In the Matter of Arbitration Between Maria Victoria Naviera, S.A., Petitioner v. Cementos Del Valle, S.A., and Materiales Los Alpes, S.A.

759 F.2d 1027, 1986 A.M.C. 124, 1985 U.S. App. LEXIS 30354
CourtCourt of Appeals for the Second Circuit
DecidedApril 4, 1985
Docket797, Docket 84-7610
StatusPublished
Cited by19 cases

This text of 759 F.2d 1027 (In the Matter of Arbitration Between Maria Victoria Naviera, S.A., Petitioner v. Cementos Del Valle, S.A., and Materiales Los Alpes, S.A.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the Matter of Arbitration Between Maria Victoria Naviera, S.A., Petitioner v. Cementos Del Valle, S.A., and Materiales Los Alpes, S.A., 759 F.2d 1027, 1986 A.M.C. 124, 1985 U.S. App. LEXIS 30354 (2d Cir. 1985).

Opinion

TIMBERS, Circuit Judge:

Cementos del Valle, S.A. appeals from an order entered in the Southern District of New York, Mary J. Lowe, District Judge, on June 18, 1984, granting the petition of Maria Victoria Naviera, S.A. to compel arbitration under the Federal Arbitration Act, 9 U.S.C. § 4 (1982), of a claim under a maritime charter party, and denying the motion of Cementos del Valle, S.A. to dismiss the petition. We affirm.

On October 15,1982, Maria Victoria Naviera, S.A. (appellee) filed a petition in the Southern District of New York under 9 U.S.C. § 4 to compel Cementos del Valle, S.A. (appellant) and Materiales Los Alpes, S.A. (collectively, respondents) to arbitrate disputes concerning liability for outstanding freight and loading port/discharge port demurrage, detention, extra expenses and all consequential damages incurred on two voyages under a contract of charter party, totaling in excess of $1.2 million in damages. Appellee, a Panamanian corporation, owns the charter party vessel, the M/V KRETAN SPIRIT. Appellant, a Costa Rican cement manufacturer, entered into an agreement to sell cement to Materiales Los Alpes, a Mexican corporation. • On or about September 23, 1981, appellant and Materiales Los Alpes co-chartered the M/V KRE-TAN SPIRIT for certain voyages for the carriage of cement from Costa Rica to Mexico. The first voyage under the charter party was completed. The facts concerning the alleged completion of the second voyage are in dispute.

In response to appellee’s petition, Materiales Los Alpes appointed an arbitrator. On March 21, 1983, after appellant had failed to appoint an arbitrator and had indicated that it was unwilling to join in the appointment of the arbitrator selected by its co-charterer, appellee filed a motion to “compel arbitration”. Appellee moved the court for an order directing the respondents to jointly appoint an arbitrator, and disqualifying the arbitrator appointed by Materiales Los Alpes. On April 20, 1983, appellant filed a cross-motion to dismiss the petition on the ground of lack of personal and subject matter jurisdiction. In its accompanying briefs, appellant also contended that application of the doctrine of forum non conveniens required the district court to dismiss the petition. On June 29, 1983, the court ordered appellant to submit to the jurisdiction of the court for the purpose of enforcing the agreement to arbitrate and *1029 determining its scope. Thereafter, appellant filed an answer to the petition, admitting that on or about September 23, 1981 it entered into a charter party, along with Materiales Los Alpes, to charter the M/V KRETAN SPIRIT. Appellant alleged, however, that the charter party did not embody the entire agreement among the parties; that appellant did not charter the vessel, or ship any of its cement on the vessel on its second voyage; that arbitration under the charter party was limited to general average disputes and disputes arising out of perils covered by standard protective clauses incorporated in the charter party; and that the district court should decline to exercise its jurisdiction under the doctrine of forum non conveniens.

At a hearing on October 7, 1983, the court determined that the arbitration clause of the charter party was sufficiently ambiguous to require a trial to determine whether the parties’ dispute was governed by the agreement to arbitrate. On October 12, 1983, the court ordered the parties to submit a letter regarding their ability to secure the appearance at trial, or the deposition testimony, of the broker who negotiated the charter party, Agencias Marítimas, S. de R.L. (Agenmar). Agenmar had arranged the sale of the cement by appellant to Materiales Los Alpes, and its transport by appellee. Agenmar’s status as a mutual broker for all the parties, or as an agent for only one of them, is disputed. The parties informed the court by letter that Agenmar’s representative would not voluntarily appear, could not be compelled to appear, and could not be deposed in Costa Rica. They stated that written interrogatories were a possibility, but neither party made use of them. Appellee also contended that Agenmar was not an indispensable witness for a trial on the scope of the agreement to arbitrate since, inter alia, the arbitration clause was based on a clause taken from an earlier charter party, and was not negotiated by the parties.

