In re Oil Spill by the Oil Rig "Deepwater Horizon"

77 F. Supp. 3d 500, 2015 WL 225421
CourtDistrict Court, E.D. Louisiana
DecidedJanuary 15, 2015
DocketNo. MDL 2179
StatusPublished
Cited by5 cases

This text of 77 F. Supp. 3d 500 (In re Oil Spill by the Oil Rig "Deepwater Horizon") is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Oil Spill by the Oil Rig "Deepwater Horizon", 77 F. Supp. 3d 500, 2015 WL 225421 (E.D. La. 2015).

Opinion

CARL BARBIER, District Judge.

Pursuant to Federal Rule of Civil Procedure 52(a), the Court enters these Findings of Fact and Conclusions of Law relative to the Phase Two trial. If any finding is in truth a conclusion of law or any conclusion stated is in truth a finding of fact, it shall be deemed so, labels notwithstanding.

CONTENTS

I. Introduction and Procedural History.502

II. Source Control Segment.504

A. Parties to the Source Control Segment.504

B. Stipulated Facts; Timeline of Source Control Events.504

i. Terms and Definitions.504

ii. Response Framework .507

iii. Events of April 20-April 30, 2010.508

iv. Events of May 1-May 30, 3010.510

v. Events of June 1-June 30, 2010 .512

vi. Events of July 1-July 31, 2010.>.513

vii. Events of August 1-August 31, 2010.515

viii. Events of September 1-September 19, 2010 .516

C. Findings on Disputed Issues.516

i. BP’s Oil Spill Response Plan.517

ii. BP’s Flow Rate Misrepresentations .518

D. Conclusions .520

III. Quantification Segment.521

IV. Summary.. • 525

I. Introduction and Procedural History

1. This multidistrict litigation arises from the April 20, 2010, blowout, explosions, fire, and subsequent oil spill involving the mobile offshore drilling unit DEEPWATER HORIZON (sometimes referred to as “HORIZON”) and the well, known as Macondo, it had drilled in the Gulf of Mexico approximately fifty miles from the Louisiana coast.

2. Presented here is an abridged version of the procedural history for this mul-tidistrict litigation. The reader is directed to the Findings of Fact and Conclusions of Law for the Phase One trial (“Phase One Findings”) for a more thorough account of the procedural history.1

[503]*5033. The Court has' held thus far two major trial proceedings. Further trials are planned, including, a “Penalty Phase” scheduled to begin on January 20, 2015.

4. The “Phase One” trial was held between February 25, 2013 and April 17, 2013 and consisted of twenty-nine trial days. It addressed fault determinations relating to the loss of well control, the ensuing explosion and fire, the sinking of the HORIZON, and the initiation of the release of oil. After the Phase One trial, the parties submitted memoranda, responses, and proposed findings of fact and conclusions of law.

5. A “Phase Two” trial was then held from September 30, 2013 to October 18, 2013 and consisted of twelve trial days. Phase Two was divided into two segments: “Source Control” and “Quantification.” Source Control concerned issues pertaining to the conduct or omissions relative to stopping the discharge of hydrocarbons. The Quantification segment addressed the amount of oil actually released into the Gulf of Mexico. As with the Phase One trial, the parties submitted post-trial mem-oranda, responses, and proposed findings of fact and conclusions of law.

6. On September 4, 2014, the Court issued the Phase' One Findings,2 which were revised slightly and re-issued on September 9, 2014.3 BP subsequently moved to amend the Phase One Findings or for a new trial, which the Court denied on November 13, 2014.4

7. The Phase One Findings made numerous factual and legal determinations, only a few of which are mentioned here.

8. With respect to the United States’ action for civil penalties under the Clean Water Act’s (“CWA”)5 against BP Exploration & Production, Inc. (“BPXP”),6 the Court found that the discharge of oil was the result of BPXP’s gross negligence and willful misconduct. Consequently, the Court concluded that BPXP was subject to a higher maximum penal amount than would apply in the absence of such conduct. However, the Court did not determine the actual penal amount in the Phase One Findings.

9. The Phase One Findings also made fault allocations under general maritime law. The Court attributed 67% of the fault for the blowout, explosion, and oil spill to two BP entities, BPXP and BP America Production Company (“BPAPC”). Transocean (meaning Transocean Holdings LLC, Transocean Deepwater Inc., and Transocean Offshore Deepwater Drilling Inc.) and Halliburton (meaning Halliburton Energy Service, Inc. and Halliburton’s Sperry division) bore 30% and 3% of the fault, respectively.

10. Athough the Phase One Findings found that certain BP employees acted recklessly, which would normally warrant punitive damages under general maritime law, the Court concluded that, under the circumstances, Fifth Circuit precedent barred the imposition of punitive damages against BPXP and BPAPC. The Phase One Findings found that Transocean’s and [504]*504Halliburton’s misconduct did not exceed ordinary negligence; thus, these parties also did not face punitive damages.

11. The Court turns now to the issues presented in the Phase Two trial.

II. Source Control Segment

A. Parties to the Source Control Segment

12. The Source Control segment was tried as a bench trial that began on September 30, 2013, and concluded on October 3, 2013. Participants were the “Aligned Parties” on one side and the BP entities on the other.

13. The Aligned Parties consisted of private plaintiffs and claimants-in-limitation (represented by the Plaintiffs’ Steering Committee or “PSC”), the States of Alabama and Louisiana, the Transocean entities (Transocean Offshore Deepwater Drilling Inc., Transocean Holdings LLC, Transocean Deepwater Inc., and Triton Asset Leasing GmbH), and Halliburton Energy Services, ínc.

14. The BP entities were BPXP, BPAPC, and BP p.l.c. (collectively “BP” for purposes of the Source Control segment).

B. Stipulated Facts; Timeline of Source Control Events

15. The parties to the Source Control segment stipulated to certain facts,7 providing a timeline of source control events. The Court has reproduced these stipulations in paragraphs 16 to 212, below.8

i. Terms and Definitions

16. BOEMRE — Bureau of Ocean Energy Management, Regulation and Enforcement. This term refers to the federal agency responsible for overseeing the development of energy and mineral resources on the Outer Continental Shelf. This agency was formerly known as Minerals Management Service and is now known as Bureau of Safety and Environmental Enforcement (BSEE) and Bureau of Ocean Energy Management (BOEM).

17. BOP — This term refers to the Blowout Preventer used in conjunction with the DEEPWATER HORIZON.

18. BOP-on-BOP — This term refers to a contemplated operation to place a second BOP on the DEEPWATER HORIZON BOP.

19. CDP — Containment and Disposal Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gulf Restoration Network v. Jewell
161 F. Supp. 3d 1119 (S.D. Alabama, 2016)
In re Oil Spill by the Oil Rig "Deepwater Horizon"
98 F. Supp. 3d 872 (E.D. Louisiana, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
77 F. Supp. 3d 500, 2015 WL 225421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-oil-spill-by-the-oil-rig-deepwater-horizon-laed-2015.