In Re Sanner Contracting Co.

181 B.R. 465, 1995 Bankr. LEXIS 636, 1995 WL 283912
CourtUnited States Bankruptcy Court, D. Arizona
DecidedMay 4, 1995
DocketBankruptcy 89-11744-PHX-SSC
StatusPublished
Cited by3 cases

This text of 181 B.R. 465 (In Re Sanner Contracting Co.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Sanner Contracting Co., 181 B.R. 465, 1995 Bankr. LEXIS 636, 1995 WL 283912 (Ark. 1995).

Opinion

OPINION

SARAH SHARER CURLEY, Bankruptcy Judge.

PROCEDURAL BACKGROUND

This matter comes before this Court on a “Motion to Approve Compromise with Caliber Bank” filed on February 3, 1994 by Robert J. Davis, the Chapter 7 Trustee (hereinafter “the Trustee”). On March 17, 1994, Bank of America, formerly known as Caliber Bank (hereinafter “BA”), filed a “Notice of Supplementing Record” in which BA provided a fully executed copy of the settlement agreement.

On March 30, 1994, SANNER CONTRACTING CO. (hereinafter “Debtor”) filed an “Objection to Trustee’s Motion to Approve Compromise With Caliber Bank”. The Debtor argued that BA did not have a perfected security interest in the settlement proceeds from the litigation on the contract between the Debtor and the Bureau of Indian Affairs; and that BA had only obtained a perfected security interest on certain “contract rights” and “accounts”, which did not include the settlement proceeds. BA filed a response to the Debtor’s objection on April 6.

On April 6, the Debtor filed a motion to continue the hearing and requested a further opportunity to respond to the issues raised by BA in its Response. This Court granted the Debtor’s Motion to Continue the hearing on the Trustee’s Motion to Compromise, because of the unique issues involved and because an evidentiary hearing was required. 1

The Court conducted the evidentiary hearing on June 7, 1994, July 29, 1994, and September 1, 1994. BA filed a hearing memorandum on June 6; the Trustee, on June 7; and the Debtor, on August 31, 1994.

At the conclusion of the hearing on September 1, 1994, this Court then deemed the matter under advisement.

This constitutes this Court’s findings of fact and conclusions of law pursuant to Rule 7052, Rules of Bankruptcy Procedure (hereinafter “RBP”). This is a “core” proceeding and this Court has jurisdiction over this matter. 28 U.S.C. §§ 1334 and 157.

FACTUAL BACKGROUND

A. The Loan Agreement Between The Debtor And BA.

BA loaned funds to the Debtor and took a security interest in certain personal property of the Debtor pursuant to the Accounts Financing Revolving Loan and Security Agreement dated July 23, 1985. 2 BA perfected its security interest in certain property on July 30, 1985 by the filing of the UCC-1 Financing Statement -with the Arizona Secretary of State. 3 The UCC-1 expressly stated, in part, that the collateral for the loan included:

All accounts receivable, instruments, chattel paper and contract rights now in existence or that may hereafter be acquired and all proceeds thereof in any form. 4

BA filed a continuation statement on July 15, 1991 with the Secretary of State to maintain its perfected security interest in the collater *468 al. 5

B. The BIA Contract.

The Debtor subsequently bid on a contract with the Bureau of Indian Affairs (hereinafter “BIA”). 6 Pursuant to the letter dated September 27, 1987, Debtor was awarded BIA Contract No. H50C14207326 (hereinafter “Contract”). 7 This Contract contained provisions regarding the variation in estimated quantity of fill or rock to complete the job, suspension of work, disputes as to the performance of the contract, differing site conditions, site investigation, conditions affecting the work and changes. 8 The differing site conditions provision stated:

If conditions do materially so differ and cause an increase or decrease in the Contractor’s costs of, or the time required for, performing any part of the work under this contract whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly. 9

The Contract provided that the Debtor would perform grading, draining and placing aggregate sub-base on a 9.9039-mile stretch of the roadway to be constructed on Routes 70 and 71 of the Fort Apache Indian Reservation in Navajo and Apache Counties, Arizona. 10 The BIA initially agreed that the Debtor would be paid $1,312,474.40, pursuant to the Debtor’s estimate. 11 The completion date was subsequently extended by the parties due to difficulties encountered by the Debtor. BIA personnel, primarily in the Phoenix office located away from the job site, had prepared the plans as to the construction project. The Contract was to balance the excavating cut and fill work so that no excess dirt or importation of dirt was contemplated. 12 The Contract also contemplated that there would be normal site conditions; that is, no huge boulders or rocks were to be encountered. Because of the construction problems encountered by the Debtor, the BIA and the Debtor modified the Contract on two separate occasions to extend the date of performance. 13 The parties modified the Contract to provide that the Debtor would be paid the sum of $1,414,322.50. 14 The Debtor ultimately completed the project eighty-nine days late.

C. The BIA Litigation and Settlement.

Throughout construction, the Debtor had meetings with the BIA officials. The Debtor asserted that it was entitled to an additional sum of $970,950 in compensation to complete the Contract. At the Agency level and as part of the initial discussions between the Debtor and the BIA contracting officer, the BIA only conceded that the Debtor was entitled to reimbursement for increased costs of $52,966, which the Debtor rejected. 15 The Debtor filed a certified claim with the BIA for $941,500, but there was no decision from the BIA contracting officer. 16 The Debtor then filed a notice of appeal with the Interior Board of Contract Appeals (hereinafter “IBCA”), but the appeal was dismissed without prejudice, with the BIA contracting officer at the agency level to render a decision within sixty days. 17 No decision was rendered. The Debtor then filed a second notice of appeal and a complaint. 18 The Debtor *469

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Millennium Bank v. UPS Capital Business Credit
2014 COA 30 (Colorado Court of Appeals, 2014)
In Re Genesis Health Ventures, Inc.
266 B.R. 591 (D. Delaware, 2001)
In Re Dow Corning Corp.
198 B.R. 214 (E.D. Michigan, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
181 B.R. 465, 1995 Bankr. LEXIS 636, 1995 WL 283912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-sanner-contracting-co-arb-1995.