In re the Acquisition of Real Property by the Village of Saranac Lake

93 A.D.3d 971, 939 N.Y.S.2d 654
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 8, 2012
StatusPublished
Cited by2 cases

This text of 93 A.D.3d 971 (In re the Acquisition of Real Property by the Village of Saranac Lake) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Acquisition of Real Property by the Village of Saranac Lake, 93 A.D.3d 971, 939 N.Y.S.2d 654 (N.Y. Ct. App. 2012).

Opinion

Malone Jr., J.

Appeal from an order of the Supreme Court (Demarest, J.), entered August 19, 2010 in Franklin County, which, in 11 proceedings pursuant to EDPL article 4, among other things, partially granted certain respondents’ cross motions for, among other things, awards of costs and counsel fees.

In August 2005, petitioner commenced these eminent domain proceedings pursuant to EDPL article 4, seeking easements to access a sewer line running under respondents’ respective properties along the shore of Lake Flower in the Village of Saranac Lake, Franklin County that had discharged raw sewage into the lake.1 By order to show cause, petitioner also sought immediate access to respondents’ properties, alleging that financial and environmental issues made it necessary to complete the work before the end of 2005. After reviewing respondents’ opposition to the application and following an appearance before it, Supreme Court granted petitioner immediate access to respondents’ properties and the repairs were completed.

In the meantime, respondents submitted answers and objections to the petitions and, in April 2006, Supreme Court ordered a fact-finding hearing to resolve various issues raised by respondents, including the scope and location of the easements, whether petitioner had been entitled to immediate access to the properties pursuant to EDPL 402 (B) (6) and whether petitioner had complied with the provisions of EDPL article 3. The parties did not conclude the hearing, which took place over the course of five days between December 2006 and July 2007; they instead reached a partial settlement pursuant to which the parties agreed to the location and scope of each of the easements and several respondents agreed to the valuation of their respective easements, while others reserved their rights to seek additional compensation. However, all respondents reserved their rights to seek an award of counsel fees and costs based upon various alleged procedural improprieties by petitioner during the acquisition process, including its alleged failure to comply with EDPL articles 2 and 3 and its allegedly improper application for immediate access to the properties.

In June 2008, petitioner moved by orders to show cause for [973]*973orders of condemnation and acquisition pursuant to the parties’ settlement agreement. Respondents Wayne Bujold, Denise Wilson (also known as Denise Bujold), Edward Dukett, Joseph Fiorile, John Banta, Linda Banta and Lakeside House, Inc. opposed the motion and cross-moved for, as is relevant here, costs, counsel fees and sanctions, including the costs associated with defending against petitioner’s two prior unsuccessful attempts to obtain the easements.2 Supreme Court issued orders of condemnation, but determined that petitioner had made misrepresentations to the court in its application for immediate access to the properties and had not complied with the offer and negotiation requirements of EDPL article 3. Therefore, the court granted those parts of the cross motions seeking costs and counsel fees, including those resulting from the prior proceedings, and denied those parts seeking sanctions. Petitioner appeals.

As is relevant here, discretionary allowances, including counsel fees and costs, may be ordered if a court “determines that the condemnor was not legally authorized to acquire the property” (EDPL 702 [B]). Here, Supreme Court determined that, by not complying with EDPL article 3 and by making misrepresentations in its application pursuant to EDPL 402 (B) (6) for immediate access to respondents’ properties, petitioner was not legally authorized to acquire the easements and, thus, respondents were entitled to discretionary allowances.

However, contrary to Supreme Court’s findings, the record reflects that, with respect to the instant proceedings, petitioner satisfied the requirements of EDPL article 3 by hiring an appraiser and, based upon that appraiser’s report, extending written offers of compensation to each respondent in an amount that petitioner believed reflected just compensation for interest it sought to acquire (see EDPL 303).3 Notably, each written offer informed respondents that the appraiser determined that there [974]*974would be “no measurable change in the value of [respondents’] property” as a result of the easement, but that petitioner “recogni[zed] that some minimal value should be imputed to the rights taken.” Although Supreme Court faulted petitioner for making the offers two months after the commencement of the instant proceedings, we note that the Eminent Domain Procedure Law does not require that offers be made prior to the commencement of the eminent domain proceeding (see EDPL 303 [“Wherever practicable, the condemnor shall make the offer prior to acquiring the property” (emphasis added)]). Finally, contrary to Supreme Court’s finding, “[t]here is no requirement that petitioner ‘plead or prove, as a prerequisite to the acquisition of the [easements] by eminent domain, that it negotiated in good faith with the [property] owner[s]’ ” (Matter of National Fuel Gas Supply Corp. v Town of Concord, 299 AD2d 898, 899 [2002], quoting Oswego Hydro Partners L.P. v Phoenix Hydro Corp., 163 AD2d 829 [1990]).4 If respondents believe the offer of compensation to be inadequate, their remedy is to seek additional compensation in a proceeding pursuant to EDPL article 5. Based on the foregoing, we find that the record does not support the court’s determination that, with respect to the instant proceedings, petitioner failed to satisfy its EDPL article 3 obligations prior to acquiring the easements.

Nor does the record support Supreme Court’s finding that petitioner was not entitled to immediate access to respondents’ property. Although respondents neither appealed from the order granting petitioner immediate access nor made a motion to reargue or renew, Supreme Court nevertheless apparently reconsidered that order in deciding the issue of whether the moving respondents were entitled to compensation pursuant to EDPL 702 (B). Pursuant to EDPL 402 (B) (6), when a court is satisfied “that the public interests will be prejudiced by delay, it may direct that the condemnor be permitted to enter immediately upon the real property to be taken, and devote it temporarily to the public use specified in the petition.”

In support of its application for immediate access, petitioner submitted evidence that, among other things, it was in danger of losing its no-interest financing for the repairs if it did not close on that financing before October 6, 2006. Petitioner’s proof in that regard, which is not controverted by respondents, [975]*975established that the work needed to be completed before the end of the year 2005 in order for petitioner to complete the additional steps needed to close on the financing before October 2006. If petitioner lost the no-interest financing, it would be forced to secure conventional financing at the market rate of interest, which would result in a large additional expense for its taxpayers. Petitioner provided additional proof that raw sewage from the sewer line servicing respondents’ properties had leaked into the lake and that the Department of Environmental Conservation, the Department of Health and the Environmental Protection Agency had all expressed concerns about additional raw sewage discharge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Acquisition of Easements by Bluestone Gas Corp. of New York, Inc.
116 A.D.3d 1182 (Appellate Division of the Supreme Court of New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
93 A.D.3d 971, 939 N.Y.S.2d 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-acquisition-of-real-property-by-the-village-of-saranac-lake-nyappdiv-2012.