Independent Bridge Co. v. Ætna Casualty & Surety Co.

175 A. 644, 316 Pa. 266, 96 A.L.R. 549, 1934 Pa. LEXIS 705
CourtSupreme Court of Pennsylvania
DecidedOctober 3, 1934
DocketAppeal, 117
StatusPublished
Cited by4 cases

This text of 175 A. 644 (Independent Bridge Co. v. Ætna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent Bridge Co. v. Ætna Casualty & Surety Co., 175 A. 644, 316 Pa. 266, 96 A.L.R. 549, 1934 Pa. LEXIS 705 (Pa. 1934).

Opinion

Opinion by

Mr. Justice Maxey,

In April, 1925, Greene and Fayette Counties entered into a written contract with Independent Bridge Company (hereinafter called the bridge company), to build a bridge across the Monongahela River. On April 15, 1925, the bridge company sublet the work of building the approaches and substructure to H. B. Mish Company. On May 22, 1925, H. B. Mish Company and The iEtna Casualty & Surety Company, appellant, delivered to the bridge company a bond conditioned that Mish perform and complete the subcontract, and containing, inter alia, the following: “......it is hereby further stipulated and agreed that the said principal and said surety jointly and severally further covenant and agree with said Independent Bridge Company that any person or persons having a claim for any sum alleged to be due by said principal for any labor or materials furnished in or about the construction of said contract, which shall have remained unpaid for a period of sixty days after the completion and performance of the above mentioned contract and acceptance by the two counties of the work done thereunder, shall have the right to bring suit upon this obligation and to recover any sums as may be justly and legally due him or them. Such suits may be brought in the name of the Independent Bridge Company for the use of the person or persons having such claim......”

*268 James Ainsley, the appellee, sued in the name of the bridge company for his use, to recover for certain coal sold and delivered by him to Mish, which was consumed in firing the boilers, and otherwise in and about the work. The surety denied liability. The case was tried and a verdict rendered for the use-plaintiff in the sum of $1,-891.20, with interest, or the total sum of $2,790.31. Binding instructions for defendant were refused. A rule for judgment n. o. v. was entered and later discharged, the court saying: “In the case at bar it will be noted by reference to the above recited quotations from the contract [i. e., the agreement of the suh-contractor to give the contractor a surety bond ‘conditioned for the faithful performance of this contract in every particular and the payment for all material and labor’] and the bond [heretofore cited in this opinion] that it was the intention that the surety was to be liable to the extent of the penal sum in the bond for the execution or carrying out by the sub-contractor, H. B. Mish Company, of its said contract. That contract obligated it to pay for all the labor and material used by it without regard to the nature thereof and without regard to whether the material became a part of the completed structure. [The phrase of twenty-three words following the word “material” is not found in the contract.] What the use-plaintiff, Ainsley, furnished was just as essential to the performance of the contract by H. B. Mish Company, as was material remaining upon the completion of the contract a component part of the completed bridge.”

The test is not whether the materials furnished were “essential to the performance of the contract.” Such a test would be impracticable. Applying it, even the electric light furnished the laborers to enable them to work after dark, or the food and water supplied them during their employment would be included under the term “materials furnished.” The appellate courts of Pennsylvania have clearly expressed and consistently adhered to a practicable test to be applied in suits of this character.

*269 In Philadelphia, to nse, Aplnt., v. Malone, 211 Pa. 90, 63 A. 539, it was held that where the bond was conditioned that the contractors “shall and will promptly pay all sums of money which may be due for labor and materials furnished and supplied, or performed in and about the said work,” and an inspection of the contract and specifications “discloses nothing whatever which could be construed to include coal furnished for running a steam shovel or locomotive,” “a subcontractor is not entitled to recover against the surety for coal furnished for generating steam to run a steam shovel and a locomotive used in excavating and removing dirt in constructing a reservoir.” This court there also said: “Unless a claimant can show that the labor he performed or the materials he furnished are such as the contractors obligated themselves to furnish the city, he cannot compel payment of his claim by suit against the surety on the bond.......”

An inspection of the specifications in the instant case, so far as they are before us, likewise discloses nothing which can be construed to include coal furnished for any purpose. We cannot accept the reasoning of the court below that because the surety was liable to the extent of the penal sum in the bond for the execution by the subcontractor of its contract with the bridge company, and that that contract obligated it (i. e., H. B. Mish Co.) to pay for all the labor and materials used by it, and that because what Ainsley furnished was “just as essential” to the performance of the contract by the Mish Company as was the material which became a component part of the completed bridge, the surety company is liable for the coal furnished by the use-plaintiff. There was never any question of the liability of the Mish Company to pay for the coal furnished it. The question here is the liability of the surety company to pay for that coal. No such liability can be read into the bond unless the phrase “materials furnished in or about the construction of said contract” is given a meaning not heretofore judicially accepted. In Com., to use, v. Union Indemnity Co., 299 Pa. *270 143, 149 A. 170, it was held that the surety was not liable for gasoline furnished to operate shovels employed in the work. In Com., to use, Aplnt., v. Ætna Casualty & Surety Co., 101 Pa. Superior Ct. 314, it was held that the surety was not liable for lumber, nails, and roofing paper used by a subcontractor for the construction of forms into which concrete was poured for the erection of two bridges on a highway. In Com., to use, Aplnt., v. Empire State Surety Co., 50 Pa. Superior Ct. 404, it was declared to be “the settled rule” here and elsewhere that a surety was not liable for coal oil, tools and nails furnished in and about the construction of a highway, merely for facilitating the work, and that the words “materials furnished” apply only to such materials as enter into and become component parts of the structure. In Com., to use, Aplnt., v. Ætna Casualty & Surety Co., 309 Pa. 263,163 A. 530, the principle underlying the cases just cited, was reiterated, though that was not the pivot of the decision.

In all these cases, though the provisions of the bond were as definite and comprehensive as in the bond now being interpreted, it was held that such provisions gave a right of action only to those who furnished to the principal on the bond material actually incorporated in the completed job. In Philadelphia v. Jackson & Co., Inc., 280 Pa. 319, 124 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pennsylvania Turnpike Commission v. Girard Construction Co.
38 Pa. D. & C. 1 (Philadelphia County Court of Common Pleas, 1940)
Philadelphia School District v. B. A. Shrages Co.
4 A.2d 558 (Superior Court of Pennsylvania, 1938)
Independent Bridge Co. v. Ætna Casualty & Surety Co.
178 A. 473 (Supreme Court of Pennsylvania, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
175 A. 644, 316 Pa. 266, 96 A.L.R. 549, 1934 Pa. LEXIS 705, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-bridge-co-v-tna-casualty-surety-co-pa-1934.