In re Northwest Airlines Corp.

393 B.R. 352, 67 U.C.C. Rep. Serv. 2d (West) 184, 2008 Bankr. LEXIS 2509
United States Bankruptcy Court, S.D. New York·Decided September 5, 2008·No. No. 05-17930 (ALG)·Published·Cited by 3 cases

Opinion

MEMORANDUM OF OPINION

ALLAN L. GROPPER, Bankruptcy Judge.

This is an objection by the above-captioned reorganized debtors (the “Debtors”) to proofs of claim (collectively, the “Claims”) filed by ALG DC-9 L.L.C. (“ALG”), as lessor of two McDonnell Douglas DC-9-32 aircraft (collectively, the “Aircraft”). The Claims arise in connection with the Debtors’ rejection of the leases. ALG claims damages of $7.5 million on each lease, relying for its calculation of damages on a liquidated damages clause that bases damages on a fixed Stipulated Loss Value (“SLV”) for the planes. The Debtors have objected to the Claims, and the issue before the Court is whether a damages clause based on a fixed and non-declining SLV is an enforceable liquidated damages provision or whether it is a penalty that is unenforceable under applicable law. For the reasons set forth below, the Court finds that the clause is unenforceable and sustains the Debtors’ objection.

Background

The Debtors first leased the Aircraft in 1987. In 1996, JetStream II, L.P. (“Jet-Stream”) became successor-in-interest to the first owner and executed new leases with one of the Debtors. The leases, dated September 1,1996 and August 21,1996, respectively (collectively, the “Leases”), provided for a $35,000 monthly rent and had an expiration date of January 31, 2007. It appears that at the time the new Leases were negotiated, the Aircraft had to be upgraded, and the parties agreed that the Debtors would perform this work, estimated to cost $2.95 million per plane. In return, the Leases contained the rent and term provisions set forth above and, ALG alleges, the following residual sharing provision: (1) at the expiration of the Leases the Debtors would receive one-half of the •value of each Aircraft or one-half of the proceeds of sale, less in each case amounts necessary to cure any default; or (2) if the Leases did not extend to their termination date, one-half SLV. SLV is a liquidated damages provision common in aircraft [355]*355leases that sets the amount for which the lessee must insure the plane and is also used to calculate damages after a default. See In re Delta Air Lines, 870 B.R. 552, 555 (Bankr.S.D.N.Y.2007); see also Mentor Ins. Co. (UK) Ltd. v. Brannkasse, 996 F.2d 506, 507 (2d Cir.1993); Interface-Group Nevada, Inc. v. Trans World Airlines, Inc. (In re TWA), 145 F.3d 124, 134 (3d Cir.1998); Atel Fin. Corp. v. Quaker Coal Co., 132 F.Supp.2d 1233, 1241 (N.D.Cal.2001); In re U.S. Airways, 2002 WL 31829093, at *5 (Bankr.E.D.Va. Dec. 16, 2002).1 Typically SLV declines over the course of the lease term, recognizing depreciation and the payment of rent over time. See, e.g., In re Grubbs Constr. Co., 319 B.R. 698, 708 (Bankr.M.D.Fla.2005). In this case, it is ALG’s contention (which the Debtors do not dispute) that the parties stipulated that SLV would not decline because a static value for the Aircraft of $7.3 million and a residual sharing provision, giving the Debtors half of this value, would permit the Debtors to recover their investment in the cost of the overhaul.2

ALG purchased the Aircraft and succeeded to JetStream’s interests under the Leases in April, 2000. On September 14, 2005, the Petition Date, the Debtors filed a motion to reject the Leases and abandon the Aircraft. On October 13, 2005, the Court entered an order granting the rejection motion, with an effective rejection date of October 7, 2005, and ALG took possession of the Aircraft. On June 16, 2006, ALG sold the Aircraft for an aggregate of $230,000, or $115,000 for each aircraft.

ALG filed proofs of claim, dated July 31, 2006. Each Claim was for $7,500,000, representing $7.3 million SLV, plus $315,000 in unpaid rent as of June 16, 2006 (the date of the foreclosure sale), less $115,000 in sale proceeds.3 The Debtors objected to ALG’s claim on the ground that the total amount payable on the Leases, if they had remained in effect for the remaining 16-Hi months of their term, was $1.36 million in face amount (not present-valued) and thus the damages claimed were an unenforceable penalty that was more than 10 times the amount they would have paid under the Leases if they had not been rejected. In the alternative, the Debtors contended that even if the damages clause is enforceable, ALG’s claims should be subordinated by the terms of the Debtors’ Plan of Reorganization because the damages claimed do not represent actual pecuniary loss. The Court held a hearing on the Objection on July 16, 2008. Neither party requested an evidentiary hearing, and the enforceability of a liquidated damages provision is ordinarily “a [356]*356legal issue not requiring an evidentiary showing.” Wells Fargo Bank Northwest, N.A. v. Taca Int’l Airlines, S.A., 315 F.Supp.2d 347, 350 (S.D.N.Y.2003).

Decision

The issue before the Court is whether the liquidated damages clauses in the Leases are enforceable. There is no dispute that this question should be decided by reference to Minnesota law, as the Leases provide that the law of Minnesota governs all matters of construction, validity, and performance. (Leases, § 22.5.) Moreover, both parties have cited and relied on general provisions of Minnesota law rather than cases under Article 2A of the Uniform Commercial Code, which applies to “any transaction ... that creates a lease.” Minn.Stat. Ann. § 336.2A-102. Minnesota has adopted Article 2A, but there do not appear to be any reported Minnesota decisions on the section on liquidated damages, and as will be seen below, this provision basically restates the law on liquidated damages in general terms. Minn.Stat. Ann. § 336.2A-504(1) simply provides that damages “may be liquidated in the lease agreement but only at an amount or by a formula that is reasonable in light of the then anticipated harm caused by the default or other act or omission.”

In the leading case on the issue of liquidated damages in Minnesota, the Minnesota Supreme Court held that a liquidated damages clause is enforceable when “(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and (b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.” Gorco Constr. Co. v. Stein, 256 Minn. 476, 482, 99 N.W.2d 69, 74-75 (1959). As the Minnesota Supreme Court held in that case, “the controlling factor, rather than intent, is whether the amount agreed upon is reasonable or unreasonable in the light of the contract as a whole, the nature of the damages contemplated, and the surrounding circumstances.” Id. See also Costello v. Johnson, 265 Minn. 204, 209-10, 121 N.W.2d 70, 75 (1963) (citing Gorco); Tenant Constr. Inc. v. Mason, 2008 WL 314515, at *5 (Minn.App. Feb. 5, 2008) (same); Bellboy Seafood Corp. v. Nathanson, 410 N.W.2d 349, 352 (Minn.App.1987) (same). In determining the fundamental issue of reasonableness, Minnesota presumes that a liquidated damages provision is valid unless the party disputing the clause rebuts the presumption. See, e.g., 606 Vandalia P’ship v. JLT Mobil Bldg. Ltd. P’ship, 2000 WL 462988, at *5 (Minn.App. Apr. 25, 2000).

In this case the Debtors have easily rebutted the presumption of validity.

Free access — add to your briefcase to read the full text and ask questions with AI

In re Northwest Airlines Corp., 393 B.R. 352, 67 U.C.C. Rep. Serv. 2d (West) 184, 2008 Bankr. LEXIS 2509 (N.Y. 2008).

393 B.R. 352 (In re Northwest Airlines Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Republic Airways Holdings Inc.
598 B.R. 118 (S.D. New York, 2019)
Dougan v. Dougan
970 A.2d 131 (Connecticut Appellate Court, 2009)