Independent Energy Corp. v. Trigen Energy Corp.

944 F. Supp. 1184, 1996 U.S. Dist. LEXIS 16508, 1996 WL 651024
CourtDistrict Court, S.D. New York
DecidedNovember 4, 1996
Docket94 Civ. 8995 (WCC)
StatusPublished
Cited by38 cases

This text of 944 F. Supp. 1184 (Independent Energy Corp. v. Trigen Energy Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent Energy Corp. v. Trigen Energy Corp., 944 F. Supp. 1184, 1996 U.S. Dist. LEXIS 16508, 1996 WL 651024 (S.D.N.Y. 1996).

Opinion

OPINION AND ORDER

WILLIAM C. CONNER, Senior District Judge:

Plaintiff Independent Energy Corporation filed this diversity action on December 15, 1994. Plaintiff contends that it is entitled to reimbursement of $228,100 plus interest from Defendant Trigen Energy Corporation for expenses that plaintiff allegedly incurred in furtherance of its efforts to develop a construction project in El Salvador. Plaintiff asserts claims against defendant for breach of written and oral promises, common law fraud, failure of consideration, unjust enrichment, and breach of fiduciary duty. Defendant has moved under Fed.R.Civ.P. 56(c) for summary judgment dismissing the complaint or, in the alternative, under Fed.R.Civ.P. 9(b) for an order dismissing plaintiffs common law fraud claim for failure to plead with particularity. Defendant has also moved for partial summary judgment on several of plaintiffs claims in the event that they are not dismissed. For the reasons set forth below, defendant’s motion is granted in part and denied in part.

*1188 BACKGROUND

In 1993, the government of El Salvador, through its nationally-owned utility, Comisión Ejecutiva Hidroeléctrica del Rio Lempa (“CEL”), solicited bids from developers interested in acquiring the right to develop an eighty megawatt electrical generating plant in El Salvador. Pursuant to CEL’s bidding process, the bidder selected by CEL would receive the exclusive right, for a fixed period, to negotiate and enter into a “power purchase agreement” with CEL. This agreement would establish the terms and conditions under which the bidder would agree to construct and operate the power plant, and CEL would agree to purchase electricity from that facility.

With a view toward securing the right to develop the Salvadoran project, United Thermal Corporation (“UTC”) and Plaintiff Independent Energy Corporation (“IEC”), in conjunction with Desarrollos Energéticos Latino Americanos, S.A. (“DELASA”) and La Casa Castro, S.A. (collectively the “Participants”) submitted a bid to CEL on behalf of the “IEC/UTC limited partnership.” 1 In addition, the Participants posted a $2 million bond as required by CEL. CEL’s bidding rules provided that if, after being awarded the project, the successful bidder failed to reach agreement with CEL on the terms of the power purchase agreement by the end of the negotiating period, the bond would be subject to forfeiture.

On February 3, 1994, CEL accepted the Participants’ bid but formally awarded the project to IEC and UTC as independent entities, rather than as a limited partnership. Additionally during this period, Defendant Trigen Corporation (“Trigen”) acquired UTC, although the parties disagree as to whether Trigen formally completed its acquisition of UTC before or after CEL awarded the project.

Trigen’s board of directors harbored reservations about the Salvadoran project and indicated to Trigen’s management that the board would not authorize Trigen to proceed unless Trigen secured an equity partner willing to assume a significant share of the project’s risk, obtained a source of debt financing, and entered into an engineering, procurement, and construction contract (“EPC contract”) with a suitable contractor. 2 By mid-May 1994, Trigen’s management had taken steps to comply with its board’s requirements. Trigen’s management signed a letter of intent with Wartsila Diesel Corporation to enter into an EPC contract and had identified Tenneco Gas International, Inc. as a potential equity partner for the project. Also in May 1994, Trigen signed an agreement with La Casa Castro and DELA-SA setting forth conditions under which Trigen agreed to enter into the power purchase agreement with CEL on behalf of La Casa Castro and DELASA. 3 Last, Trigen sought to modify the proposed power purchase agreement then under negotiation with CEL in order to provide Trigen with the right to cancel the agreement prior to June 17, 1994 or to assign its interest subject to CEL’s approval.

On May 16, 1994, one day before the expiration of the time allotted by CEL for IEC and Trigen to enter into the power purchase agreement with CEL, representatives of IEC and Trigen convened to negotiate IEC’s assignment of its project rights to Trigen. Such an assignment would enable Trigen *1189 alone to sign the power purchase agreement with CEL. At this meeting, IEC’s general counsel proposed that Trigen unconditionally promise to reimburse IEC $228,100 for the expenses IEC had incurred in connection with the project. In exchange for Trigen’s promise to pay, IEC offered to assign its project rights to Trigen immediately. 4 Trigen’s management, however, was unwilling to incur an unconditional obligation to reimburse IEC’s expenses, and after a period of negotiations regarding the reimbursement issue, Trigen and IEC reached the following agreement:

In consideration of the assignment by Independent Energy Corporation (“IEC”) of all of its interests in and to the electrical generating plant to be developed in El Salvador (the “Project”) pursuant to Adju-dicación Licitacion No. CEL-1304 from Comision Ejecutiva Hidroelectrica del Rio Lempa (“CEL”), dated February 3, 1994, including the right to negotiate a power purchase agreement with CEL (the “PPA”), to Trigen and other good and lawful consideration, the receipt and sufficiency whereof is hereby acknowledged, and not withstanding any release by IEC of claims against Trigen in connection with the bid to CEL, Trigen hereby promises to pay to IEC the sum $228,100.00 on the happening of the second of 1) June 17, 1994 and 2) the date on which Trigen receives the approval of its Board of Directors to fully implement the Project, provided that, if Trigen shall not have received such Board approval by December 31, 1994, this promise to pay shall be null and void.

Letter Agreement dated May 16, 1994 attached as Exhibit 3 to Affirmation of Edward Kehoe, dated July 15,1996 (emphasis in original). In addition, IEC obtained agreements from Trigen, DELASA, and La Casa Castro absolving IEC of any obligations stemming from the Salvadoran project.

The following morning, notwithstanding the recently concluded letter agreement between Trigen and IEC, Trigen’s board of directors instructed Trigen’s management not to enter into the power purchase agreement with CEL. However, later that day, Tenneco agreed to accept a complete assignment of Trigen’s interest under the power purchase agreement. Trigen’s board of directors then granted Trigen’s management the authority to execute the power purchase agreement and assign Trigen’s entire interest in the project to Tenneco.

On May 18, 1994, Trigen did, in fact, enter into the power purchase agreement and assign its rights to Tenneco. Tenneco, however, assumed no obligation to reimburse IEC for its development expenses. Subsequently, Tenneco reassigned the project rights to the Coastal Corporation, which guided the project to its completion.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
944 F. Supp. 1184, 1996 U.S. Dist. LEXIS 16508, 1996 WL 651024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-energy-corp-v-trigen-energy-corp-nysd-1996.