In Re Establishing Certain Territorial Electric Boundaries Within the State of South Dakota

318 N.W.2d 118, 1982 S.D. LEXIS 290
CourtSouth Dakota Supreme Court
DecidedApril 7, 1982
Docket13506, 13508
StatusPublished
Cited by19 cases

This text of 318 N.W.2d 118 (In Re Establishing Certain Territorial Electric Boundaries Within the State of South Dakota) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Establishing Certain Territorial Electric Boundaries Within the State of South Dakota, 318 N.W.2d 118, 1982 S.D. LEXIS 290 (S.D. 1982).

Opinion

DUNN, Justice.

This case involves the establishment of territorial boundaries for electric utilities in the Aberdeen vicinity. It is before us on appeal for the second time, and we refer to our prior decision for a further statement of the facts. See Matter of Certain Territorial Elec. Boundaries, Etc., 281 N.W.2d 72 (S.D.1979), hereinafter cited as Aberdeen Vicinity-

In Aberdeen Vicinity, we determined that the electric lines in the entire disputed area were intertwined. We remanded the matter, therefore, to the Public Utilities Commission (PUC) to determine service area boundaries in accordance with our decision and the statutory guidelines set forth in SDCL 49-34A-^4.

On May 15, 1980, the PUC made assignments of territory to Northwestern Public Service Company (NWPS) and Northern Electric Cooperative, Inc. (NEC) without receiving additional testimony. The PUC assigned approximately 29¾⅛ square miles of the disputed territory to NEC and 20½ square miles to NWPS, based on the June 22,1976 recommendations of Willis Jongeri-us, a consultant engineer from Rock Rapids, Iowa. NWPS appealed to circuit court from the decision and order of the PUC. NEC requested a rehearing with the PUC, which request was denied. NEC then appealed to circuit court. These appeals were consolidated and the circuit court affirmed the decision of the PUC. NWPS (# 13506) and NEC (# 13508) appeal separately from the order of the circuit court. We affirm.

NEC contends that the appeal of NWPS should be dismissed as untimely because it was not from a final agency decision. We disagree. The PUC entered its decision and order on May 15,1980. Thirty days later NWPS filed a notice of appeal to the Sixth Judicial Circuit and on the same day NEC filed an application for rehearing with the PUC. Five days later the PUC denied the request for rehearing and NEC subsequently filed a notice of appeal to the Fifth Judicial Circuit. NEC claims that the agency decision was not final until its request for rehearing was denied.

In part, SDCL 1-26-30 provides:

*120 A person who has exhausted all administrative remedies available within any agency or a party who is aggrieved by a final decision in a contested case is entitled to judicial review under this chapter. If a rehearing is authorized by law or administrative rule, failure to request a rehearing will not be considered a failure to exhaust all administrative remedies and will not prevent an otherwise final decision from becoming final for purposes of such judicial review.

Under this statute, NWPS’s notice of appeal was filed in a timely manner within thirty days after the PUC entered its decision and order. It was not necessary for NWPS to request a rehearing for the purpose of exhausting all administrative remedies, because under the statute the failure to request a rehearing does not prevent an otherwise final decision from becoming final for purposes of judicial review. NWPS filed its notice of appeal on the same day that NEC filed its application for rehearing with the PUC. Since the application for rehearing was not pending at the time NWPS filed its notice of appeal, we find that the appeal by NWPS was filed in a timely manner.

The United States Supreme Court in American Farm Lines v. Black Ball, 397 U.S. 532, 90 S.Ct. 1288, 25 L.Ed.2d 547 (1970), was confronted with a similar situation, wherein the Interstate Commerce Commission (ICC) granted an application to provide temporary operating authority to a single-line motor carrier service. Petitions for reconsideration were filed and before they were passed upon, some carriers filed suit. The rehearing was subsequently granted. In determining whether the ICC had the power to grant a rehearing while the matter was pending before the District Court, the Supreme Court noted that in multi-party proceedings some of the parties may seek judicial review and others may seek administrative reconsideration. “The concept ‘of an indivisible jurisdiction which must be all in one tribunal or all in the other may fit’ some statutory schemes, ibid., but it does not fit this one.” 397 U.S. at 541, 90 S.Ct. at 1293-94, 25 L.Ed.2d at 554. See also United States v. Benmar Transp. & Leas. Corp., 444 U.S. 4, 100 S.Ct. 16, 62 L.Ed.2d 5 (1979). Our statutory scheme leaves it to each litigant’s choice to determine whether they will seek judicial review under SDCL 1-26-30.2 or administrative reconsideration under SDCL 49-34A-61.1 of a final agency decision. If the petition for rehearing is granted, judicial review may be deferred until the petition has been acted upon, B. J. McAdams, Inc. v. I.C.C., 551 F.2d 1112 (8th Cir. 1977); Outland v. C.A.B., 284 F.2d 224 (D.C.Cir.1960), or the appeal may be remanded to the agency, Anchor Line Limited v. Federal Maritime Commission, 299 F.2d 124 (D.C.Cir.1962), cert. denied, 370 U.S. 922, 82 S.Ct. 1563, 8 L.Ed.2d 503 (1962).

NEC contends that the trial court erred in denying its affidavit for change of judge. The affidavit alleged that NEC could not have a fair and impartial determination of its appeal before Judge Miller. Under SDCL 15-12-22, a judge may be disqualified if a party to an action files a timely affidavit. The right to change a judge, however, is subject to SDCL 15-12-24, which provides:

The submission to a judge or magistrate of argument or proof in support of a motion or application, or upon trial, is a waiver of the right thereafter to file an affidavit for change of such judge or magistrate by any party or his counsel who submitted the same or who after notice that such matter was to be presented, failed to appear at the hearing or trial. Such waiver shall continue until the final determination of the action and includes all subsequent motions, hearings, proceedings, trials, new trials, and all proceedings to enforce, amend or vacate any order or judgment.

The matter presently before Judge Miller was the continuation of the litigation previously before him in 1977 and this court on appeal in Aberdeen Vicinity, supra. Our prior decision in this matter remanded the case to the PUC for assignment of the disputed areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Hirning
944 N.W.2d 537 (South Dakota Supreme Court, 2020)
Wuest v. Winner School District 59-2
2000 SD 42 (South Dakota Supreme Court, 2000)
Loewen v. Hyman Freightways, Inc.
1997 SD 2 (South Dakota Supreme Court, 1997)
Hanten v. Palace Builders, Inc.
1997 SD 3 (South Dakota Supreme Court, 1997)
Helms v. Lynn's, Inc.
1996 SD 8 (South Dakota Supreme Court, 1996)
Hickmann v. Ray
519 N.W.2d 79 (South Dakota Supreme Court, 1994)
Fullmer v. State Farm Insurance Co.
514 N.W.2d 861 (South Dakota Supreme Court, 1994)
State v. Lohnes
432 N.W.2d 77 (South Dakota Supreme Court, 1988)
Petition of Famous Brands, Inc.
347 N.W.2d 882 (South Dakota Supreme Court, 1984)
Application of Southern Hills Bank of Edgemont
339 N.W.2d 310 (South Dakota Supreme Court, 1983)
Application of Northern States Power Co.
328 N.W.2d 852 (South Dakota Supreme Court, 1983)
Driscoll v. Great Plains Marketing Co.
322 N.W.2d 478 (South Dakota Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
318 N.W.2d 118, 1982 S.D. LEXIS 290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-establishing-certain-territorial-electric-boundaries-within-the-state-sd-1982.