In re Packard Square LLC

574 B.R. 107, 2017 Bankr. LEXIS 3577
United States Bankruptcy Court, E.D. Michigan·Decided October 13, 2017·No. Case No. 17-52483·Published·Cited by 1 cases

Opinion

OPINION REGARDING DEBTOR’S POST-PETITION FINANCING MOTION

Thomas J. Tucker, United States Bankruptcy Judge

I. Introduction

This Chapter 11 case is before the Court on the Debtor’s motion under 11 U.S.C. §§ 364(c)(1) and 364(d) for approval of post-petition financing, filed September 5, 2017, entitled “First Day Emergency Motion of the Debtor for Entry of Interim and Final Orders (I) Authorizing Debtor to Obtain Post-Petition Financing, (II) Scheduling a Final Hearing, and (III) Granting Certain Related Relief’ (Docket # 13, the “Motion”). The Court held a preliminary hearing on the Motion on September 13, 2017. Several creditors filed objections to the Motion before the hearing, including several creditors claiming to have construction liens on the Debtor’s real property. Those objections were all styled as “limited” objections.1 The primary filed objection to the Motion is not limited in nature, but rather objects to the Motion on numerous grounds, including a lack of adequate protection. That is the objection filed by the Debtor’s pre-petition secured lender, CAN IV Packard Square LLC (“Canyon”).2

The Court held an evidentiary hearing on the Motion, limited to the issue of adequate protection as described below, on September 19 and 20, 2017, then took the matter under advisement. The Court has considered all of the evidence presented at the evidentiary hearing, and all of the arguments of the parties. This opinion states the Court’s findings of fact and conclusions of law regarding the Motion and the subject matter of the evidentiary hearing. For the reasons stated in this opinion, the Court will deny the Motion.

II. Jurisdiction

This Court has subject matter jurisdiction over this bankruptcy case and this contested matter under 28 U.S.C. §§ 1334(b), 157(a) and 157(b)(1), and Local Rule 83.50(a) (E.D. Mich.). This is a core proceeding under 28 U.S.C. §§ 157(b)(2)(D) and 157(b)(2)(0).

This proceeding also is “core” because it falls within the definition of a proceeding “arising under title 11” and of a proceeding “arising in” a case under title 11, within the meaning of 28 U.S.C. § 1334(b). Matters falling within either of these categories in § 1334(b) are deemed to be core proceedings. See Allard v. Coenen (In re Trans-Industries, Inc.), 419 B.R. 21, 27 (Bankr. E.D. Mich. 2009). This is a proceeding “arising under title 11” because it is “created or determined by á statutory provision of title 11,” see id., including Bankruptcy Code §§ 364 and 361. And this is a proceeding “arising in” a case under title 11, because it is a proceeding that “by [its] very nature, could arise only in bankruptcy cases.” See id. at 27.

III. Background

A. The Construction Loan

Pre-petition, in October 2014, the Debt- or obtained a construction loan from Canyon in the maximum principal amount of $53,783,184,00 (the “Construction Loan”) to finance the construction of “a 360,000 square foot mixed-use development [project] on a six and a half acre site on Packard Street in Ann Arbor, Michigan,” including “249 residential units with high-end amenities, nearly 30,000 square feet of retail space and over 450 parking space[s] including an underground parking garage” (the “Project”).3 The Debtor signed a promissory note, and other loan documents, and granted Canyon a mortgage on the real property of the Project “together with the related easements, privileges and licenses, and the buildings, structures, improvements, fixtures and personal property located [on it]” to secure the Debtor’s indebtedness for the Construction Loan.4 The Debtor also executed an assignment of leases and rents in favor of Canyon.5

B. The appointment of a receiver in the state court suit

On October 21, 2016, Canyon filed suit against the Debtor in Washtenaw County Circuit Court, in the case of CAN IV Packard Square LLC v. Packard Square, LLC, et al., Case No. 16-000990 CB (the “state court case”). In its verified complaint in the state court case, Canyon requested the appointment of a receiver over the property securing its debt, due to the Debtor’s alleged failure “to fulfill its obligations to complete construction of improvements for which funds were provided in accordance with the relevant loan agreements” and “to maintain the [property is a suitable condition,”6 Canyon also sought foreclosure of its mortgage in the state court complaint.7

Free access — add to your briefcase to read the full text and ask questions with AI

In re Packard Square LLC, 574 B.R. 107, 2017 Bankr. LEXIS 3577 (Mich. 2017).