In Re the City of Redwood Falls

756 N.W.2d 133, 2008 Minn. App. LEXIS 353, 2008 WL 4394711
CourtCourt of Appeals of Minnesota
DecidedSeptember 30, 2008
DocketA07-1957
StatusPublished
Cited by1 cases

This text of 756 N.W.2d 133 (In Re the City of Redwood Falls) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the City of Redwood Falls, 756 N.W.2d 133, 2008 Minn. App. LEXIS 353, 2008 WL 4394711 (Mich. Ct. App. 2008).

Opinion

OPINION

KLAPHAKE, Judge.

Relator City of Redwood Falls (the city) challenges a compensation order issued by respondent Minnesota Public Utilities Commission (the commission). Because we conclude that the commission erred in ordering compensation with respect to relator’s wastewater treatment facility, but observe no error in the commission’s calculation of compensation due for other, annexed areas, we affirm in part and reverse in part.

FACTS

This appeal arises from a dispute over the compensation due in relation to a municipal acquisition of utility property under Minn.Stat. § 216B.44 (2006). In 2005, the city filed a petition with the commission seeking a determination of compensation due for a number of recently annexed areas for which the city now wished to become the electric utility provider. Until that time, each of the areas had received electricity from Redwood Electric Cooperative (the cooperative), the primary provider of electricity for unincorporated areas of Redwood County. The city also sought a determination from the commission that the city had the right — without paying compensation — to take over the provision of electricity to its wastewater treatment facility, which is located in a service area acquired by the city from Northern States Power (NSP) in 1998 but which had been receiving services from the cooperative since 1996.

The commission referred the matter to an administrative law judge (ALJ) for a contested case hearing. In written findings of fact, conclusions, and recommended order, the ALJ concluded that: (1) the cooperative was not, as a utility customer, entitled to compensation for loss of waste-water treatment ponds because there was no written service-exception agreement between NSP and the cooperative, but that, to avoid unjust enrichment to the city, compensation should be required for facilities that the cooperative had installed that were compatible with the city’s electric facilities; (2) the cooperative was not entitled to compensation for future customers in the Prairie Knoll subdivision, which did not yet have any residents and had been developed by the city at significant expense; and (8) the appropriate rate of compensation for the remaining areas was 21.28 mils per kilowatt hour (kWh) of electricity used.

Both the city and the cooperative filed exceptions to the ALJ’s report, although the city’s exceptions were “simply to clarify or correct certain findings.” The cooperative challenged the ALJ’s findings and recommendations with respect to (1) the denial of compensation for the transfer of the wastewater treatment ponds to city power and (2) the calculation of the power cost adjustment component of gross revenues for purposes of determining appropriate compensation.

Following a hearing on the exceptions, the commission rejected both of the challenged recommendations. With respect to the wastewater treatment facility, the commission determined that, although it had *136 never been reduced to writing, a valid service-exception agreement did exist between NSP and the cooperative, but that the terms of that agreement were unclear. Under these unique circumstances, the commission decided that compensation was appropriate, but that it should be calculated based on a five-year compensation period instead of the ten-year period typically allowed by the commission.

With respect to the power cost adjustment component, the commission determined that the ALJ had improperly used the actual pre-acquisition power cost adjustment — which blended the cost of power that the cooperative purchased from the Western Area Power Administration (WAPA) and the more expensive, supplemental power that it purchased from Great River Energy (GRE). The commission determined that the power cost adjustment should be based only on the higher priced GRE power because that was the power that the cooperative would cease to purchase post-acquisition.

Using the revised power cost adjustment calculation, the commission granted a final compensation award of 29.7 mils per kilowatt hour. On the cooperative’s motion for reconsideration, the commission issued a corrective order granting a higher rate of- compensation, 32.9 mils per kilowatt hour, for the wastewater treatment facility.

The city appeals.

ISSUES

1. Did the commission err by determining that the cooperative was entitled to compensation for the loss of the wastewa-ter treatment facility as a customer?

2. Did the commission err by using only the higher, supplemental power cost to calculate gross revenues for the purposes of determining the appropriate rate of compensation?

ANALYSIS

Pursuant to the Minnesota Public Utilities Act (the MPUA), electric utilities are assigned exclusive service territories and may not serve customers within an area assigned to another utility unless the other utility “consents thereto in writing.” Minn.Stat. § 216B.40. Notwithstanding these limitations, however, a utility owned by a municipality that extends its corporate boundaries through annexation or consolidation may coextensively extend its service territory by purchasing the facilities of another utility. Minn.Stat. § 216B.44(a). The municipal utility must compensate the previously assigned utility for “the appropriate value of its properties ... giving due consideration to revenue from and value of the respective properties.” Id. § 216B.44(b).

If the two utilities are unable to agree on the value of the properties being transferred, either utility may petition the commission for a determination of appropriate compensation. In making that determination, the commission must consider “the original cost of the property, less depreciation, loss of revenue to the utility formerly serving the area, expenses resulting from integration of facilities, and other appropriate factors.” Id. Where, as here, the commission departs from the recommendations of an administrative law judge, the commission “must include the reasons for each rejection or modification.” Minn. Stat. § 14.62, subd. 1 (2006); see also Bloomquist v. Comm’r of Natural Res., 704 N.W.2d 184, 190 (Minn.App.2005) (explaining that, although not binding on the commission, the ALJ’s findings should not be taken “lightly”).

In reviewing decisions by the commission, this court “adherefs] to the funda *137 mental concept that decisions of administrative agencies enjoy a presumption of correctness and that deference should therefore be shown by courts to the agency’s expertise and its special knowledge in the field.” In re Grand Rapids Pub. Utils. Comm’n, 731 N.W.2d 866, 870 (Minn.App.2007) (citing Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 824 (Minn. 1977)).

Agency decisions following contested-case hearings are reviewed under the Administrative Procedure Act, which provides that such decisions may be reversed or modified if

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Moorhead v. Red River Valley Cooperative Power Ass'n
811 N.W.2d 151 (Court of Appeals of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
756 N.W.2d 133, 2008 Minn. App. LEXIS 353, 2008 WL 4394711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-city-of-redwood-falls-minnctapp-2008.