Ind. Comm. v. Alton & Ind

2010 DNH 081
CourtDistrict Court, D. New Hampshire
DecidedMay 7, 2010
DocketCV-08-122-JL
StatusPublished

This text of 2010 DNH 081 (Ind. Comm. v. Alton & Ind) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Comm. v. Alton & Ind, 2010 DNH 081 (D.N.H. 2010).

Opinion

I n d . Comm. v . Alton & I n d . Tower v . Epping, CV-07-82-JL, CV-08-122-JL 5/7/10 P UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

Industrial Communications and Electronics, Inc. et al.

v. Civil N o . 07-cv-82-JL

Town of Alton, David Slade, and Marilyn Slade

Industrial Tower and Wireless, LLC

v. Civil N o . 08-cv-122-JL Opinion N o . 2010 DNH 081 Town of Epping and Jane Burley

MEMORANDUM ORDER

These cases raise the question of whether an intervenor who

presents no independent federal claims can persist in litigating

an action that the principal parties seek to resolve upon a

negotiated settlement. As explained below, the answer is n o .

I. Background

Each of the cases was commenced by a provider of personal

wireless services to challenge a decision by a local land use

authority denying permission to construct a cellphone tower. The

providers claimed that the decisions violated the

Telecommunications Act of 1996 (the “TCA”), specifically 47 U.S.C. §§ 332(a)(7)(B)(i)(II) and 332(a)(7)(B)(iii), and, in one

case, asked for judicial review of the decision as authorized by

N.H. Rev. Stat. Ann. § 677:15. Each provider sought, among other

relief, a declaration that the decision was therefore invalid and

an injunction requiring the defendant town to allow construction

of the proposed tower.

In each case, a local landowner whose property abuts the

proposed tower site subsequently moved to intervene, both as of

right and permissively, under Rule 24 of the Federal Rules of

Civil Procedure. These abutters--David and Marilyn Slade in the

case against the Town of Alton and Jane Burley in the case

against the Town of Epping--argued that the proposed tower would

adversely impact their property interests, particularly by

obstructing their views. The Slades’ motion was granted without

any objection from the provider or explanation by the court. See

Order of Aug. 2 , 2007 (Barbadoro, J . ) . In granting Burley’s

motion over the provider’s objection, the court noted in a margin

order that “[t]he motion satisfies the criteria for intervention

as of right under Rule 24(a)(2). See Nextel Commc’ns of the Mid-

Atl. Inc. v . Town of Hanson, 311 F. Supp. 2d 1 4 2 , 150-52 & 160

(D. Mass. 2004).” Order of Sept. 3 0 , 2008 (Laplante, J . ) .

Following substantial motion practice in each case, the

provider and the town notified the court that they had settled.

2 Alton and the provider in its case filed an “Agreement for Entry

of Consent Decree,” while Epping and the provider in its case

filed a “Joint Motion to Approve and Implement Settlement

Agreement.” Each of these filings called upon the court to issue

an order granting the provider permission to build a cellphone

tower at the proposed location subject to a number of conditions

and, implicitly or explicitly, to enter judgment ending the case.

Each of the filings also noted that the intervenor purported

to “object” to the settlement. The court therefore ordered the

intervenors “to file a memorandum regarding their continued

standing in this matter following such a settlement under

applicable law.” Each intervenor did s o , and responses from the

provider and the town followed (as well as an additional round of

briefing in the Alton case).

II. Analysis

A. The abutters never presented any claims for adjudication

“It has never been supposed that one party--whether an

original party, a party that was joined later, or an intervenor--

could preclude other parties from settling their own disputes and

thereby withdrawing from the litigation.” Local N o . 9 3 , Int’l

Ass’n of Firefighters v . City of Cleveland, 478 U.S. 5 0 1 , 528-29

(1986). In light of this inarguable reality, the intervenors’

3 position that they “object” to the settlement is difficult to

understand. They can no more “object” to the town’s settlement

of claims brought against it than any third party--including,

even, a co-defendant to a claim asserting joint and several

liability--could “object” to another defendant’s settlement of

the plaintiff’s claim against i t .

“Of course, parties who choose to resolve litigation through

settlement may not dispose of the claims of a third party,” so

that “approval of a consent decree between some of the parties

therefore cannot dispose of the claims of nonconsenting

intervenors; if properly raised, these claims remain and may be

litigated by the intervenor.” Id. at 529. The problem here, as

the towns appropriately point out, is that the intervenors have

not “properly raised” any claims of their own. When their

motions to intervene were granted, in fact, Burley filed an

answer without making any counterclaims or cross-claims, and the

Slades did not file any pleading whatsoever. Like the intervenor

in Local 9 3 , the intervenors here “did not allege any causes of

action or assert any claims against” any of the original parties

to the lawsuit. Id. at 507. Just as in Local N o . 9 3 , then, this

court can enter judgment based on the consent of all parties to

the only claims that have in fact been asserted, despite the

intervenors’ purported “objections.” See id. at 529.

4 Burley does not argue to the contrary. Indeed, she concedes

“that if the Town and [the provider] have, in fact, reached a

valid and enforceable settlement of this dispute, then there is

no need for her claims to continue in this forum,” without

identifying what those claims are or whether they were ever

presented here. Again, she never raised any counterclaims.

The Slades, in contrast, argue that despite the settlement

they “retain the right to press their claims that the proposed

telecommunications tower violates local zoning ordinances and

that the ZBA’s decision does not contravene the Federal

Telecommunications Act.” Again, though, the Slades never made

any such claims: they never filed any pleading, and even their

motion to intervene and supporting memorandum do not assert that

Alton’s decision to disallow the tower was consistent with the

TCA. Indeed, until their recently filed briefing on whether

judgment could enter without their consent, the Slades have

submitted nothing whatsoever on the merits of the provider’s TCA

claims, leaving the litigation of that issue to the principal

parties, who filed voluminous summary judgment papers.

Yet the Slades intervened in this case more than two years

ago, and the deadline for amendment of pleadings has long since

passed, with the trial date approaching. This unexplained delay

is reason enough to conclude that the Slades cannot now start

5 pursuing a claim that Alton’s decision to disallow the proposed

tower complied with the TCA.1 See Quaker State Oil Refining

Corp. v . Garrity Oil Co., 884 F.2d 1510, 1518 (1st Cir. 1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2010 DNH 081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ind-comm-v-alton-ind-nhd-2010.