In Re Petition of Otter Creek Solar LLC

2025 VT 65
Supreme Court of Vermont·Decided December 12, 2025·No. 24-AP-374·Published

Opinion

NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal revision before publication in the Vermont Reports. Readers are requested to notify the Reporter of Decisions by email at: Reporter@vtcourts.gov or by mail at: Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made before this opinion goes to press.

2025 VT 65

No. 24-AP-374

In re Petition of Otter Creek Solar LLC Supreme Court

On Appeal from

Public Utility Commission

September Term, 2025

Edward McNamara, Chair Michael Melone, Allco Renewable Energy Inc., New Haven, Connecticut, for Appellant. Ben Civiletti, Special Counsel, Vermont Department of Public Service, Montpelier, for Appellee.

PRESENT: Reiber, C.J., Eaton, Cohen and Waples, JJ., and Zonay, Supr. J., Specially Assigned

¶ 1. EATON, J. Appellant, Otter Creek LLC, sought to construct a solar facility in Bennington, Vermont and applied to the Public Utility Commission for a Certificate of Public Good (CPG). The Commission denied the CPG, concluding that the proposed new plant together with an existing nearby solar facility constituted a single plant which exceeded the plant-capacity of the Standard Offer Program and was therefore ineligible for it. Otter Creek appeals, arguing that the Commission applied the wrong test to determine if its facility was a single plant, that the Commission should not have applied the single-plant test during the CPG determination, that the Commission’s decision violates its due process rights, and that it is entitled to a new hearing. We conclude that the Commission applied the correct standard and acted within its discretion in denying the CPG, and therefore affirm.

I. Legal Background

¶ 2. Some background on the applicable statutes is helpful to understanding the issues.

One of Vermont’s general policies is “[t]o ensure to the greatest extent practicable that Vermont can meet its energy service needs in a manner that is adequate, reliable, secure, and sustainable.” 30 V.S.A. § 202a. To achieve this, the Legislature has specific “[r]enewable energy goals” including “[p]roviding support and incentives to locate renewable energy plants of small and moderate size” across the state “including locating such plants in areas that will provide benefit to the operation and management of that grid through such means as reducing line losses and addressing transmission and distribution constraints.” Id. § 8001(a)(7).

¶ 3. The Standard Offer Program furthers this goal by requiring Vermont distribution utilities to buy renewable power from an eligible renewable-energy plant for a set price and amount of time. Id. § 8005a(f)(4), (e). To incentivize small- and moderate-size plants, the program is available to a renewable-energy plant only if it “has a plant capacity of 2.2 MW or less.” Id. § 8005a(b). The statute defines “plant” and lists factors relevant to whether a group of nearby facilities are part of the same plant for the purpose of the statute: common equipment and infrastructure, common ownership, contiguity in time of construction, and proximity of the facilities to each other. Id. § 8002(18).

¶ 4. If a new renewable energy facility submits a proposal for a standard-offer contract from the Commission and is awarded that contract, the facility must also apply for and receive a CPG from the Commission to begin construction. Id. § 248(a)(2)(A)-(B) (stating no company or person “may begin site preparation for or construction of an electric generation facility, energy storage facility, or electric transmission facility within the State that is designed for immediate or eventual operation at any voltage . . . unless the [Commission] first finds that the same will promote the general good of the State and issues a certificate to that effect”).

II. Facts and Procedural History

¶ 5. The following facts are undisputed unless otherwise noted. In 2016, the Commission issued requests for proposals (RFP) for the Standard-Offer Program based on its annual available capacity. See 30 V.S.A. § 8005a. Otter Creek, LLC submitted three project bids in response to the RFP solicitation. Those projects were originally named Battle Creek 1, Battle Creek 2, and Battle Creek 3. Each of the proposed projects would be located off Rice Lane in Bennington on adjacent parcels of land between Hardwood Hill Road and North Bennington Road. Battle Creek 1 was the western-most proposed project. At its closest point, Battle Creek 2 would be located 150 feet to the east of Battle Creek 1. Battle Creek 3 would be located to the north and east of Battle Creek 1 and 2, closer to Rice Lane. All facilities planned to interconnect to the grid on Rice Lane.

¶ 6. The Commission awarded Battle Creek 1 a standard-offer contract but did not offer a contract to the other two proposed facilities at that time. Otter Creek subsequently applied for and received a CPG for Battle Creek 1, then-renamed “Battle Creek Solar,” from the Commission pursuant to 30 V.S.A. § 248. To bring Battle Creek into operation, a number of upgrades were performed to allow it to safely connect to Green Mountain Power’s (GMP) distribution lines. This included the construction of a three-phase distribution line, funded by Battle Creek, that ran west from the Battle Creek Solar facility along Rice Road and ultimately to a GMP substation.1 Battle Creek Solar began operating in September 2019.

¶ 7. While Battle Creek was being constructed, Otter Creek re-submitted proposals for Battle Creek 2 and Battle Creek 3 in response to the Commission’s 2018 RFP solicitation. At that point, Battle Creek 2 and 3 had been renamed Warner Solar and Stark Solar. In total, the

1 Otter Creek disputes the Commission’s finding that Battle Creek funded the upgrade, arguing that it is entitled to a refund. We address that argument below. See infra, ¶ 30 n.4.

Commission received fourteen proposals in response to its 2018 RFP process and it selected four solar-facility proposals for standard-offer contracts. Warner Solar and Stark Solar were both awarded contracts. The Commission rejected the other proposals submitted for a variety of reasons. Relevant to this case, the Commission rejected a proposal for a dam facility because the Commission determined that it would be considered the “same plant” with a nearby existing dam and because, as a result, the combined energy production would exceed the 2.2 MW limit for a standard-offer contract. See 30 V.S.A. § 8005a (restricting standard-offer program eligibility to renewable energy plants with “a plant capacity of 2.2 MW or less”).

Free access — add to your briefcase to read the full text and ask questions with AI

In Re Petition of Otter Creek Solar LLC, 2025 VT 65 (Vt. 2025).

2025 VT 65 (In Re Petition of Otter Creek Solar LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Otter Creek Solar LLC v. Vermont Public Utility Commission
2026 VT 15 (Supreme Court of Vermont, 2026)
In Re Petition of Apple Hill Solar LLC
2026 VT 8 (Supreme Court of Vermont, 2026)