In re Vermont Gas Systems, Inc. (William Marks, Nancy Baker, Linda Gage, Rachael Smolker, Melanie Pulley, Stephanie Spencer, and Lawrence Shelton, Appellants)

2017 VT 83, 174 A.3d 1253
Supreme Court of Vermont·Decided September 22, 2017·No. 2016-396·Published·Cited by 3 cases

Opinions

ROBINSON, J.

¶ 1. This appeal requires us to decide whether land dedicated to a public use may be condemned for another public use when the new use does not materially interfere with the prior use. Intervenors, a group of Hinesburg residents who use Geprags Park, appeal the Public Service Board's order authorizing Vermont Gas Systems, Inc. (VGS) to condemn an easement through the park for the purpose of installing a natural gas pipeline. They argue that the Board erred in authorizing the condemnation in light of the fact that the park was already dedicated to a public use, and in concluding that the condemnation was necessary under 30 V.S.A. § 112(a)(2). We affirm the Board's decision on the issues raised in this appeal, but remand for a minor correction to the order relating to the terms of the easement.

¶ 2. The following background facts provide context to this appeal. VGS had previously constructed a pipeline from the Canadian border to Burlington, was providing natural gas services to customers in Chittenden and Franklin counties, and sought to expand its services to customers in Addison County. In December 2012, VGS filed a petition with the Board for approval of a forty-one mile pipeline expansion that would run from Colchester to Middlebury. Under 30 V.S.A. § 248(a)(3), VGS could not commence construction unless the Board concluded that the pipeline would promote the general good of the state and issued a certificate of public good (CPG) authorizing the project. Throughout the CPG proceedings, VGS's proposed route for the expansion included a segment that went through Geprags Park in Hinesburg. The Board concluded that the project satisfied the eleven criteria established in § 248(b). It determined that the project would not impose undue negative consequences on any of the affected regions and identified several benefits that would flow from the project, including lower energy costs and a decrease in greenhouse gas emissions. The Board ultimately concluded that the pipeline would promote the general good of the state and issued a CPG in December 2013. VGS began constructing the pipeline expansion in the summer of 2014.

¶ 3. The undisputed facts concerning the immediate appeal are as follows. Dora Geprags devised the park at issue to the Town of Hinesburg in 1991. A covenant in the decree of distribution provides that "the property decreed hereby shall be used only as a public park or school or for public recreational or educational purposes." The park covers approximately eighty-five and a half acres and contains a barn, a sledding hill, and walking trails. VGS sought an easement through this park in order to complete its pipeline expansion, but the Town would not voluntarily convey the easement to VGS because it determined that the decree's covenant restricted its ability to do so. Subsequently, VGS and the Town stipulated to condemnation of an easement through the park for the pipeline.

¶ 4. In October 2015, VGS filed a petition of condemnation with the Board, seeking to condemn a 1987-foot-long and fifty-foot-wide easement that runs north to south on the western side of the park. By that time, VGS had acquired easement rights from all other property owners along the pipeline route, prepared the pipeline corridor up to the northern and southern boundaries of the park, and begun construction of the pipeline on other parts of the route; the easement through the park was the last segment of the pipeline route that VGS needed to acquire to complete construction of the expansion.

¶ 5. In March 2016, several residents of the Town and the Hinesburg Conservation Commission filed motions to intervene in the proceeding. The Board initially denied these motions but after the intervenors filed a motion to reconsider, it allowed some, but not all, of the movants to intervene because they had a substantial interest in the use and enjoyment of the park which was different than that of the Town, and this interest could be impacted by the proceeding. These intervenors are the appellants in this appeal.

¶ 6. In March 2016, the Town's selectboard held a public meeting and voted against ratification of the stipulation with VGS. Soon thereafter, VGS filed an amended petition of condemnation with the Board, acknowledging that the Town no longer stipulated to the condemnation. VGS and the Town engaged in further discussions, and on August 1, 2016, they signed a revised stipulation for condemnation of an easement to the west of, and roughly parallel to, the Vermont Electric Power Company (VELCO) electricity transmission easement that ran through the park. The stipulation included the agreed-upon compensation for the easement, terms of VGS's distribution of natural gas to customers in Hinesburg, and conditions that would restrict VGS's use of the easement. It provided that VGS would use horizontal directional drilling (HDD), meaning it would drill bores in the properties to the north and south of the park to install the pipeline thirty to fifty feet underground throughout the length of the easement without disrupting the land within the park. 1 The stipulation provided that VGS would comply with plans to protect the golden-winged warbler habitat in the vicinity of the pipeline and to conserve the recreational uses and ecology of the park. The stipulation also included a proposed deed of easement that provided more details about VGS's rights and restrictions.

¶ 7. The Board conducted a site visit of the park on August 2, 2016, and held an evidentiary hearing two days later on August 4. VGS witnesses testified about the alternative routes VGS had analyzed and the impact of the easement on the park. 2 Intervenors did not present testimony or other evidence. In their post-hearing briefing, intervenors contended that: (1) the prior public use doctrine as articulated by this Court barred the condemnation because the park was already dedicated to a public use; (2) if the Board were to recognize an exception to the public use doctrine that allowed condemnation when the new use would not materially interfere with the prior use, the easement would materially interfere with the use of the park; and (3) the condemnation was not necessary as required by 30 V.S.A. § 112(a)(2) because VGS did not show that the alternative routes were infeasible, more costly, or would result in greater impacts to natural resources.

¶ 8. On September 13, 2016, the Board issued a written order authorizing VGS to condemn the easement in the park. First, the Board determined that VGS had satisfied the requirements of 30 V.S.A. § 112. It concluded that the condemnation was reasonably necessary pursuant to § 112(a)(2) so that VGS could provide adequate natural gas service in Addison and Chittenden counties.

¶ 9. With respect to the applicability of the prior public use doctrine, the Board recognized that this Court has not squarely addressed whether land dedicated to a public use may be condemned for another public use when the new use does not materially interfere with the prior use. It explained that other jurisdictions have recognized an exception to the doctrine which allows the condemnation of land when the new public use does not destroy or materially impair the prior public use.

Free access — add to your briefcase to read the full text and ask questions with AI

In re Vermont Gas Systems, Inc. (William Marks, Nancy Baker, Linda Gage, Rachael Smolker, Melanie Pulley, Stephanie Spencer, and Lawrence Shelton, Appellants), 2017 VT 83, 174 A.3d 1253 (Vt. 2017).

2017 VT 83 (In re Vermont Gas Systems, Inc. (William Marks, Nancy Baker, Linda Gage, Rachael Smolker, Melanie Pulley, Stephanie Spencer, and Lawrence Shelton, Appellants)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related