In Re Jay Forni, Inc.
This text of 33 B.R. 538 (In Re Jay Forni, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
In re JAY FORNI, INC., Debtor.
L.B. FOSTER CO., Plaintiff and Counter-Defendant,
v.
JAY FORNI, INC., Defendant and Counter-Claimant.
United States Bankruptcy Court, N.D. California.
*539 John T. Hansen, Richard M. Kaplan, San Francisco, Cal., for L.B. Foster Co.
Irving J. Kornfield, Oakland, Cal., for Jay Forni, Inc.
DECISION
CAMERON W. WOLFE, Bankruptcy Judge.
This action is a complaint and counter-claim for declaratory and injunctive relief regarding the plaintiff's right to perfect and enforce claims against contractors' payment bonds for three public works projects in which debtor JAY FORNI, INC. fabricated construction materials from steel pipe it purchased from plaintiff L.B. FOSTER CO. The projects are: 1) COLUSA COUNTY WATER DISTRICT, Arbuckle, California; 2) LAKE TYEE PROJECT, Ketchican, Alaska; and 3) BURCH LAKE WATER TREATMENT PLANT, Longmont, Colorado.
FINDINGS OF FACT
Debtor filed its petition for relief under Chapter 11 of title 11 U.S.C. on June 3, 1982.
COLUSA PROJECT
On March 18, 1982, FOSTER delivered materials with a value of $3,408.31 to FORNI. FORNI fabricated those materials to the specifications of the COLUSA project. FOSTER gave a preliminary notice of its claim to KAWEAH CONSTRUCTION CO., a subcontractor of W.M. LYLES & CO. (the general contractor) on March 16, 1982.
LAKE TYEE PROJECT
On May 10, 1982, FOSTER delivered materials with a value of $1,504.90 to FORNI. FORNI fabricated those materials to the specifications of the LAKE TYEE project. FOSTER gave a preliminary notice of its claim to HANNISON WESTERN, a subcontractor of MORRISON KNUDSEN (the general contractor) on June 7, 1982.
BURCH PROJECT
On May 25, 1982, FOSTER delivered materials with a value of $1,989.56 to FORNI and on June 2, 1982, FOSTER delivered additional materials with a value of $7,869.05. FORNI fabricated those materials to the specifications of the BURCH LAKE project. FOSTER gave a preliminary notice of its claim on June 7, 1982, to the CITY OF LONGMONT, the contracting body, and WESTERN EMPIRE CONSTRUCTION, the general contractor.
APPLICABLE LAW
The COLUSA project is governed by THE MILLER ACT, 40 U.S.C. § 270a et seq.; the TYEE project is governed by ALASKA LAW, A.S. § 36.25.010 et seq.; and the BURCH project is governed by COLORADO LAW, C.R.S. § 38-26-105 et seq.
*540 CONCLUSIONS OF LAW
FORNI's extensive alteration of the pipe supplied by FOSTER to the specifications of the construction projects indicate its status as a subcontractor rather than a mere supplier of materials.
FORNI's work was done under the specifications of detailed contracts supplemented by plans and blue prints. The final products were in each case custom-made for the particular job complying with specifications for that job only. Further, in each case the price to the contractor with whom FORNI contracted was approximately ten times the cost of the pipe, the labor being the primary factor in this increase. For example, the pipes obtained from FOSTER were cut, bent, lined, welded, fitted with flanges, etc., and became part of an entire specific portion of the general construction job. Although the TYEE project did not include plans and specifications, there was a blue print and a special fitting was made up with two flanges. See U.S. etc. v. Morrison Knudsen Co., Inc., 687 F.2d 129, 134-136 (6th Cir.1982). Consequently, FOSTER has a right of action against the Contractor's Payment Bond under Federal, Alaska and Colorado Law provided proper notice was given.
COLUSA and TYEE PROJECTS
Since Alaska law is directly patterned on Federal law and has almost identical provisions, the COLUSA and TYEE projects will be considered concurrently.
Federal and Alaska law permit a materialman a right of action on a contractor's payment bond even if the materialman has no direct contractual relationship with the contractor, if the materialman has a contractual relationship with a subcontractor and the materialman gives notice to the contractor within ninety (90) days from the last date on which the material is furnished, 40 U.S.C. § 270b(a), A.S. § 36.25.020(b). Suits on contractors' payment bonds must be brought within one year of when the material was supplied, 40 U.S.C. § 270b(b), A.S. § 36.25.020(c).
FOSTER complied with the notice requirements of Federal and Alaska law by giving a preliminary notice in each project within ninety (90) days of the delivery of the pipe to FORNI. FORNI is estopped from challenging the validity of the notice despite the fact that it was given to a subcontractor rather than the contractor since FOSTER gave notice based on information given it by FORNI. FORNI has not challenged the sufficiency of the form of notice. However, FOSTER has not yet complied with the requirements of 40 U.S.C. § 270b(b) or A.S. 36.25.020(c) since it has not brought an action on its claim, believing it is stayed by 11 U.S.C. § 362.
BURCH LAKE
Colorado provides two alternatives for unpaid materialmen. Contractors on public works projects are required to post payment bonds for labor and material. Materialmen have a right of action on the bond if it is brought within six months after the materials are supplied C.R.S. XX-XX-XXX(1). However, C.R.S. XX-XX-XXX(3) provides that materialmen may bring an action against the surety within ninety (90) days following the date fixed for final settlement as published. To the extent that sections 38-26-105 and 38-26-107(3) are irreconcilable, section 38-26-107(3), adopted subsequent to section 38-26-105 and containing specific time requirements controls, Rocky Mountain Association of Credit Management v. Marshall, 44 Colo.App. 467, 615 P.2d 68 (1980).
Alternatively, materialmen may file a claim with the contracting body for material supplied a subcontractor, C.R.S. XX-XX-XXX(1). The contracting body is then required to withhold payment to the contractor in an amount equal to the claim until the claim is paid or withdrawn. However, the funds may only be held ninety (90) days following the date fixed for final settlement as published unless an action has been commenced by the claimant to enforce the unpaid claim and it has filed a lis pendens with the contracting body C.R.S. XX-XX-XXX(2).
*541 FOSTER complied with requirements of C.R.S. XX-XX-XXX(2) by filing its claim with the contracting body, the CITY OF LONGMONT, within ninety (90) days of supplying the materials. However, it has not yet complied with C.R.S. XX-XX-XXX(1) or XX-XX-XXX(3) since it has not brought an action on its claim, believing it is stayed by 11 U.S.C. § 362.
EFFECT OF 11 U.S.C.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
33 B.R. 538, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-jay-forni-inc-canb-1983.