it is identified as the “Owner.” The contracts provided in part as follows:

4 6. Contract Sum Contractor shall pay Subcontractor for the performance of the work, subject to additions and deductions by change order as hereinafter provided, the Contract Sum as specified in Item 1.a.(6) above, upon the terms and conditions hereinafter set forth. 7. Progress Payments (Also see Exhibit “A” – Billing Instructions, incorporated herein by reference) Contractor agrees to pay Subcontractor, on account of the Contract Sum, progress payments for actual work performed to the satisfaction of the Contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Agco Corporation v. Max Anglin
216 F.3d 589 (Seventh Circuit, 2000)
Beam v. Wausau Insurance Co.
765 N.E.2d 524 (Indiana Supreme Court, 2002)
Ziegler v. Whale Securities Co., LP
786 F. Supp. 739 (N.D. Indiana, 1992)
Oxford Financial Group, Ltd. v. Evans
795 N.E.2d 1135 (Indiana Court of Appeals, 2003)
St. John Sanitary District v. Town of Schererville
621 N.E.2d 1160 (Indiana Court of Appeals, 1993)
State Farm Mutual Automobile Insurance Co. v. D'Angelo
875 N.E.2d 789 (Indiana Court of Appeals, 2007)
Merchants National Bank v. Simrell's Sports Bar & Grill, Inc.
741 N.E.2d 383 (Indiana Court of Appeals, 2000)
Stech v. Panel Mart, Inc.
434 N.E.2d 97 (Indiana Court of Appeals, 1982)
Trimble v. Ameritech Publishing, Inc.
700 N.E.2d 1128 (Indiana Supreme Court, 1998)
Continental Basketball Ass'n v. Ellenstein Enterprises, Inc.
669 N.E.2d 134 (Indiana Supreme Court, 1996)
Newnam Manufacturing, Inc. v. Transcontinental Insurance Co.
871 N.E.2d 396 (Indiana Court of Appeals, 2007)
Indianapolis-Marion County Public Library v. Shook, LLC
835 N.E.2d 533 (Indiana Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Brant Construction, LLC and Dune Harbor, LLC v. Circle Electric, Inc. DeBoer Egolf Corp. Auditor, Porter County, Indiana First National Bank of Illinois and Wachovia Financial Srvcs., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brant-construction-llc-and-dune-harbor-llc-v-circle-electric-inc-indctapp-2013.