In Re the Grand Rapids Public Utilities Commission

731 N.W.2d 866, 2007 Minn. App. LEXIS 70, 2007 WL 1531862
CourtCourt of Appeals of Minnesota
DecidedMay 29, 2007
DocketA05-2550
StatusPublished
Cited by4 cases

This text of 731 N.W.2d 866 (In Re the Grand Rapids Public Utilities Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the Grand Rapids Public Utilities Commission, 731 N.W.2d 866, 2007 Minn. App. LEXIS 70, 2007 WL 1531862 (Mich. Ct. App. 2007).

Opinion

OPINION

DIETZEN, Judge.

In this certiorari proceeding, relator challenges the amount of a compensation award ordered by the Minnesota Public Utilities Commission (Commission) pursuant to Minn.Stat. § 216B (2006) to compensate an electric utility for territory it annexed as provided by law. Relator argues that the Commission’s order (1) was arbitrary and capricious and not supported by substantial evidence; and (2) was unconstitutional. We affirm.

FACTS

The City of Grand Rapids provides electricity to the area within its municipal boundaries through the Grand Rapids Public Utilities Commission (City). The City’s annual sales in kilowatt hours (kWh) is approximately 147 million kWh. Lake Country Power Cooperative Electric Association (Lake Country) provides electricity to a large area outside of municipal-utility service boundaries in eight counties in northern Minnesota. Lake Country’s service area completely surrounds the City. Its annual sales are just above 600 million kWh.

In June 2003, the City filed a petition with the Minnesota Public Utilities Commission (Commission) under Minn.Stat. § 216B.44 (2002), exercising its right to extend its assigned service area to include two areas recently annexed to the city but located within the assigned service area of Lake Country. The petition asked the Commission to adjust the City’s service-area boundaries to include these areas and *869 to schedule a contested-case proceeding to determine appropriate compensation to Lake Country as required by the statute. 1 In making a determination of the appropriate compensation, Minn.Stat. § 216B.44(b) requires the Commission to consider (1) the original cost of the property, less depreciation; (2) loss of revenue to the utility formerly serving the area; (3) expenses resulting from integration of facilities; and (4) other appropriate factors.

The administrative law judge (ALJ) assigned to the case conducted a two-day evidentiary hearing in June 2004. Witnesses, including experts, were presented by the City and Lake Country. The parties reached agreement on virtually all compensation factors except lost revenue. Based on different conclusions regarding the application of the “net-revenue-loss” formula to the facts, the City advocated a total award of $204,402, or 16.5 mills/kWh, limited to existing customers, and Lake Country advocated a total award of $521,657, or 35.4 mills/kWh for present customers and 32.4 for future customers.

Following the hearing, the ALJ issued findings, conclusions, and a recommendation for a compensation award to Lake Country for lost revenue of $233,820 (unadjusted for present value), or 15.5 mills/kWh. In reaching the recommendation the ALJ adopted the City’s proposed calculation method and rejected Lake Country’s proposed award. Alternatively, the ALJ recommended a compensation award of $270,850, using the gross-revenue-multiplier formula.

Lake Country filed exceptions to which the City responded, and the matter was presented to the Commission. Subsequently, the Commission filed its Order Determining Compensation, which was supported by findings and conclusions. The Commission concluded that it would use the “net-revenue-loss” formula to calculate the “loss of revenue to the utility formerly serving the area” required by the statute, with the objective of putting the displaced utility in the same position it would have occupied but for the loss of service rights to the area for which compensation is being determined.

The “net-revenue-loss” formula was developed by the Commission in 1990, with several refinements and clarifications in subsequent cases. The formula (1) determines gross revenues for each year of the compensation period, which the Commission has set at ten years, to reflect the intermediate planning period of most utilities; (2) determines avoided costs that the utility would no longer be required to incur because it is no longer serving the area (such costs would include the purchase of power to be sold within the area); (3) subtracts the avoided cost from the gross revenues, which results in yearly net-revenue loss for each year in the ten-year compensation period; and (4) reduces net revenue losses to present value. Due to the uncertainty of future events, the lump-sum amount calculated under this method is often converted into a kilowatt-per-hour rate, or mill rate, and payment is made at this mill rate over the compensation period.

The Commission found that the primary difference between the parties in the calculations of lost revenue was how the parties calculated “avoided costs,” or the costs that Lake Country would avoid by not serving the annexed areas and that would be deducted from the areas’ gross revenue, to arrive at a net-revenue-loss figure. Based on its analysis, the Commission awarded Lake Country a total compensa *870 tion rate of 30 mills/kWh. The Commission rejected the ALJ’s report and, with minor adjustment, adopted Lake Country’s proposed compensation award. The City filed a petition for rehearing and reconsideration, which was denied. This certiorari appeal followed.

ISSUES

1. Was the Commission’s compensation award to Lake Country arbitrary, capricious, contrary to law, or unsupported by substantial evidence in the record?

2. Was the Commission’s compensation award to Lake Country unconstitutional?

ANALYSIS

I.

The City argues that the Commission’s order was arbitrary and capricious and not supported by substantial evidence. When reviewing agency decisions, we adhere to the fundamental concept that decisions of administrative agencies enjoy a presumption of correctness and that deference should therefore be shown by courts to the agency’s expertise and its special knowledge in the field. Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 824 (Minn.1977). The agency decision-maker is presumed to have the expertise necessary to decide technical matters within the scope of the agency’s authority. In re Excess Surplus Status of Blue Cross & Blue Shield of Minn., 624 N.W.2d 264, 278 (Minn.2001).

A. ALJ Report

Initially, the City argues that the Commission erred by rejecting the ALJ’s report. The decision of the ALJ is entitled to some weight. In re Denial of Eller Media Co. 's Applications for Outdoor Adven Permits, 664 N.W.2d 1, 6 (Minn.2003). But the agency decision-maker owes no particular deference to the ALJ’s findings, conclusions, or recommendation. Blue Cross & Blue Shield, 624 N.W.2d at 278. Although an agency owes no particular deference to the ALJ’s report, Minn.Stat. § 14.62 (2006), requires an agency to give reasons for its rejection of the ALJ’s recommendation, and failure to do so is evidence that the agency’s decision was arbitrary and capricious. Bloomquist v. Comm’r of Natural Res.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Moorhead v. Red River Valley Cooperative Power Ass'n
811 N.W.2d 151 (Court of Appeals of Minnesota, 2012)
In Re the City of Redwood Falls
756 N.W.2d 133 (Court of Appeals of Minnesota, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
731 N.W.2d 866, 2007 Minn. App. LEXIS 70, 2007 WL 1531862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-grand-rapids-public-utilities-commission-minnctapp-2007.