In re Vermont Electric Generation & Transmission Cooperative, Inc.

502 A.2d 841, 146 Vt. 235, 1985 Vt. LEXIS 378
CourtSupreme Court of Vermont
DecidedAugust 14, 1985
DocketNo. 85-241
StatusPublished
Cited by1 cases

This text of 502 A.2d 841 (In re Vermont Electric Generation & Transmission Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Vermont Electric Generation & Transmission Cooperative, Inc., 502 A.2d 841, 146 Vt. 235, 1985 Vt. LEXIS 378 (Vt. 1985).

Opinion

Gibson, J.

Vermont Electric Generation and Transmission Cooperative, Inc. (VEG&T) appeals from a decision of the Vermont Public Service Board (Board) denying its petition for approval of long-term financing. In the proceedings before the Board, VEG&T sought permission to convert into permanent, [236]*236long-term financing from the Rural Electrification Administration (REA) some $634,000 in short-term borrowings it had accumulated while making payments toward its share of the construction of the Seabrook nuclear power project (Seabrook).

VEG&T contends that the Board’s decision must be reversed because (1) it is unsupported by the evidence; (2) the Board gave no notice that it would consider the merits of the Seabrook project herein, but instead had given notice that it would consider that issue in a separate proceeding in which all interested Vermont utilities, including VEG&T, were to participate; (3) the Board provided VEG&T with no opportunity to litigate the issue of whether a default by VEG&T on its obligations to Seabrook was a viable risk; and (4) the Board’s findings are inadequate to support its decision. For the reasons stated herein, we reverse.

The hearing examiner found, among other things, that VEG&T requires $634,000 to finance its participation in Seabrook Unit No. 1 for the period between January 1, 1985 and April 16, 1985; that VEG&T has been advised by the National Rural Utilities Cooperative Finance Corporation (CFC), its source of short-term borrowings, that CFC would stop advancing funds if VEG&T did not immediately convert its short-term Seabrook borrowings to permanent long-term debt; that, although “rolling over” short-term debt in this fashion would make available more short-term borrowing capability for VEG&T to use for additional Seabrook progress payments, “VEG&T will not use this financing to increase its obligations associated with Seabrook Unit No. 1.”

At the hearing, the Department of Public Service “was unwilling to recommend to the Board a course of action that would precipitate the VEG&T’s default upon its Seabrook obligations at this time . . .” and recommended a prohibition of any further short-term financing of Seabrook Without prior Board approval. The hearing examiner found that the proposed long-term financing was “consistent with the general good of the State of Vermont.”

Subsequently, at oral argument before the Board, the Department argued that the hearing examiner’s proposal for decision should be affirmed and that the Board should thereafter require VEG&T to obtain its approval for any renewed short-term borrowings for Seabrook. The Board adopted the hearing examiner’s findings of fact; however, it concluded that “further VEG&T long-term financings for Seabrook investments are not in the best [237]*237interests of the State of Vermont, and that they should be denied.” The Board stated that the only direct consequence of its ruling was that VEG&T would have to continue to pay short-term rates for the loans then outstanding; it was not persuaded that CFC might cut off further short-term loans if the permanent financing was disallowed. Finally, it concluded “that VEG&T’s request to borrow more money to invest in the Seabrook project should be denied.” (Emphasis added.)

In reviewing this matter, it is important to consider the context in which it arose. The Seabrook project consists of two 1,150-megawatt nuclear power units utilizing pressurized water reactors. Construction began in July 1976, and as of November 1983 Unit No. 1 was 88% complete. (At that time Unit No. 2 was 28% complete.) The project was originally estimated to cost a total of $1,175 billion, with Unit No. 1 to be in service by November 1979 and Unit No. 2 by September 1981. Delays and cost overruns have escalated the cost to a point where the Board noted, in its May 3, 1985 order in separate Docket No. 4701, that when Unit No. 1 is ready for commercial operation (recent forecast: December 31, 1986), the total investment in the project will have reached $5.3 to $6 billion.

VEG&T has an ownership interest of 0.41259%, a 9745-kilo-watt share in each unit. The Board has approved numerous prior applications of participating Vermont utilities for long-term financing in connection with Seabrook. On November 30, 1984 the Board approved VEG&T’s application for $2,500,000 in long-term financing to cover its share of construction costs and interest during construction through December 31, 1984. At that time, the Board refused to approve VEG&T’s request to issue $11,567,500 in long-term financing to finance its share of the completion of Seabrook, stating that the evidence was insufficient to convince the Board that completion of Seabrook Unit No. 1 was in the best interests of Vermont ratepayers. It referred to a reopened earlier docket (No. 4701), which it planned to use as a forum “to review the economics and rate impact of the project” and in which to decide whether Vermont utilities should be allowed to finance the completion of Seabrook.

On December 28, 1984 the Board scheduled a hearing to be held on April 16, 1985 in Docket No. 4701, and ordered that, if final financing plans, including regulatory approvals, for completing Seabrook were not in effect by April 15, 1985, each Vermont [238]*238utility having an interest therein should be prepared to show cause “why the Board should not enter an order requiring such utility immediately to take all feasible and prudent steps to effect the cancellation of the [Seabrook] project and/or terminate its participation therein.” A motion for reconsideration filed by the Department was denied by the Board in an order dated January 15, 1985 wherein the Board noted that there was “a significant legal question as to whether the Board, absent a finding that PSNH [Public Service Company of New Hampshire, the principal owner of Seabrook] has not managed this project in accordance with sound practices, can order Vermont utilities to default on their contractual obligations,” and that there were possible constitutional issues connected therewith.

The hearing in Docket No. 4701 resumed on April 17, 1985, at which time position statements and offers of proof were taken, but no evidence. It was represented to the Board that owners of more than 75% of the project did not then have financing in place to carry the project to completion and that one of the major owners had been ordered by the Massachusetts Department of Public Utilities on April 4, 1985 not to complete its financing. That order has been appealed to the Supreme Judicial Court of Massachusetts.

On May 3, 1985 the Board, in Docket No. 4701, notified the Vermont utilities to prepare for a show cause hearing at which the Board would consider whether it should enter an order requiring cessation of future payments for Seabrook. That hearing had not been held as of the date of argument herein.

In reviewing an appeal from the Board, this Court accords great weight to decisions that are within the Board’s expertise, In re Young’s Community TV Corp., 141 Vt. 53, 55-56, 442 A.2d 1311, 1312 (1982), and defers to the findings and conclusions of the Board unless they are clearly erroneous. In re Central Vermont Public Service Corp., 141 Vt. 284, 288, 449 A.2d 904, 907 (1982); 30 V.S.A. § 11(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Burlington Electric Light Department
542 A.2d 294 (Supreme Court of Vermont, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
502 A.2d 841, 146 Vt. 235, 1985 Vt. LEXIS 378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-vermont-electric-generation-transmission-cooperative-inc-vt-1985.