On June 12 and 13, 1984, a trial was held on the scope of the agreement to arbitrate. Materiales Los Alpes did not appear. At trial, appellant contended that the arbitration clause of the charter party was narrow in scope; that appellant was relieved from any obligation to arbitrate, and any liability for, post-loading damages by virtue of another document (the “side agreement”) which purportedly modified the charter party; and that appellant was relieved from any obligation to arbitrate damages related to the second voyage by its alleged cancellation of the charter party and refusal to ship any of its cement on the vessel’s second voyage. Appellant attempted to raise the issue of forum non conveniens, but the court stated summarily that “that will certainly be denied.” Appellant testified that it executed the charter party and the side agreement on October 2, 1981. The court found that the terms of the charter party were fixed on September 22, 1981, by a telex sent to appellee’s representative in New York by Agenmar, and that appellant had failed to establish that the side agreement modified the agreement to arbitrate contained in the charter party. The court further found the arbitration clause of the charter party so broad in scope as to cover all disputes arising under the charter party, and held that all other issues were to be arbitrated. On June 18, 1984, the court granted appellee’s petition to compel arbitration, and denied appellant’s motion to dismiss the petition. On July 16, 1984, appellant filed its notice of appeal from the court’s order. The appeal was withdrawn on October 2,1984, but was reinstated on December 14, 1984.

At issue on appeal are the court’s determination that the agreement to arbitrate covered the underlying dispute, and its decision not to dismiss the petition to compel arbitration on the ground of forum non conveniens.

I.

We hold that there is no real issue as to the scope of the agreement to arbitrate contained in the charter party. The evidence presented at trial was overwhelmingly in support of the court’s finding that *1030 the agreement was unlimited as to the disputes it encompassed.

Appellant, however, contends that the agreement to arbitrate contained in the charter party was modified by a side agreement it executed on October 2, 1981. The court found that the terms of the charter party were fixed by telex on September 22, 1981, and that the agreement to arbitrate was incorporated therein by reference to the terms of another agreement used in drafting, the charter party. It also found that the parties began to perform on or after the fixture date in accordance with the fixture. The court stated that the side agreement would not be found to change the terms of the fixture unless there was proof by a preponderance of the evidence that the signatories to the charter party agreed to the subsequent modification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Promega Corp. v. Life Technologies Corp.
674 F.3d 1352 (Federal Circuit, 2012)
Indian Harbor Insurance v. Global Transport System, Inc.
197 F. Supp. 2d 1 (S.D. New York, 2002)
ACEquip Ltd. v. Am. Eng'g Corp.
153 F. Supp. 2d 138 (D. Connecticut, 2001)
Bodner v. Banque Paribas
114 F. Supp. 2d 117 (E.D. New York, 2000)
W.J. Nolan & Co. v. Midway Federal Credit Union
913 F. Supp. 806 (S.D. New York, 1996)
Ishwar Jain v. Henri Courier De Mere
51 F.3d 686 (Seventh Circuit, 1995)
Filanto, S.P.A. v. Chilewich International Corp.
789 F. Supp. 1229 (S.D. New York, 1992)
Cotter v. Shearson Lehman Hutton, Inc.
126 F.R.D. 19 (S.D. New York, 1989)
Rush v. Oppenheimer & Co., Inc.
681 F. Supp. 1045 (S.D. New York, 1988)
Finkielstain v. Seidel
692 F. Supp. 1497 (S.D. New York, 1988)
Transunion Corp. v. Pepsico, Inc.
640 F. Supp. 1211 (S.D. New York, 1986)
Oil Basins Ltd. v. Broken Hill Proprietary Co.
613 F. Supp. 483 (S.D. New York, 1985)
Matterhorn, Inc. v. Ncr Corporation
763 F.2d 866 (Seventh Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
759 F.2d 1027, 1986 A.M.C. 124, 1985 U.S. App. LEXIS 30354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-arbitration-between-maria-victoria-naviera-sa-ca2-1985.