In Re Jandous Electric Construction Corp.

96 B.R. 462, 1989 Bankr. LEXIS 288, 1989 WL 18867
CourtUnited States Bankruptcy Court, S.D. New York
DecidedMarch 6, 1989
Docket19-22310
StatusPublished
Cited by9 cases

This text of 96 B.R. 462 (In Re Jandous Electric Construction Corp.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Jandous Electric Construction Corp., 96 B.R. 462, 1989 Bankr. LEXIS 288, 1989 WL 18867 (N.Y. 1989).

Opinion

DECISION ON ORDER TO SHOW CAUSE FOR ORDER DIRECTING ABANDONMENT OF MATERIALS AND TO MODIFY AUTOMATIC STAY

HOWARD SCHWARTZBERG, Bankruptcy Judge.

Slattery Associates, Inc. (“Slattery”), a general unsecured creditor of the Chapter 11 debtor, Jandous Electric Construction Corp. (“Jandous”), seeks an order pursuant to 11 U.S.C. § 554(b) directing Jandous to abandon to Slattery certain customized materials that were procured by Jandous as a subcontractor for use in a New York City Transit Authority project where Slattery is the general contractor. Some of the fabricated materials were paid for by the debtor whereas approximately $636,890.34 is owed by the debtor to the suppliers of these materials. Slattery offers to pay the suppliers the balance owed for the materials *463 and to apply the amounts so paid as re-coupment against any claims by the debtor against Slattery for work performed or materials supplied for the project.

The debtor, Jandous, opposes Slattery’s motion for an abandonment of the materials to Slattery and maintains that the materials are not valueless to it or a burden to the estate, especially since the debtor is entitled to receive from Slattery a profit on the materials over and above the cost of purchase. Moreover, The Union Trust Co., a creditor claiming a secured interest in the debtor’s inventory, objects to the abandonment of any materials belonging to this estate and notes that Slattery has not given notice of its abandonment motion to other creditors of this estate who might have an interest in the property sought to be abandoned. Had the debtor sought to abandon the property, it would have been required to give notice to all creditors of the proposed abandonment, as required by Bankruptcy Rule 6007(a).

FINDINGS OF FACT

1. On or about August 29, 1986, Slat-tery entered into a contract with the Transit Authority to provide approximately $50,-000,000 of permanent rehabilitations, renovations and improvements to the Prospect Avenue Line which included installing new signal equipment, rewiring, new lighting, conduits and electrical distribution to 26 stations on over one mile of Transit Authority track. The Project also included rehabilitation of three sump rooms and pumping systems in the East River tunnels.

2. On or about November 18,1986, Slat-tery entered into a subcontract with Jan-dous to provide the electrical work required to complete the Project (the “Subcontract”). The Subcontract provided that Jandous complete all the specified work for $13,000,000 in accordance with terms of the Subcontract and the Transit Authority’s specifications.

3. On or about January 27, 1987, Jan-dous began its subcontract work for the Project. Pursuant to the terms of the Subcontract, Jandous attempted to obtain specially fabricated materials and equipment that are to be permanently installed in the Project. For some of these materials, Jan-dous had to prepare detailed shop drawings, submit them for approval and then have them fabricated. Typical of such materials and equipment were the two massive switching gears that were necessary for the new pumping systems as well as the extensive necessary appurtenances to operate those gears (the “Switching Gears and Appurtenances”). These switching gears cost approximately $275,000 each and were specifically designed for the Project by Westinghouse Electric Supply Company (“WESCO”) and took several months to fabricate. Similarly, much of the other material and equipment took lengthy periods to obtain because of design, approval and manufacturing requirements.

4. On December 1, 1988, Jandous. filed with this court its petition for Chapter 11 relief under the Bankruptcy Code. Jan-dous continued in possession of its property and continued to manage its business as a debtor in possession in accordance with 11 U.S.C. §§ 1107 and 1108.

5. There is no question that all of the equipment sought by Slattery for its New York Transit project, except for certain “catalogue” items, were specifically customized and fabricated for this job and are not readily usable elsewhere. Most of the equipment is in the possession of the debt- or, although some items are held by vendors. The debtor has installed materials at the job site for which there remains an unpaid balance of approximately $636,-890.39. Slattery reasons that the debtor’s nonpayment for materials installed at the job site constitutes a breach of its subcontract, which requires Slattery to execute a payment bond which guarantees payment to persons furnishing labor or materials to the project, thereby increasing Slattery’s claim against the debtor. Additionally, the debtor has, on hand or in stock, specifically fabricated materials and equipment invoiced at approximately $137,000 which has not been paid to the vendors of these items.

*464 6. At a meeting held on December 7, 1988, the debtor informed Slattery that it did not have sufficient financial resources to continue with the Slattery subcontract and that a source of additional financing had to be found to the extent of an additional one and one-half million dollars. Jandous also informed Slattery that the cost to complete the job exceeds Jandous’ contract price by $4.3 million.

7. During Jandous’ performance under the Subcontract, and as an accommodation to Jandous, Slattery executed a guarantee of payment to WESCO securing them for payment of the Switching Gears and Appurtenances. Jandous has received and installed the Switching Gears but has not paid for one switching gear and the Appurtenances despite its Payment Certifications. Slattery argues that it has a pressing need for these materials and is left in the impossible situation of either (a) reordering the Appurtenances, which would take many months and cause unacceptable delay, or (b) paying Jandous’ estate for the Appurtenances but having no assurance that Jandous will use the money to pay WESCO thereby requiring Slattery to also pay on the guarantee.

8. At another meeting between the parties held on December 19, 1989, the debtor, Jandous, objected to the fact that Slattery had received progress payments from the New York City Transit Authority but that Slattery would not make any payments to Jandous for work performed by Jandous in October of 1988 because of the debtor’s financial inability to complete its subcontract work for the project.

DISCUSSION

The basic issue for determination is whether or not a general unsecured creditor, who has neither a possessory nor a secured interest in specific property purchased by a debtor as a subcontractor at a particular project, may compel the debtor to abandon customized property to the creditor who has need for the property in conjunction with the creditor’s obligation as the general contractor for the project. The concept of abandonment is governed by 11 U.S.C. § 554. If the debtor or a trustee seeks abandonment of property of the estate that is burdensome or of inconsequential value and benefit to the estate, resort must be had to 11 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rajesh C Patel
N.D. Georgia, 2019
In re Mejia
576 B.R. 464 (S.D. New York, 2017)
Failla v. Citibank, N.A.
542 B.R. 606 (S.D. Florida, 2015)
In re Jimenez
492 B.R. 373 (S.D. New York, 2013)
In Re Renaissance Stone Works, L.L.C.
373 B.R. 817 (E.D. Michigan, 2007)
In Re Kasper
309 B.R. 82 (District of Columbia, 2004)
In Re Manchester Heights Associates, L.P.
165 B.R. 42 (W.D. Missouri, 1994)
Matter of Popp
166 B.R. 697 (D. Nebraska, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
96 B.R. 462, 1989 Bankr. LEXIS 288, 1989 WL 18867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-jandous-electric-construction-corp-nysb-1989.