In Re Ryerson Hill Solid Waste Disposal Site

379 A.2d 384, 11 ERC 1042, 1977 Me. LEXIS 387
CourtSupreme Judicial Court of Maine
DecidedNovember 7, 1977
StatusPublished
Cited by7 cases

This text of 379 A.2d 384 (In Re Ryerson Hill Solid Waste Disposal Site) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Ryerson Hill Solid Waste Disposal Site, 379 A.2d 384, 11 ERC 1042, 1977 Me. LEXIS 387 (Me. 1977).

Opinion

WERNICK, Justice.

In its “Findings of Fact and Order” dated November 12, 1975, the Maine Board of Environmental Protection approved, subject to specified conditions, the application of the Paris Utility District (hereinafter “Paris”) for permission to construct and operate a sludge disposal dump on Ryerson Hill in South Paris. Pursuant to the Site Location of Development Law, 38 M.R.S.A. § 487 (1973 Supp.), the Ryerson Hill Association (hereinafter “Ryerson”), an Intervenor organization of Ryerson Hill property owners, brought this direct appeal from the Order of the Board. The points on appeal are: (1) the Board unlawfully imposed conditions on the Order of approval; (2) applicant Paris failed to demonstrate compliance with each statutory criterion of § 484 of the State Location of Development Law, and (3) the Board relied upon incompetent and prejudicial evidence.

We deny the appeal.

In 1973, Paris first applied for a permit to construct and operate a public wastewater treatment plant to process industrial and domestic waste in South Paris. On September 26, 1973, the Board approved the construction and operation of the wastewater treatment plant but denied a proposal to use a site owned by the A. C. Lawrence Co. tannery for disposal of the sludge.

With the wastewater treatment plant already operational, Paris in 1975 submitted an application for permission to develop an alternative site on the side of Ryerson Hill for the sludge disposal dump. The proposed disposal site is a remote 52 acre area located on the north side of Ryerson Hill in South Paris. The wastewater treatment plant eventually is expected to produce a residue of 1600 cubic feet of sludge per day for deposit on the Ryerson Hill site. The project will be the first in Maine for the trenching of sludge in which there is chromium, from the waste of a local tannery. Even though the chromium will not be in actually soluble form, the Board was induced by the presence of chromium and its potential solubility, coupled with the high level of ground water in the area of the proposed site, to give the application close scrutiny and to impose the specific conditions upon the grant of approval stated in the Board’s Findings of Fact and Order.

Commonly associated with any land-fill project is the primary danger of a possible contamination of water either through surface water run-off carrying deposited pollutants or through leachate from waste filtering down through the soil and contaminating the ground water. Hence, here, as in any such land-fill project, the first step of the proposed project is drainage of the site’s ground water and interception and diversion of both surface and ground water around the site. Once the site is completely dry, the sludge is to be encapsulated in strip trenches dug in the impervious fragipan that exists on the site between the surface soils and bedrock. After deposit of the sludge, the trenches will be reforested, the untouched wooded strips will become new trench sites and the process will be repeated.

Although finding that the proposed disposal method “generally incorporates known technology”, the Board nevertheless imposed several express conditions upon its *387 grant of approval to the Ryerson Hill site because of the “untried nature of the proposal.” The specified conditions include construction of an all-weather section of the site, construction of a sedimentation-retention basin to collect surface run-off and effluent from the drainage system, development of an intensive monitoring program by the applicant Paris under close supervision of the Department of Environmental Protection, submission of a detailed erosion control and reforestation plan, and production of affirmative on-site evidence of ability to lower and maintain the water table at an acceptable level prior to placement of the sludge and installation of permanent peripheral drains to maintain that capacity over time.

I.

In addressing Ryerson’s first contention on appeal, that the Board acted unlawfully in imposing the above-described conditions upon the Order of approval, we commence with the Board’s statement in its findings that the “record is limited” in many areas and that the “untried nature of the proposal dictates that maximum caution be exercised.” Ryerson uses this statement as the basis of its contention that the Board acted unlawfully in imposing the above-described conditions. This shows, Ryerson argues, that the Board was aware that Paris, as an applicant, had failed to meet its burden of proof to come forward with a proposal adequately complying with the criteria requisite under § 484 of the Site Location of Development Law for the Board’s approval and that, instead of rejecting the Paris proposal as thus deficient, the Board improperly assumed the burden, through the imposition of conditions, of transforming a deficient application into an adequate one.

We disagree with Ryerson’s contention.

38 M.R.S.A. § 484 (1973 Supp.) expressly confers authority on the Board to approve an application

“upon such terms and conditions as the . [Board] may deem advisable to protect and preserve the environment and the public’s health, safety and general welfare.”

See also § 484. Recently, we made the point that careful use by the Board of this express authority to impose conditions can advance the general mandate in § 481 that the Board adopt a “flexible and practical” approach to site regulation. In re Belgrade Shores, Inc., Me., 371 A.2d 413 (1977).

Considering the specific conditions here imposed by the Board we conclude that the Board did not exceed, or abuse, its authority-

Most of the conditions merely require the development of new or more detailed plans designed to safeguard the environment. As to these, the short answer to Ryerson’s attack is, as we explained in In re Belgrade Shores, supra, that such conditional approval achieves the same effect as a series of disapprovals pending the correction of deficiencies in the proposal.

Others of the conditions, however, calling for development of an intensive monitoring program designed to provide assurance over the impact life of the project that reforestation is feasible and that all applicable water quality standards are met, 1 do go one step beyond those considered in Belgrade Shores. We reject Ryerson’s suggestion, however, that in imposing the long-range monitoring condition the Board supplied necessary matter to enable Paris, as the applicant, adequately to discharge its burden of proof which, absent the condition, would not have been met. In approving the application for the sludge disposal site, the Board heard an abundance of expert testimony in five days of public hearings, after which it specifically found that the proposal “generally incorporates known technology” and that the applicant “complied with the requirements of 38 M.R.S.A. § 481 et seq.” *388 The Board thus made clear that Paris had established justification for the Board to grant the application without imposition of the enumerated conditions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minot School Committee v. Minot Education Ass'n
1998 ME 211 (Supreme Judicial Court of Maine, 1998)
Maine Real Estate Commission v. Jones
670 A.2d 1385 (Supreme Judicial Court of Maine, 1996)
Mutton Hill Estates, Inc. v. Town of Oakland
488 A.2d 151 (Supreme Judicial Court of Maine, 1985)
Bolduc v. Androscoggin County Commissioners
485 A.2d 655 (Supreme Judicial Court of Maine, 1984)
Frye v. Inhabitants of Town of Cumberland
464 A.2d 195 (Supreme Judicial Court of Maine, 1983)
State v. Beck
389 A.2d 844 (Supreme Judicial Court of Maine, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
379 A.2d 384, 11 ERC 1042, 1977 Me. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-ryerson-hill-solid-waste-disposal-site-me-1977.