312 N.E.2d 503 (1974)

INDIANA AND MICHIGAN ELECTRIC CO., Appellant-Defendant,
v.
WHITLEY COUNTY RURAL ELECTRIC MEMBERSHIP CORP., Appellee-Plaintiff.

No. 3-573A50.

Court of Appeals of Indiana, Third District.

June 19, 1974.

*504 Milford M. Miller, Edward L. Murphy, Jr., Fort Wayne, and C. Erik Chickedantz, Fort Wayne, of Counsel; Livingston, Dildine, Haynie & Yoder, Fort Wayne, for appellant.

Parr, Richey, Obremskey, Pedersen & Morton, Lebanon, Bloom, Bloom & Fleck, Columbia City, for appellee.

GARRARD, Judge.

This case arises under Section 18A of the Rural Electric Membership Corporation Act,[1] which provides for the purchase or condemnation of electric utility property upon annexation of additional territory to a city or town.

In 1967 the Town of Huntertown granted to the appellant (I & M) a franchise to provide electric utility service within the town. On June 12, 1969, the town annexed approximately 69 acres of additional land. At the time of the annexation the 69 acres were within the franchise area of the appellee (REMC). However, at the time of annexation, there were no persons residing within the newly-annexed area and at that time REMC had no tangible or physical property located within the area. After annexation, a residential development was commenced and I & M began constructing facilities into and in the area to supply it with electric service. Shortly thereafter the REMC brought this suit to enjoin I & M's activity. I & M filed a motion for summary judgment which was granted. This summary judgment was later corrected to specify the reasons therefor and REMC's subsequent motion to correct errors was granted and "a new trial" was ordered. Finally, the court, apparently pursuant to Indiana Rules of Procedure, Trial Rule 56(B), granted summary judgment in favor of the REMC. The overruling of I & M's timely filed motion to correct errors addressed to the grant of the latter judgment prompts the present appeal.

As we conclude that the judgment must be reversed, our discussion will be limited to the asserted errors necessary to our decision.

Section 18A of the REMC Act provides:

"Whenever a municipality in which a public utility (including a corporation organized, or admitted to do business, under this act [8-1-13-1 - X-X-XX-XX]) is rendering electric utility service under a franchise, license or indeterminate permit or in which a municipally-owned utility is rendering electric utility service, as the case may be (such public or *505 municipal utility being hereinafter called the `franchised utility'), annexes additional territory and such annexed territory includes any territory in which the franchised utility was not authorized to render electric utility service immediately prior to such annexation but in which some other public utility (including a corporation organized, or admitted to do business, under this act) or municipally-owned utility (such public or municipally owned utility being hereinafter called the `other utility') was lawfully rendering electric utility service at such time, then the franchised utility and the other utility shall promptly negotiate for the purchase by the franchised utility of the property owned by the other utility within the annexed territory and used and useful by the other utility in or in connection with the rendering of electric utility service therein. In the event that such property has not been purchased by the franchised utility within 90 days after such annexation takes place, then the franchised utility may bring an action in the circuit or superior court of the county where such municipality (or the major part thereof in area) is located against the other utility, as defendant, for the condemnation of such property of the other utility. Until and unless such purchase or condemnation is effected, the other utility shall have authority to operate within the portion of the annexed territory in which it was lawfully rendering electric utility service immediately prior to such annexation. [Acts 1935, ch. 175, § 18A, as added by Acts 1953, ch. 48, § 2, p. 153.]" IC 1971, X-X-XX-XX (Burns Code Ed.).

I & M first contends that injunctive relief is inappropriate because REMC has an adequate remedy at law since it could bring an action for inverse condemnation pursuant to IC 1971, XX-XX-X-XX (Burns Code Ed.).

Such a remedy is, however, not adequate in terms of defeating the right to equitable relief unless it is as complete, practical, efficient and adequate as an action in equity. Meyer v. Town of Boonville (1904), 162 Ind. 165, 70 N.E. 146; Fischer v. Carey (1918), 67 Ind. App. 438, 119 N.E. 376.

In considering the adequacy of the suggested legal remedy, we note that the purpose of public utility statutes, including § 18A, is to facilitate service to the public.[2]

We further note that § 18A does not mandate the "franchised utility" to acquire and serve the newly annexed territory, but instead permits the "other utility" to continue serving the area "until and unless" a purchase or condemnation is effected. In addition, our cases have already decided that where the other utility has a franchise for the area and is ready, willing and able to serve, the actual provision of service to customers is not essential to the continuance of its service right. City of Greenfield v. Hancock Co. REMC (1971), 256 Ind. 15, 266 N.E.2d 799; Morgan Co. REMC v. Public Service Co. of Ind. (1970), 253 Ind. 541, 255 N.E.2d 822.

Thus, a proceeding for injunction where the franchised utility has neither purchased nor commenced eminent domain proceedings might provide an early (if perhaps interim) determination of service rights which would be beneficial to the public interest.

In addition, Art. 1, § 21 of the Constitution of Indiana provides that, except in the case of the State, property shall not be taken by law "without such compensation first assessed and tendered." To limit the REMC to proceedings in inverse condemnation would deprive it of this constitutional right. Sidener v. Norristown, H. & St. L. Turnpike Co. (1864), 23 Ind. 623.

*506 I & M next asserts that the statute entitles it to the territory automatically upon annexation; that to perfect the entitlement all it must acquire is "the property owned by the other utility within the annexed territory and used and useful by the other utility in or in connection with the rendering of electric utility service therein"; that since REMC had no property located within the annexed territory there is nothing for I & M to condemn in order to perfect its right to serve; and that therefore there is no basis for injunctive relief. In other words, it is I & M's position that where no property of the other utility is located within the territory at the time of annexation it would be a meaningless gesture to require it to file a condemnation suit which would result in a zero award on the basis that no property has been taken.

We agree that if REMC has no compensable interest, then I & M's right to serve was perfected upon the annexation and no basis for injunction existed.

A plain reading of § 18A with its single subject and conjunctive "and" clearly establishes that the property to be acquired is that which is both located within the annexed area and is used and useful in providing service therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
312 N.E.2d 503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indiana-mich-elec-co-v-whitley-cty-rem-indctapp-1974.