Hempfield Township School District v. Cavalier

164 A. 602, 309 Pa. 460, 1932 Pa. LEXIS 744
CourtSupreme Court of Pennsylvania
DecidedOctober 11, 1932
DocketAppeal, 185
StatusPublished
Cited by22 cases

This text of 164 A. 602 (Hempfield Township School District v. Cavalier) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hempfield Township School District v. Cavalier, 164 A. 602, 309 Pa. 460, 1932 Pa. LEXIS 744 (Pa. 1932).

Opinion

Opinion by

Mr. Justice Maxey,

On July 27, 1928, the School District of Hempfield Township, Westmoreland County, entered into a written contract with Frank Cavalier, John Cavalier and James V. Cavalier, trading as Cavaliers, Contractors, for the construction of a high school. On the same day the Cavaliers, as principals, and the Commercial Casualty Insurance Co., hereinafter referred to as the insurance company, as surety, executed and delivered to the school district a completion bond and in addition thereto a contractor’s bond for labor and material, pursuant to the Act of May 10,1917, P. L. 158. On August 21,1928, the use-plaintiffs, Jerald T. Dougherty and Michael J. Jennings, trading as Dougherty & Jennings, on the one *463 hand, and Cavaliers, Contractors, on the other, entered into a written contract by the terms of which Dougherty & Jennings agreed for the sum of $11,000 to do all the work in connection with the lathing and plastering of the school building. The use-plaintiffs practically completed this work, but they received only $1,500. Cavaliers were entitled to a certain credit of $239.10, leaving the balance due use-plaintiffs of $9,260.90, for which suit was brought against the Cavaliers and against the insurance company. No service was had upon the former and the case proceeded against the latter.

The defense was that by the terms of a proviso in the bond, action “could not be had” on it “after the expiration of one year from the delivery and acceptance of said contract.” Defendant’s contention is that “said contract” meant the contract between the school district and Cavaliers. The trial judge construed the bond to require the institution of suit thereon within one year from the date of the completion and acceptance of the work under the contract, and gave binding instructions for plaintiffs.

It is an elementary proposition that a written contract should in case of doubt be interpreted against the party who has drawn it: 6 R. C. L., page 854, section 242; White v. Smith, 33 Pa. 186. The defendant company drafted the contract in question.

As the insurance company is a corporation engaged in the business of furnishing surety bonds for a monetary consideration, the contract of surety must be construed strictly against it. See Wheaton Coal Co. v. Harris et al., 288 Pa. 294, 135 A. 637, and Fink v. Farmers’ Bank of Harrisburg et al., 178 Pa. 154, 169, 35 A. 636.

In Mechanics Trust Co. v. Fidelity & Casualty Co., 304 Pa. 526, 156 A. 146, this court stated in opinion by the present Chief Justice: “We have frequently said that the trend of modern decisions, federal and state, has been to distinguish between individual and corporate surety-ship, where the surety has undertaken, for money, the *464 contract of .suretyship which it is its business to sell; in such cases, the contract should be construed most strictly in favor of the obligee.”

“The primary rale in the construction of contracts is that the court must, if possible, ascertain and give effect to the mutual intentions of the parties, so far as that may be done without contravention of legal principles. Greater regard is to be had to the clear intent of the parties than to any particular words which they may have used in the expression of their intent:” 13 C. J., page 521, section 482.

“In construing a written contract the words employed will be given their ordinary and popularly accepted meaning, in the absence of anything to show that they were used in a different sense. But they may be given a peculiar meaning when such intent of the parties is shown by the context in Avhich they occur, or by admissible evidence...... Where a Avord has a broad and also a restricted meaning, .both of which are consistent Avith approved usage, the question of which meaning is intended in a particular case must be determined from the context:” 13 C. J., page 531, section 489. “Contracts must receive a reasonable interpretation, according to the intention of the parties at the time of executing them, if that intention can be ascertained from their language. Where the language of a contract is contradictory, obscure, or ambiguous, or where its meaning is doubtful, so that it is susceptible of two constructions, one of Avhich makes it fair, customary, and such as prudent men would naturally execute, while the other makes it inequitable, unusual, or such as reasonable men would not be likely to enter into, the interpretation which makes a rational and probable agreement must be preferred. If one construction would make it unreasonable, while another would do justice to both parties, the latter will be adopted:” 6 B. C. L., page 841, section 230. “It is an established canon of construction that in order to arrive at the intention of the parties, the contract itself *465 must be read in the light of the circumstances under Avhich it Avas entered into. General or indefinite terms employed in the contract may be thus explained or restricted as to their meaning and application. And the contract must be so construed as to give it such effect, and none other, as the parties intended at the time it Avas made. This rule appears to be applicable only Avhere the terms employed are susceptible of more than one meaning. In such case it is the duty of the court not only to regard the nature of the instrument, but also to inform itself of the circumstances Avhich surrounded the parties at the time, so as to interpret the language employed from the standpoint Avhich the parties occupied Avhen they executed the contract6 R. O. L., page 850, section 239.

