In Re Len Kelley Enterprises, Inc.

124 B.R. 352, 1991 Bankr. LEXIS 197, 1991 WL 22964
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedFebruary 4, 1991
DocketBankruptcy 88-1212-BKC-3P1
StatusPublished
Cited by1 cases

This text of 124 B.R. 352 (In Re Len Kelley Enterprises, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Len Kelley Enterprises, Inc., 124 B.R. 352, 1991 Bankr. LEXIS 197, 1991 WL 22964 (Fla. 1991).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

(DEBTOR’S OBJECTION TO CLAIM NUMBER 61).

GEORGE L. PROCTOR, Bankruptcy Judge.

Upon debtor’s objection to Claim Number 61 filed by John A. Marqua and Mary Jane Marqua (claimants) in the amount of $43,-038.63, the Court enters the following Findings of Fact and Conclusions of Law:

Findings of Fact

1. The grounds for objection are (1) the debt is not owed and (2) the claim was untimely filed. The claimants suggest that *353 the failure to file within the bar date limitations was due to the lack of notice.

2. The issues to be determined are (1) the amount of damages, if any; (2) justification shown by the claimants under Bankruptcy Rule 3003(c)(3) for an extension of time to file a proof of claim.

3. Claimants on October 1, 1987, contracted with the debtor to build a home according to drawings and specifications. The contract price was $112,000. Paragraph 8 reads as follows:

“No changes or additions to the plans and specifications, unless set forth in this agreement, are included in the price here-inabove, and no extra work or changes shall be made unless pursuant to a written order signed by the Buyer and accepted by the Seller.”

4. The debtor was paid $22,400 upon execution of the contract and construction began. During the period from November, 1987, through July, 1988, materials and labor were furnished. However, the debt- or seldom paid subcontractors, material-men, or laborers and used the downpayment for purposes other than the construction of the home.

5. The debtor and the claimants entered into an agreement on July 23, 1988, modifying the original contract to provide for a joint checking arrangement to pay for further materials and labor. The parties further acknowledged the filing of this Chapter 11 case. Paragraph 3 of the Modification Agreement is as follows:

“Both parties hereto agree that, prior to the issuance of the above referenced joint check, the debtor shall provide Mar-qua with invoices evidencing the exact amount of payment to be presented jointly to the debtor and the other person or entity entitled to the payment. Said joint check arrangements to insure Marqua that all materialmen, suppliers, laborers, sub-contractors, sub-contractors, (sic) or any other persons who have provided any services whatsoever and thus afforded any right to file a lien against the subject property shall be paid in full.”

6. The debtor then proceeded to construct the home pursuant to the contract and Modification Agreement. During the course of construction two change orders were submitted to claimants. Change Order No. 1 was signed by claimants on December 14, 1987, authorizing the debtor to charge an additional $150.00 for smoothing walls and an additional $292.00 for changing the fireplace. The change order also authorized the deductions of $2,100.00 for credit of cabinet costs and $80.00 for balance of credit on prints from the contract price.

7.Claimants authorized a second change order on June 26,1988, and it added $1,831.55 to the contract price for pouring concrete under the wood floor.

The contract price after accounting for the two change orders is as follows:
Original Contract Price $112,000.00
Total Credits Change Order 1 — 2,180.00
Total Additions Change Order 1 + 342.00
Total Additions Change Order 2 + 1,831.55
Total Contract Price w/Change Orders $111,993.55

8. Construction on the home ceased in early 1989. The home was substantially complete, however, various contract items needed to be finished. By letter dated August 15, 1989, the debtor credited claimants $5,000.00 for window credit (less expensive windows were used), $150.00 for Landscape Allowance and $980.00 for Sod Allowance (claimants paid for landscaping and laying of sod). Accordingly, $6,130.00 was to be deducted from the contract price.

9. The total contract price for the home, as substantially completed, is as follows:

Total Contract Price w/change order $111,993.55
Less Pool Credit — 15,000.00
Less August 15, 1989, credit — 6,130.00
Total Contract Price as Built $ 90,863.55

10.The debtor provided invoices showing the total amount of payments made under the Modification Agreement and after the debtor filed for protection under Chapter 11 of the Bankruptcy Code. Since July 23, 1988, $97,058.06 in bills were paid by claimants. Accordingly, the total amount paid by claimants is as follows:

Initial Deposit $ 22,400.00
Total Bills Paid 97,058.06
Total Paid by Claimants $119,458.06

*354 11.The total cost of the home to claimants is greater than the total adjusted contract price as built, resulting in a substantial overpayment:

Total Paid by Claimants $119,458.06
Total Contract Price as Built 90,863.55
Overpayment 28,594.51

12.The home as substantially completed differs from the home proposed to be constructed under the contract. There are a number of items that were to be completed or incorporated into the construction that the debtor failed to provide:

2 fiberglass double front doors 478.00
1 steel rear door 215.00
1 door to garage 345.00
Concrete deck under porch 727.00
Impact fee, included in contract 1,079.00
Mica countertop 356.16
Kitchen vinyl flooring 155.88
3 bathroom floors ceramic tile 486.00
Foyer ceramic tile 567.00
3 bathroom walls ceramic tile 639.00
Ceilings over bathtub 250.00
3 rooms carpet credit 2,774.00
Hard board under floors 590.00
Total Items Missing $ 8,662.04

13.The Court finds that overpayment of the contract price, together with the total amount for items missing under the contract, constitutes claimants’ damages.

Overpayment $ 28,594.51
Total amount for items missing 8,662.04
Total damages $ 37,256.55

14. The debtor argues that extra work was performed and was not included in either the original contract, the Modification Agreement, or the Change Orders, suggesting that the Court make an appropriate adjustment.

15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
124 B.R. 352, 1991 Bankr. LEXIS 197, 1991 WL 22964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-len-kelley-enterprises-inc-flmb-1991.