In Re the Complaint of Hercules Carriers, Inc.

614 F. Supp. 16, 1984 U.S. Dist. LEXIS 25013
CourtDistrict Court, M.D. Florida
DecidedSeptember 14, 1984
Docket80-563-Civ-T-GC
StatusPublished
Cited by1 cases

This text of 614 F. Supp. 16 (In Re the Complaint of Hercules Carriers, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re the Complaint of Hercules Carriers, Inc., 614 F. Supp. 16, 1984 U.S. Dist. LEXIS 25013 (M.D. Fla. 1984).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

DANIEL HOLCOMBE THOMAS, District Judge.

The above styled ease was heard by the Court without a jury commencing on May 21, 1984, and ending on May 25, 1984. The evidence was concluded by one deposition on May 29, 1984, which was submitted to the Court for consideration. After having heard all of the evidence, examining the *17 exhibits, pleadings, stipulations, and Proposed Findings of Fact and Conclusions of Law submitted by all parties, the Court makes the following Findings and Fact and Conclusions of Law as to the damages sustained by the Department of Transportation, State of Florida, (hereinafter DOT) as a result of the collision of the M/V SUMMIT VENTURE with the Sunshine Skyway Bridge on May 9, 1980.

FINDINGS OF FACT

1. At or about 0734 on May 9, 1980, the M/V SUMMIT VENTURE struck the Sunshine Skyway Bridge located at the entrance to Tampa Bay. On May 12, 1980, Hercules Carriers, Inc. (hereinafter Hercules) as owner of the M/V SUMMIT VENTURE, filed its complaint pursuant to 46 U.S.C. § 183, et seq. and Rule F, Supplemental Rules, for certain admiralty and maritime claims, praying in the alternative for either exoneration from or limitation of liability with respect to all claims for damages which might be asserted against the vessel and/or Hercules arising out of the collision. Numerous claims were also filed for wrongful death, personal injury and property damage, as well as counterclaims and cross-claims against various parties. Prior to this trial, some of the above claims were determined by the Court, namely:

(a) This Court denied Hercules’ claim for exoneration from or limitation of liability, holding that Hercules is liable for all damages resulting from the collision of the M/V SUMMIT VENTURE with the Sky-way Bridge.

(b) Upon completion of the limitation trial, the Court next elected to try all wrongful death and personal injury claims which now have all been resolved by trial or settlement.

The Court next set this matter down for trial. The trial included the following issues:

(a) The damages, if any, sustained by the DOT as a result of the M/V SUMMIT VENTURE striking the Skyway Bridge.

(b) Whether the DOT was negligent in designing and/or protecting and/or maintaining the bridge, and if so, whether such negligence was a contributing cause to the collision or to the damages sustained to the bridge.

The trial did not include, by stipulation of the parties with the consent of the Court, the following issues:

(a) Hercules’ counterclaim for damages';

(b) Hercules’ claim that the DOT was negligent in failing to provide proper aids to navigation;

(c) Hercules’ claim that the State of Florida negligently hired and/or retained Pilot Lerro;

(d) Hercules’ claim that the DOT should have had a device on the bridge to warn motorists in the event the bridge failed. The above issues will be set for trial at a later date. At the conclusion of that trial, a judgment will then be issued with respect to the State’s claim.

2. To the extent pertinent, the facts stipulated to by the parties and incorporated in this Court’s Findings of Fact and Conclusions of Law dated March 14, 1983 (See 566 F.Supp. 962 (S.D.Ala.)) are reincorporated herein as if fully set forth.

3. The Sunshine Skyway Bridge is a twin bridge toll facility and carries U.S. Route 19 and Interstate Route 275 traffic over and across Tampa Bay. The entire bridge is approximately five miles in length with the remaining 10 miles made up of causeway and land highway.

4. The main ship channel is spanned by a bridge approximately 5,621 feet in length, with the main channel clearance being 800 feet and a minimum vertical clearance of 141.6 feet above the water.

5. The bridge consists of a three-span steel cantilever truss with a center span of 864 feet flanked by 360 foot anchor arms on either side for a total length of 1,584 feet. The cantilever truss spans are supported on four concrete piers designated as IN and 2N on the Northside of the main channel and IS and 2S on the Southside. The remainder of the bridge consisting of *18 two 289 foot 3 inch deck trusses, six 140 foot steel girder spans and six 100 foot steel girders were not involved in this collision. Exhibit A attached to these findings illustrates the relevant portions of the bridge.

6. The bridge is made up of a two lane northbound span and a two lane southbound span. These two spans are separated by a distance of approximately 100 feet. It was the southbound span that was struck by the M/V SUMMIT VENTURE. The northbound span was only slightly damaged.

7. On May 9, 1980, the bow of the M/V SUMMIT VENTURE collided with Pier 2S of the southbound span. The initial impact was between the flared bow of the ship and the west column of Pier 2S. Almost simultaneously the bulbous bow of the vessel hit the pedestal of Pier 2S. As a result, both east and west columns of Pier 2S collapsed and 1,261 feet of the superstructure fell into the bay below. This included the south anchor span from Pier 3S to Pier 2S, the south cantilever span, and the drop-in span, as indicated in Exhibit A.

8. Within seconds after the bulbous bow hit the pedestal, the vessel deflected to port causing it to scrape alongside Pier 2S.

9. The DOT elected to construct a new four lane span, rather than to rebuild the damaged southbound span.

10. The Court finds that any repairs if made to the portion of the bridge damaged by the M/V SUMMIT VENTURE would not extend the overall useful life of the bridge, nor would they enhance its value. The Court further finds that the repairs, if made, would put the bridge back to its pre-collision condition.

11. As a result of the collision, the Coast Guard ordered the DOT to immediately clear the channel in order to reopen the harbor to vessel traffic.

12. Because of the numerous and varied claims for damages, the Court will make special findings of fact for each element of damages claimed.

BRIDGE REPAIR — PROPERTY DAMAGE

13. The Court finds that actual loss and damage sustained by the DOT to the superstructure of the southbound span as a result of the collision of May 9, 1980, was as follows:

(a) The entire span between 2S and 3S, the entirety of the anchor span between 2S and IS, and a part of the southern portion of the cantilever structure extending from Pier IN over the channel were destroyed and would have to be rebuilt in their entirety.

(b) The deck trusses and various members between Piers 3S and 4S were damaged and would have to be repaired or replaced.

(c) A portion of the bridge extending north from Pier IN was damaged and would have to be replaced or repaired.

(d) All navigation and aerial lights plus the connecting conduits were destroyed and would have to be replaced.

14. The Court finds that the damage to the substructure of the southbound span as a result of the collision was as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
614 F. Supp. 16, 1984 U.S. Dist. LEXIS 25013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-complaint-of-hercules-carriers-inc-flmd-1984.