The application of these canons of interpretation lead to the conclusion that the Avord “contract” in the proviso refers to the Avork under the contract and not to the Avritten instrument itself. In the contractor’s bond for labor and material the first “Avhereas-clause” reads as folloAvs: “Whereas, the said Cavaliers, Contractors, have entered into a written contract Avith School District of Hempfield ToAvnship, Westmoreland County, the obligor, dated the 27th day of July, 1928, for general contract work — Hempfield ToAvnship Consolidated and Junior High School, Westmoreland County, Pa.” There is no doubt as to what Avas referred to in the first part of that clause as “Avritten contract.” There the Avord “contract” Avas given its technical meaning, to wit, an agreement in Avriting Avhich had been “entered into” on July 27, 1928. But it is to be noted that the “whereas-clause” refers not only to a “written contract” but also to “general contract work.” The proviso on the interpretation of which the decision in this case depends, reads as folIoavs : “Provided, however, that no claim shall be secured hereby and no action shall be entered or had on this obligation after the expiration of one full year from and after the delivery and acceptance of said contract by said *466 school district.” The question is whether the antecedent of the phrase “said contract” was the phrase “written contract” in the whereas-clause or the phrase “general contract work,” which appears a little later in the same clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Refining Co. v. Jenkins
189 A.2d 574 (Supreme Court of Pennsylvania, 1963)
Heilwood Fuel Co. v. Manor Real Estate Co.
175 A.2d 880 (Supreme Court of Pennsylvania, 1961)
Jenkins Towel Service, Inc. v. Fidelity-Philadelphia Trust Co.
161 A.2d 334 (Supreme Court of Pennsylvania, 1960)
Barium Steel Corp. v. Wiley
108 A.2d 336 (Supreme Court of Pennsylvania, 1954)
Betterman v. American Stores Co.
80 A.2d 66 (Supreme Court of Pennsylvania, 1951)
Solomon v. Neisner Bros.
93 F. Supp. 310 (M.D. Pennsylvania, 1950)
MOWRY v. McWherter
74 A.2d 154 (Supreme Court of Pennsylvania, 1950)
Fugh Coal Co. v. City of Pittsburgh
70 Pa. D. & C. 299 (Alleghany County Court of Common Pleas, 1949)
Wolter's Estate
61 Pa. D. & C. 133 (Philadelphia County Orphans' Court, 1947)
Harmony Twp. School Dist. v. United States F. & G. Co.
53 Pa. D. & C. 547 (Beaver County Court of Common Pleas, 1945)
Sgarlat v. Griffith
36 A.2d 330 (Supreme Court of Pennsylvania, 1944)
Spingarn v. Fidelity-Philadelphia Trust Co.
49 Pa. D. & C. 383 (Philadelphia County Court of Common Pleas, 1943)
Navarro Corp. v. Pittsburgh School District
25 A.2d 808 (Supreme Court of Pennsylvania, 1942)
Sudnick v. Home Friendly Insurance Co. of Maryland
27 A.2d 468 (Superior Court of Pennsylvania, 1942)
Shallcross v. Highway Trailer Co.
24 A.2d 71 (Superior Court of Pennsylvania, 1941)
Strassburger v. Joseph S. Finch & Co.
22 A.2d 641 (Supreme Court of Pennsylvania, 1941)
Walls v. Gaines
46 Pa. D. & C. 327 (Chester County Court of Common Pleas, 1940)
Ebbert v. Philadelphia Electric Co.
198 A. 323 (Supreme Court of Pennsylvania, 1937)
Pure Oil Co. v. Shlifer
175 A. 895 (Superior Court of Pennsylvania, 1934)
Independent Bridge Co. v. Ætna Casualty & Surety Co.
175 A. 644 (Supreme Court of Pennsylvania, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
164 A. 602, 309 Pa. 460, 1932 Pa. LEXIS 744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hempfield-township-school-district-v-cavalier-pa-1932.